XXbridge
Lightingconstructionscheme
Review:
Approval:
XXXbridgeprojectmanagementdepartment
May10th,2013
catalogue
1.Compilationbasis:2
2.ProjectOverview2
3,themainquantitiesof2...4,ofvariousconstructionmanagementobjectives3...
4.1Qualityobjectives3
4.2Timelimitforaprojecttarget3...4.3Safetyproductiontarget3...
4.4civilizedconstructiontarget3...4.5linkprotectiontarget...5,ConstructionOrganizationandManagementOrganizationandGuaranteeMeasures4...
5.1ofconstructionorganizationandinvestmentpersonnel4...
5.2Tableofmajorconstructionmachineryandequipmentinvestedin5..
5.3ofinvestedmeasuringinstrumentsandmeters5...
5.4oflaborprotectionmaterialsandsafetyfacilitiesinvested6..
6.Constructionschemeandmethod7...
6.1Constructionschemeandmethodofstreetlampfoundationproject7..
6.2PipelineEmbeddedConstructionScheme7...
6.3Cablelayingconstructionscheme7...
7.Theconstructionsequenceofeachsub-projectis1..1.
7.1Streetlampfoundationsub-project1..1.
7.2Cablelaying1..2..
7.3Streetlampinstallation1..2..
7.4Anti-theftmeasuresInstallationofdistributionbox1..2.8,TechnicalMeasurestoEnsuretheQualityofLightingEngineering1..3.
8.1Mainmeasuresofqualitycontrol:1.3.
8.2Qualityinspection:1..3.
8.3Qualityevaluation:1.4.
8.4Constructionqualityassurancemeasures1.4.
9,civilizedconstructionoperationplan,safetyproductionandenvironmentalprotectionmeasures2..2
9.1civilizedconstructionoperationplan2..2.
9.2Safetyproductionmeasures2.5.
9.3Environmentalprotectionmeasures3.2..
-1-
ConstructionschemeofXXXbridgelightingproject
1.Compilationbasis
1,"XXXBridgeProject"constructiondrawings;
2.Overallconstructiondeploymentandtimelimitplan;
3.DesignStandardofUrbanRoadLightingCJJ45-2006
4.CodeforConstructionandAcceptanceofLow-voltageElectricalApparatusinElectricalInstallationEngineeringX(GB50254-96)
5.CodeforConstructionandAcceptanceofCableLinesinElectricalEquipmentInstallationProjectX(GB50168-92)
6.CodeforConstructionandAcceptanceofGroundingDeviceinElectricalDeviceInstallationProjectX(GB50169-92)
7.CodeforConstructionandAcceptanceofOverheadPowerLinesof35KVandBelowinElectricalEquipmentInstallationProjectX(GB50173-92)
8.CodeforConstructionandAcceptanceofUrbanRoadLightingEngineering(CJJ89-2001).
2.Projectoverview
TheconstructionareaoftheprojectislocatedinXXXBridgeProjectinXXProvince,withastartingandendingmileageofK0+113~K0+363,includingXXX.
Leftandrightsidesofthebridge.
XXXbridgespantypeis(65+110+65)mthree-spanprestressedconcretecontinuousboxgirder;TheroadgradeisGradeII.
Highway(whichisalsoaclassIItrunkroadinthecity).Thetotallengthofthebridgeis250m,andthewidthofthebridgedeckis2×(3.5(sidewalk)+0.5(A
Full)+3×3.5(carriageway)+0.5(safetybelt)+0.5(crashbarrier))+0.5=24.5m,includingthesouthbankconnection.
Civilengineering,trafficengineering,lightingengineering,etc.attheintersectionoftheline.
Thedesignspeedofhighwayengineeringinthisbidsectionis40km/h,andthebaseperiodofstructuraldesignis100years.Typeselectionoflampsandlanterns
Single-armstreetlamp,thepoleheightis10m,andtheboomlengthis2m.
Theincomingpowersupplyofthisprojectisprovidedbytheowner,andthepowersupplyisintheformof380Vvoltagenearby.Thestreetlampcontrolboxislocatedin
ProvincialHighwayNo.304attheabutment.TN-Sgroundingprotectionsystemisadoptedforlow-voltagepowerdistribution,andstreetlamptransformerandcontroldistributionboxareintegrated.
Type.
3.Mainquantities
Name,specification,unitquantityremarks
1-armstreetlamp
H=10MIP65NG250boom:2m
Elevation:12degrees
Tai18
2OutdoorlightingcontrolboxKTJSQ-30/3.3-A-Iset1
2
3Low-voltagecableYJV-0.6/1kV-5*6m545
4GalvanizedsteelpipeG50m520
5GalvanizedsteelpipeG100m30
6handholewell90cm*120cmmouth1
7StreetlampfoundationVV-1kv4*2518
8galvanizedflatsteel-50*5m20
9AnglesteelartificialgroundingelectrodesL50*50*25004
10
Outdoorlightingcontrolboxbase
seat
40*800*11201
4,theconstructionmanagementobjectives
4.1Qualityobjectives
Projectqualityobjective:toreachthequalifiedstandardintheStandardforQualityInspectionandEvaluationofHighwayEngineering(JTGF80-2004)
Accurate,andthecomprehensivescoreofnotlessthan95points.
4.2Timelimitforaprojectobjectives
TheplannedcommencementdateofthisprojectisApril1,2014,andtheplannedcompletiondateisMay31,2014,withatotaldurationof61.
God.
4.3safetyproductionobjectives
Thesafetyproductiongoalofthisprojectis:nomajorcasualtyaccidents,accidentinjuryratecontrolledbelow0.06%,andnoweight.
Equipment,fire,pipeline,trafficandotheraccidents.
4.4civilizedconstructiongoal
Thecivilizedconstructionmanagementobjectivesofthisproject:donotcauseallkindsofenvironmentalpollutionaccidents,andputanendtoriverpollutionincidents;strict
Followthe"ImplementationMeasuresforConstructionSiteManagementofConstructionProjectsinXXProvince".
4.5Linkprotectionobjectives
Theenvironmentalprotectionoftheconstructionsiteofthisprojectshoulddothefollowingwork:controlthedischargeofproductionanddomesticwaterintheconstructionsite;
Strengthenthemanagementofconstructionmachinery,improveconstructiontechnologyandreducenoise;Wasteasphaltconcretematerialswillbepileduptothedesignatedplace.
three
Location,handledbyaqualifiedenterprise;Strengthenpipelineprotectiontopreventpipelineaccidents;Implementthedangerousgoodsscene.
Control,typhoonpreventionandfloodcontrol,fireemergencycontrol,etc.Ensurenopollutiontothesurroundingenvironmentduringtheconstructionprocess,indeed
Nocomplaintsfromresidentsormanufacturers.
5,theconstructionorganizationandmanagementinstitutionsandguaranteemeasures
5.1Constructionorganizationandinvestmentpersonnel
Theprojectintendstosetuptheprojectmanager,deputyprojectmanagerandchiefengineertoformtheprojectintendstoleadtheteam.under
Setupengineeringdepartment,qualityinspectionandsafetydepartment,materialsandequipmentdepartment,laboratory,planningandcontractdepartment,eachdepartmentconsistsof
Constructionteam,formingthewholeprojectintendsto.
Projectmanager:XX
DeputyProjectManager:XXProjectChiefEngineer:XX
LaboratoryofQualityInspectionDepartmentofEngineeringDepartment:PlanningMachineryOffice:
Contractministryofmaterialsandequipment
XXXXXXXXXXXXXX
Investedpersonnel
Serialnumberquantity
1electrician10
2Aerialworkers5
3Welder2
4generalworker15
four
5.2Listofmajorconstructionmachineryandequipmentinvested
Currentequipmentname,unitquantity,model,placeoforiginandtrademark
Remarksonself-ownednewpurchaseandlease
Grindingwheeltable4ChinaXXJ3GQ★
Drilltable20GermanEDH3-200E★
DrillFloor2ChinaXXZ516-2A★
Handdrilltable3Hitachi,Japan★
Hydraulicpipebender2ChinaXX★
ACweldingmachineplatform2,SouthChinaSea60a★★★
Gasolinegeneratorset3ChinaXX4KW★★
diesel
1Cummins40KW★generatorset
Windweldingtoolset3ChinaXX★
Craneplatform1Xugong16T★
Craneplatform2Xugong8T★
Aerialworkplatform2Xugong28M★
Truckplatform1Futianlighttruck1.5T★
Handgrinderbench15ChinaXX★★
Wirepipebend
Put12ChineseXX★ware
Hydrauliclinepressingpliershandle5ChinaXX★★
Manualhoisttable4ChinaXX2T,5T★
Mobilehangingbaskettable8XX★Custommade
Radiointercom
20ChinaXX1-5km★machine
5.3Inputmeasuringinstrumentsandmeters
Name,unit,quantity,model,placeoforigin,trademarkstatus
five
Remarksonself-ownednewpurchaseandlease
Currentmeter4UnitedStatesFLUKE★
Automaticquantity
4XXSima★lightmeter
figure
4XXHuatian★GroundingResistanceTable
DigitalTaiwan4500V★InsulationResistanceMeter
FLUKE
DigitalTaiwan11000V★InsulationResistanceMeter
FLUKE
Testbench1HuaFeiHF5130A★
Luminancemeter1FLUKE★
Theodolite1USAFLUKE★
microcomputer
2GermanHDT★streetlampcommissioninginstrument
Phasesequencedetector1GermanBEHA★
5.4Laborprotectionmaterialsandsafetyfacilitiesinvested
Name,specificationandquantity
180safetybelts
2100safetyhelmets
3warningcylinders,100
410warninglights
5warningsigns,16pieces
6.10setsofinsulatingglovesandboots
six
6.Constructionschemeandmethod
6.1Constructionschemeandmethodofstreetlampfoundationengineering
Accordingtothedesignrequirements,carryouttheconstructionofgaugeX..
6.1.1.Settingoutandpositioningofstreetlamps
Carryoutdetailedreconnaissanceontheconstructionsite,andsetoutandpositionthestreetlampsaccordingtotheconstructiondrawings.
6.1.2,diggingahole
Accordingtotheconstructiondrawingdesignrequirements,digholestomaketheholesizemeetthedesignrequirements,andcleanuptheremainingsoilintime.
6.1.3Placementofembeddedparts
6.1.4.Concretepouring
Materialselection:ThecompositionmaterialsofconcreteshallbeselectedaccordingtotherequirementsofRegulationX,andtheproportionofconcreteshallmeettheC20designstandard.
Doagoodjobofvibratingconcretetoensureitscompactness.Theconcretesurfaceissmooth.
6.2PipelineEmbeddedConstructionScheme
6.2.1,accordingtotheon-siteconstructionprogress,accordingtotheconstructionsequenceinatimelymannerforpipelineembedment,androadconstructionunits
Coordinateandcontactintime.Makethepipelineembedmentconsistentwiththeroadconstructionprocess.Cableprotectiontubeshouldnothaveholes,cracks,
Obviousunevenness.Galvanizedsteelpipebendingisprocessedbyelectricbendingmachinetoensureeffectivediameter.bendradius
Shouldcomplywiththerequirements,cannothavesimmerflat,cracks,wrinklesandotherdefects.Thepipeshallbecutbyhacksaworpipecutter.
Thetubeshouldbeflatandsmooth,withoutsharpedgesandburrs.Whenconnecting,theelectricthreadingmachineisusedforthreading,andthentheelectricpipingisusedexclusively.
Wireconnection(buriedpipecanbeweldedbycasing),andasteeljumperisaddedattheconnection.
6.2.2,accordingtotherequirementsofgaugeX,addajunctionboxappropriately.Whenpiping,wearthecorrespondinggalvanizedironwireleadsandpipethematbothends.
Thereshouldberoomforit.Beforethreadingthewires,coverthetubesatbothendswithrubberskinstopreventforeignbodiesfromenteringandhangingwhenthreadingthewires.
Wire.
6.2.3Checkthepipelinebeforethreadingtoeliminatethefactorsthatmaydamagethewire.Blowintothepipelinewhenthreading.
Theamountoftalcumpowder.Thespecifications,models,numbersandcircuitsofthethreadingpipesandwiresmustcomplywiththedesignrequirements.
Checktheinsulationofthewirebeforeandaftertheline.Theresistancevaluecannotbeincreasedatthewireconnector,andtheoriginalinsulationstrengthcannotbereduced.
Thestressconductorcannotreducetheoriginalmechanicalstrength.
6.3Cablelayingconstructionscheme
seven
Horizontallaying
cable/telegraphicaddress
Cablelayingmark
Prepareforambition
Dingpai
Verticallaying
6.3.1,cableapproachinspectionandacceptance
Afterthecablecomesintoplay,thecablemustbeinspectedandacceptedindetail,andtheappearance,specification,modelandelectricityofthecablemustbechecked.
Pressuregrade,length,certificateofapproval,heat-resistantandflame-retardantidentification,andon-sitesamplinginspectionofinsulationlayerthicknessandroundwirecore
Diameter.
6.3.2,cablelayingpreparation
1)technicalpreparation.Carefullystudytheelectricalconstructiondrawings,masterthedistributionofcables,andcarryout
Number,andindicatethestartingposition,loopnumber,specificationandmodelofthecable.Drawcableswherecablesaredense.
Sectiondistributiondiagram,showingthepositionofthecableinthebridge;Selectthebestcablelayingaccordingtothecableprofile.
Settheorder,trytoavoidcablecrossing.
2)Preparationofpersonnelandmachines.Cablelayingrequiresalargenumberofpersonnel.Beforecablelaying,accordingtothenumberofcables
Andtheamountofcablelayingschedule,makepreparationsforthepersonnelinadvance,andensurethatthepersonnelmeettheconstructionrequirementswhenlayingcables.
Atthesametime,safetytechnicaltrainingshallbeconductedforthepersonnelenteringthesite.Beforecableconstruction,preparethemachinesandtoolsforcablelaying,suchas
Cablepay-offrack,winch,cablepulley,communicationtools,etc.
3)On-sitepreparation.Checkwhethertheinstallationofthebridgeiscompleteandtheload-bearingconditionofthebracket,andcleanupthebridge.
Miscellaneousthings.Cleartheobstaclesalongthecablelayingroutetocreateagoodexternalconditionforlayingcables.
6.3.3,cablelaying
1)atthecableend,cablejoint,bendandinterlayer,atbothendsoftunnelandshaft,itshouldbeinstalled.
Setupasignboard,indicatingthelinenumberonthesignboard.Whenthereisnonumber,thecablemodel,specificationandtheoriginanddestinationshouldbestated;
Parallelcablesshallhaveserialnumbers,andthehandwritingofsignsshallbeclearandnoteasytofalloff;Signsmustbeuniforminspecificationsandmaterials.
Qualitycanbeanti-corrosive,andhangingshouldbefirm.
2)Whenlayingthecableintheonlinetrough,thecross-sectionalareaofthelaidcableshouldnotexceed40%ofthecross-sectionalareaofthetrough.In
Layinginthetrunkingshallbearrangedneatly,withoutcrossing,overlapping,twistingorjoint,andshallbeboundevery1.5M,
Bindingshouldbefirm.
3)Whenstrongandweakcablesarelaidtogether,thereshouldbeclapboards.
eight
4)Beforelaying,thecableinsulationshallbemeasuredbyshaking,andtheinsulationresistancevalueat500Vshallnotbelessthan2mω,whichshallberequiredbeforetransmission.
Shakeitagain.
5)Whenlayingthecable,thecableshouldbeledoutfromthetopofthetray,andthecableshouldbepreventedfromrubbinganddraggingonthebracketandtheground.
Pull.Theremustbenomechanicaldamageonthecablethathasnotbeeneliminated(suchaspinflattening,cabletwisting,sheathbreaking,etc.).
6.3.4Manufactureandinstallationofcablehead
Thecableterminalsareallmadeofheat-shrinkablecableterminals,andtheheaterismadeofliquefiedgasbakinggunorblowtorch.make
Selectheat-shrinkableplasticglovessuitableforthecablecrosssection.Wheninstallingthetrigeminalgloves,itisadvisabletopreheatthemfirst.
Positionthecable,putonthebranchgloves,laythecoreaccordingtotherequiredbifurcationangle,andthenheatit.Avoidinthree
Aftertheforkglovesareheat-shrunk,theforkangleofthecablecoreisgreatlychanged,resultingintheforkmouthandfingerofthegloves.
Crackingattherootofthesleeve.Whenheatingandshrinking,itshouldgraduallyextendfromthemiddleofthepipetobothends,orfromoneendtotheother.
Inordertoexhausttheairinthetubeduringcontraction,theheatingflameshouldadvancespirally.Heatshrinkablecableheadisshowninthefigure.
6.3.5.Connectionofcables
1)Forcableslargerthan6squaremeters,itisnecessarytousepressedcopperterminalsforbusconnection,andtheterminalsshouldbeconnectedwithcables.
Thecoresectionsarematched,andmanualhydrauliccrimpingpliersareusedforcrimpingcopperterminals,asshowninthefigure.
2)Afterthecableterminalismade,theinsulationtestshallbeconductedbeforeconnectingwiththepowerdistributioncabinet.
3)Toconfirmthattheinsulationstrengthmeetstherequirements.Atthesametime,thecableshouldbemarkedwithloopandphasecolor.Cable
Cutproperlytoensurethatthecablewillnotgenerateexcessivemechanicalstressafterbeingconnectedwiththebusorterminalofthedistributioncabinet.Beforeconnection,
nine
Cleanthelapsurface,andatthesametime,applyaproperamountofpowercompoundgrease,andthetighteningtorqueisinlinewiththeapplicationofbuildingelectricalengineering.
ThequalityacceptancegaugeX(GB50303-202)ensuresreliableconnectionandconductivity.
6.3.6,cableidentification
1)Thelayingofcablesshallbemarkedintime,andthesignsshallbemadeofplasticsheetsandfixedwithcabletie.mark
Thesignshouldindicatethelinenumber,cablemodel,specification,voltagelevel,startingandendingpoints,cablestartandend,terminalandswitch.
Signsshouldbehungatbendsandintersections,andsignsshouldbesetevery20minstraightsections.Afterthecableislaid,checkthattheloopnumberis
No,completetherelevantinformation.
2)Signsshouldbeconsistentinspecifications,haveanti-corrosionfunction,andbefirmlyhung.Thesignshouldindicatethecable.
Number,specificationandvoltagegrade.Signsshouldbehungonbothendsofburiedcablesenteringandleavingbuildings,cableshaftsandcables.Applyalongthestent
Setcables,andsignboardsshallbehungatbothendsandintersections,andsignboardsshallbeappropriatelyaddedatstraightsections.
3)Powercablesandcontrolcablesshouldbearrangedseparately;
4)Whenthepowercableandcontrolcablelaidsidebysidearelaidonthesamesidebracket,thecontrolcableshouldbeplaced.
Underthepowercable,thepowercablebelow1KVshouldbeplacedunderthepowercableabove1KV.
5)Thenetdistancebetweenthepowercableslaidsidebysideshallmeetthedesignrequirements.
6)Afterthecablelayingiscompleted,thesundriesshouldberemovedintime.Coverthecoverplate,andifnecessary,thegapofthecoverplateshouldbecovered.
Sealtopreventwater,steam,oilandashfrominvading.
6.3.7,distributionboxinstallationconstructionscheme
Theinstallationprocessisasfollows
Positioningembeddedparts,makingembeddedpipelinedistributioncabinet,acceptance
Installcableheadinpowerdistributioncabinettomakecableconnection.
Testinsulationandelectrifyingoperation
1)windingofswitchboxfoundation:a)earthworkexcavation,b)embeddedpipeline,c)formworksupport,d)openingembeddedchannelsteel.
Closetheboxtoinstalltheunderframe,e)pourconcrete,f)makethelightningprotectiongroundinggrid.
10
2)Unpackinginspectionofequipment:a)Theinstallationunit,supplierorconstructionunitshalljointlycarryouttheinspection.
Record.B)Checkthespecificationsoftheequipmentbody,accessoriesandsparepartsaccordingtotheequipmentlist,constructiondrawingsandequipmenttechnicaldata.
Themodelshouldmeettherequirementsofdesigndrawings;Completeaccessoriesandspareparts;Productcertificates,technicaldata,andspecificationsareinorder.
All.C)Theappearanceinspectionofcabinet(panel)shouldbeundamagedanddeformed,andthepaintshouldbeintact.D)Internalinspectionofcabinet(panel):
Electricalappliances,componentsandinsulatingporcelainarecomplete,freefromdamage,cracksandotherdefects.
3)Installationofcabinet(panel):a)Installationoffoundationsteel:thecabinet(panel)isinplace,andthecabinetbodyisremovedafteralignmentandleveling.
Fixedwithfoundationsteel.Cabinetandcabinet,cabinetandsidebaffleareconnectedbygalvanizedscrews.
4)Groundingofcabinets(panels):eachcabinet(panel)isconnectedwiththefoundationsteelseparately.Eachcabinetisfromthebottomleftoftheback.
Thenoseisweldedonthesideofthefoundationsteel,andthegroundingterminalonthecabinetisfirmlyconnectedwith6mm2copperwire.
5)Secondarysmallwireconnectionofcabinet(panel):a)Checkallelectricalcomponentsonthecabinet(panel)onebyoneaccordingtotheschematicdiagram.
Whetheritisconsistent,itsratedvoltagemustbeconsistentwiththecontrolandoperationpowersupplyvoltage.B)laythecontrolbetweencabinetsaccordingtothedrawing.
Makecableconnectingline.See"CableLaying"forcablelayingrequirements.C)Afterthecontrollineiscalibrated,simmereachcorewireintoacircle,
Connecttoeachterminalboardwithgalvanizedscrews,eyerimsandspringpads.Generally,oneterminalpressesonewireoneachsideoftheterminalboard,
Nomorethantwo,andaddeyesocketbetweentwolines.Multi-strandwiresshouldberinsedwithtin,andnobrokenstrandsareallowed.
6)Cabinet(panel)testadjustment:a)secondarycontrolsmallwireadjustmentandsimulationtest,screwallterminals
Tightenthesilkagain.B)insulationshakingtest:usea500Vshakingtabletotesttheresistanceofeachcircuitattheterminalboard,andtheresistancemustbelarge.
Small2mω.C)turnonthetemporarycontrolpowersupplyandoperationpowersupply;Fusethecontrolandoperationpowercircuitsinthecabinet(panel)
Disconnectthephaselineattheupperendofthebreakerandconnectittothetemporarypowersupply.D)Simulationtest:accordingtotherequirementsofthedrawings,respectivelysimulatethetestcontrol,
Interlocking,operatingrelayprotectionandsignalactionarecorrect,sensitiveandreliable.E)Removethetemporarypowersupply,whichwillberemoved.
Resetthepowercordof.
7,theconstructionsequenceofeachcomponentproject
7.1SubprojectofStreetLampFoundation
Thesequenceflowofstreetlampsub-projectconstructionisasfollows:
11
On-sitereconnaissancefoundationlofting,reasonableadjustmentandpositioning
Excavationofembeddedpartsandplacementofsupportingformwork
Pouringconcretecuring
7.2Cablelaying
Protectioninspection,inspectionandcablelaying
Self-inspectionofcableheadmanufacture
7.3Streetlampinstallation
Thelamppoleisplacedtothelampinstallation,fixed,calibrated,liftedandinstalled.
Testlamp
7.4Anti-theftmeasures
Concretepouringofcable,concretepouringofcableshaft,concretepouringofdistributionbox
7.5Installationofdistributionbox
Manufactureandmaintenanceofbasicdistributionbox,installationanddebuggingofdistributionbox
12
8,technicalmeasurestoensurethequalityoflightingengineering
8.1Mainmeasuresofqualitycontrol:
1,accordingtotherequirementsoftheconstructionorganizationdesign,full-scalepreparation,partialprojectpreparation.
Andthepreparationofworkingconditions.
2.Strengthenthequalitycontrolofconstructiontechnology,andmaketechnicaldisclosurestepbysteptomakeallconstructionpersonnelfamiliarwiththiswork.
Process,mainfeatures,designintent,technicalrequirements,qualitystandardsandconstructionoperationprocedures.Constructionpersonnelshouldrecognize
Workaccordingtotherequirementsofrealprocess,soastostandardize,standardizeandinstitutionalizethequalitycontrolofconstructionprocess.
3,tocarryoutpre-workinspection,doagoodjoboftechnicalreview,checkandreviewtheimportantoperationprocess,avoid
Avoidmajormistakes.Suchasthemeasurementandpositioningoffoundationandaxis,thereservedholesandembeddedpartsofpipetrenchesandroads,andvarious
Re-measurementofelevationandslopeofroads,pipetrenchesandpipelines.
4.Strengthenthequalitycontrolofmaterials,equipment,finishedproductsandsemi-finishedproducts,andtakecorrespondingtechnicalandmanagementmeasures.
MaketheseunfavorablefactorsbecontrolledwithintheallowableXrange,includingordering,purchasing,packagingand
Transportation,allmaterialsenteringthesiteshallbestrictlycheckedandacceptedaccordingtothestandard.Allkindsofrawmaterials,semi-finishedproductsandfinishedproducts
Thereisawarrantyorcertificateofapproval.Afterenteringthesite,itshouldbestored,keptandprocessedaccordingtothespecifiedconditionsandrequirements,andaccordingtotheschedule.
Plan,specifythetime,andprovidetheconstructionneeds.Forimportantmaterialsandsemi-finishedproducts,thequalitycontrolshouldbeextendedforward.
Tothesupplyandproductionunits,checkinadvance.
5,payspecialattentiontotheconstructionprocesscontrol,implementthe"stoppoint"inspectionsystem,determinetheprocesscontrolpoints,clear
Thequalityobjectivesofeachprocesscontrolpointshouldbeachieved,andthequalityofprocesscontrolpointsshouldbetestedaccordingtoregulations,andfoundout.
Thequalitygapandthecausesofthegap,takecorrespondingtechnicalmanagementmeasurestoclearthegapandpreventthequalityproblem.
Question,neverletthenonconformingproductofthepreviousprocedurebetransferredtothenextprocedure.
6.Gothroughtheexaminationandapprovalproceduresfordesignchangesandmaterialsubstitutionintime,andtheprocedurescanonlybeimplementedaftertheyhavebeencompletelycompleted.
7.Carefullyorganizetheinspectionandacceptanceofconcealedworks,whichshallbejointlyconductedbythequalityinspectionandtechnicaldirectorandtheon-sitesupervisionengineer.
With,aftertheacceptanceofthesignature,canbehidden.
5.8Doagoodjobintheinspectionandacceptanceofpartialprojectsandtheinspectionandevaluationofconstructionqualityaccordingtoregulations.
8.2Qualityinspectionwork:
Dailyself-inspectionandmutualinspectionshallbeconductedbytheconstructionteam,andanyproblemsfoundshallbehandledintime;
Theheadoftheengineeringdepartmentshallorganizetheprocesshandoverinspectionandmulti-shiftoperationhandoverinspection,anddistinguishtheproblemsfound.
13
Handleresponsibilityatanytime;
Full-timequalityinspectorswillconductfull-timeinspections,especiallyfocusingontheinspectionofkeypartsandweaklinks.
Cooperatewithconstructiontechniciansandteamstosolveexistingproblems.
8.3Qualityevaluation:
Afterthecompletionofthepartialprojectorunitproject,thesitequalityinspectiondirectorandtheconstructiontechnicalengineerwilljointlyhaveit.
Closethefull-timequalityinspectionpersonnelforqualityevaluation,andasktheon-sitesupervisionengineertoapprovethevisa.
Aftertheabovequalityevaluation,therelevantstatementsofqualityevaluationshallbefilledoutandcarefullyfiled.
8.4Cons
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 餐饮冷链解决方案
- 建设工程管理总结
- 高三化学二轮复习 -《探究性实验微专题》说播课课件
- 防溺水防雷击安全教育
- 开花树课件教学课件
- 3.3.2氮氧化物及含氮废水的处理 课件高一上学期化学鲁科版(2019)必修第一册
- 药物滥用危害健康
- 迈柯维呼吸机培训
- 急性创伤相关知识及护理常规
- 酒店如何做好食品安全
- 心理应激与心身疾病-PPT课件
- 《中国古代文学史——第四编:隋唐五代文学》PPT课件(完整版)
- 第5章金融资产ppt课件
- 硬笔书法兴趣小组(社团)活动计划+教案
- (高清正版)JJF(浙)1149-2018生物实验用干式恒温器校准规范
- 廉洁校园你我共塑PPT课件(带内容)
- 建设银行股份关联交易申报及信息披露系统操作手册新一代
- 水文信息采集与处理习题
- 星级酒店服务技能大赛活动方案
- 义务教育《道德与法治》课程标准(2022年版)
- 中职数学认识多面体与旋转体(课堂PPT)
评论
0/150
提交评论