XXbridge

Lightingconstructionscheme

Review:

Approval:

XXXbridgeprojectmanagementdepartment

May10th,2013

catalogue

1.Compilationbasis:2

2.ProjectOverview2

3,themainquantitiesof2...4,ofvariousconstructionmanagementobjectives3...

4.1Qualityobjectives3

4.2Timelimitforaprojecttarget3...4.3Safetyproductiontarget3...

4.4civilizedconstructiontarget3...4.5linkprotectiontarget...5,ConstructionOrganizationandManagementOrganizationandGuaranteeMeasures4...

5.1ofconstructionorganizationandinvestmentpersonnel4...

5.2Tableofmajorconstructionmachineryandequipmentinvestedin5..

5.3ofinvestedmeasuringinstrumentsandmeters5...

5.4oflaborprotectionmaterialsandsafetyfacilitiesinvested6..

6.Constructionschemeandmethod7...

6.1Constructionschemeandmethodofstreetlampfoundationproject7..

6.2PipelineEmbeddedConstructionScheme7...

6.3Cablelayingconstructionscheme7...

7.Theconstructionsequenceofeachsub-projectis1..1.

7.1Streetlampfoundationsub-project1..1.

7.2Cablelaying1..2..

7.3Streetlampinstallation1..2..

7.4Anti-theftmeasuresInstallationofdistributionbox1..2.8,TechnicalMeasurestoEnsuretheQualityofLightingEngineering1..3.

8.1Mainmeasuresofqualitycontrol:1.3.

8.2Qualityinspection:1..3.

8.3Qualityevaluation:1.4.

8.4Constructionqualityassurancemeasures1.4.

9,civilizedconstructionoperationplan,safetyproductionandenvironmentalprotectionmeasures2..2

9.1civilizedconstructionoperationplan2..2.

9.2Safetyproductionmeasures2.5.

9.3Environmentalprotectionmeasures3.2..

-1-

ConstructionschemeofXXXbridgelightingproject

1.Compilationbasis

1,"XXXBridgeProject"constructiondrawings;

2.Overallconstructiondeploymentandtimelimitplan;

3.DesignStandardofUrbanRoadLightingCJJ45-2006

4.CodeforConstructionandAcceptanceofLow-voltageElectricalApparatusinElectricalInstallationEngineeringX(GB50254-96)

5.CodeforConstructionandAcceptanceofCableLinesinElectricalEquipmentInstallationProjectX(GB50168-92)

6.CodeforConstructionandAcceptanceofGroundingDeviceinElectricalDeviceInstallationProjectX(GB50169-92)

7.CodeforConstructionandAcceptanceofOverheadPowerLinesof35KVandBelowinElectricalEquipmentInstallationProjectX(GB50173-92)

8.CodeforConstructionandAcceptanceofUrbanRoadLightingEngineering(CJJ89-2001).

2.Projectoverview

TheconstructionareaoftheprojectislocatedinXXXBridgeProjectinXXProvince,withastartingandendingmileageofK0+113~K0+363,includingXXX.

Leftandrightsidesofthebridge.

XXXbridgespantypeis(65+110+65)mthree-spanprestressedconcretecontinuousboxgirder;TheroadgradeisGradeII.

Highway(whichisalsoaclassIItrunkroadinthecity).Thetotallengthofthebridgeis250m,andthewidthofthebridgedeckis2×(3.5(sidewalk)+0.5(A

Full)+3×3.5(carriageway)+0.5(safetybelt)+0.5(crashbarrier))+0.5=24.5m,includingthesouthbankconnection.

Civilengineering,trafficengineering,lightingengineering,etc.attheintersectionoftheline.

Thedesignspeedofhighwayengineeringinthisbidsectionis40km/h,andthebaseperiodofstructuraldesignis100years.Typeselectionoflampsandlanterns

Single-armstreetlamp,thepoleheightis10m,andtheboomlengthis2m.

Theincomingpowersupplyofthisprojectisprovidedbytheowner,andthepowersupplyisintheformof380Vvoltagenearby.Thestreetlampcontrolboxislocatedin

ProvincialHighwayNo.304attheabutment.TN-Sgroundingprotectionsystemisadoptedforlow-voltagepowerdistribution,andstreetlamptransformerandcontroldistributionboxareintegrated.

Type.

3.Mainquantities

Name,specification,unitquantityremarks

1-armstreetlamp

H=10MIP65NG250boom:2m

Elevation:12degrees

Tai18

2OutdoorlightingcontrolboxKTJSQ-30/3.3-A-Iset1

2

3Low-voltagecableYJV-0.6/1kV-5*6m545

4GalvanizedsteelpipeG50m520

5GalvanizedsteelpipeG100m30

6handholewell90cm*120cmmouth1

7StreetlampfoundationVV-1kv4*2518

8galvanizedflatsteel-50*5m20

9AnglesteelartificialgroundingelectrodesL50*50*25004

10

Outdoorlightingcontrolboxbase

seat

40*800*11201

4,theconstructionmanagementobjectives

4.1Qualityobjectives

Projectqualityobjective:toreachthequalifiedstandardintheStandardforQualityInspectionandEvaluationofHighwayEngineering(JTGF80-2004)

Accurate,andthecomprehensivescoreofnotlessthan95points.

4.2Timelimitforaprojectobjectives

TheplannedcommencementdateofthisprojectisApril1,2014,andtheplannedcompletiondateisMay31,2014,withatotaldurationof61.

God.

4.3safetyproductionobjectives

Thesafetyproductiongoalofthisprojectis:nomajorcasualtyaccidents,accidentinjuryratecontrolledbelow0.06%,andnoweight.

Equipment,fire,pipeline,trafficandotheraccidents.

4.4civilizedconstructiongoal

Thecivilizedconstructionmanagementobjectivesofthisproject:donotcauseallkindsofenvironmentalpollutionaccidents,andputanendtoriverpollutionincidents;strict

Followthe"ImplementationMeasuresforConstructionSiteManagementofConstructionProjectsinXXProvince".

4.5Linkprotectionobjectives

Theenvironmentalprotectionoftheconstructionsiteofthisprojectshoulddothefollowingwork:controlthedischargeofproductionanddomesticwaterintheconstructionsite;

Strengthenthemanagementofconstructionmachinery,improveconstructiontechnologyandreducenoise;Wasteasphaltconcretematerialswillbepileduptothedesignatedplace.

three

Location,handledbyaqualifiedenterprise;Strengthenpipelineprotectiontopreventpipelineaccidents;Implementthedangerousgoodsscene.

Control,typhoonpreventionandfloodcontrol,fireemergencycontrol,etc.Ensurenopollutiontothesurroundingenvironmentduringtheconstructionprocess,indeed

Nocomplaintsfromresidentsormanufacturers.

5,theconstructionorganizationandmanagementinstitutionsandguaranteemeasures

5.1Constructionorganizationandinvestmentpersonnel

Theprojectintendstosetuptheprojectmanager,deputyprojectmanagerandchiefengineertoformtheprojectintendstoleadtheteam.under

Setupengineeringdepartment,qualityinspectionandsafetydepartment,materialsandequipmentdepartment,laboratory,planningandcontractdepartment,eachdepartmentconsistsof

Constructionteam,formingthewholeprojectintendsto.

Projectmanager:XX

DeputyProjectManager:XXProjectChiefEngineer:XX

LaboratoryofQualityInspectionDepartmentofEngineeringDepartment:PlanningMachineryOffice:

Contractministryofmaterialsandequipment

XXXXXXXXXXXXXX

Investedpersonnel

Serialnumberquantity

1electrician10

2Aerialworkers5

3Welder2

4generalworker15

four

5.2Listofmajorconstructionmachineryandequipmentinvested

Currentequipmentname,unitquantity,model,placeoforiginandtrademark

Remarksonself-ownednewpurchaseandlease

Grindingwheeltable4ChinaXXJ3GQ★

Drilltable20GermanEDH3-200E★

DrillFloor2ChinaXXZ516-2A★

Handdrilltable3Hitachi,Japan★

Hydraulicpipebender2ChinaXX★

ACweldingmachineplatform2,SouthChinaSea60a★★★

Gasolinegeneratorset3ChinaXX4KW★★

diesel

1Cummins40KW★generatorset

Windweldingtoolset3ChinaXX★

Craneplatform1Xugong16T★

Craneplatform2Xugong8T★

Aerialworkplatform2Xugong28M★

Truckplatform1Futianlighttruck1.5T★

Handgrinderbench15ChinaXX★★

Wirepipebend

Put12ChineseXX★ware

Hydrauliclinepressingpliershandle5ChinaXX★★

Manualhoisttable4ChinaXX2T,5T★

Mobilehangingbaskettable8XX★Custommade

Radiointercom

20ChinaXX1-5km★machine

5.3Inputmeasuringinstrumentsandmeters

Name,unit,quantity,model,placeoforigin,trademarkstatus

five

Remarksonself-ownednewpurchaseandlease

Currentmeter4UnitedStatesFLUKE★

Automaticquantity

4XXSima★lightmeter

figure

4XXHuatian★GroundingResistanceTable

DigitalTaiwan4500V★InsulationResistanceMeter

FLUKE

DigitalTaiwan11000V★InsulationResistanceMeter

FLUKE

Testbench1HuaFeiHF5130A★

Luminancemeter1FLUKE★

Theodolite1USAFLUKE★

microcomputer

2GermanHDT★streetlampcommissioninginstrument

Phasesequencedetector1GermanBEHA★

5.4Laborprotectionmaterialsandsafetyfacilitiesinvested

Name,specificationandquantity

180safetybelts

2100safetyhelmets

3warningcylinders,100

410warninglights

5warningsigns,16pieces

6.10setsofinsulatingglovesandboots

six

6.Constructionschemeandmethod

6.1Constructionschemeandmethodofstreetlampfoundationengineering

Accordingtothedesignrequirements,carryouttheconstructionofgaugeX..

6.1.1.Settingoutandpositioningofstreetlamps

Carryoutdetailedreconnaissanceontheconstructionsite,andsetoutandpositionthestreetlampsaccordingtotheconstructiondrawings.

6.1.2,diggingahole

Accordingtotheconstructiondrawingdesignrequirements,digholestomaketheholesizemeetthedesignrequirements,andcleanuptheremainingsoilintime.

6.1.3Placementofembeddedparts

6.1.4.Concretepouring

Materialselection:ThecompositionmaterialsofconcreteshallbeselectedaccordingtotherequirementsofRegulationX,andtheproportionofconcreteshallmeettheC20designstandard.

Doagoodjobofvibratingconcretetoensureitscompactness.Theconcretesurfaceissmooth.

6.2PipelineEmbeddedConstructionScheme

6.2.1,accordingtotheon-siteconstructionprogress,accordingtotheconstructionsequenceinatimelymannerforpipelineembedment,androadconstructionunits

Coordinateandcontactintime.Makethepipelineembedmentconsistentwiththeroadconstructionprocess.Cableprotectiontubeshouldnothaveholes,cracks,

Obviousunevenness.Galvanizedsteelpipebendingisprocessedbyelectricbendingmachinetoensureeffectivediameter.bendradius

Shouldcomplywiththerequirements,cannothavesimmerflat,cracks,wrinklesandotherdefects.Thepipeshallbecutbyhacksaworpipecutter.

Thetubeshouldbeflatandsmooth,withoutsharpedgesandburrs.Whenconnecting,theelectricthreadingmachineisusedforthreading,andthentheelectricpipingisusedexclusively.

Wireconnection(buriedpipecanbeweldedbycasing),andasteeljumperisaddedattheconnection.

6.2.2,accordingtotherequirementsofgaugeX,addajunctionboxappropriately.Whenpiping,wearthecorrespondinggalvanizedironwireleadsandpipethematbothends.

Thereshouldberoomforit.Beforethreadingthewires,coverthetubesatbothendswithrubberskinstopreventforeignbodiesfromenteringandhangingwhenthreadingthewires.

Wire.

6.2.3Checkthepipelinebeforethreadingtoeliminatethefactorsthatmaydamagethewire.Blowintothepipelinewhenthreading.

Theamountoftalcumpowder.Thespecifications,models,numbersandcircuitsofthethreadingpipesandwiresmustcomplywiththedesignrequirements.

Checktheinsulationofthewirebeforeandaftertheline.Theresistancevaluecannotbeincreasedatthewireconnector,andtheoriginalinsulationstrengthcannotbereduced.

Thestressconductorcannotreducetheoriginalmechanicalstrength.

6.3Cablelayingconstructionscheme

seven

Horizontallaying

cable/telegraphicaddress

Cablelayingmark

Prepareforambition

Dingpai

Verticallaying

6.3.1,cableapproachinspectionandacceptance

Afterthecablecomesintoplay,thecablemustbeinspectedandacceptedindetail,andtheappearance,specification,modelandelectricityofthecablemustbechecked.

Pressuregrade,length,certificateofapproval,heat-resistantandflame-retardantidentification,andon-sitesamplinginspectionofinsulationlayerthicknessandroundwirecore

Diameter.

6.3.2,cablelayingpreparation

1)technicalpreparation.Carefullystudytheelectricalconstructiondrawings,masterthedistributionofcables,andcarryout

Number,andindicatethestartingposition,loopnumber,specificationandmodelofthecable.Drawcableswherecablesaredense.

Sectiondistributiondiagram,showingthepositionofthecableinthebridge;Selectthebestcablelayingaccordingtothecableprofile.

Settheorder,trytoavoidcablecrossing.

2)Preparationofpersonnelandmachines.Cablelayingrequiresalargenumberofpersonnel.Beforecablelaying,accordingtothenumberofcables

Andtheamountofcablelayingschedule,makepreparationsforthepersonnelinadvance,andensurethatthepersonnelmeettheconstructionrequirementswhenlayingcables.

Atthesametime,safetytechnicaltrainingshallbeconductedforthepersonnelenteringthesite.Beforecableconstruction,preparethemachinesandtoolsforcablelaying,suchas

Cablepay-offrack,winch,cablepulley,communicationtools,etc.

3)On-sitepreparation.Checkwhethertheinstallationofthebridgeiscompleteandtheload-bearingconditionofthebracket,andcleanupthebridge.

Miscellaneousthings.Cleartheobstaclesalongthecablelayingroutetocreateagoodexternalconditionforlayingcables.

6.3.3,cablelaying

1)atthecableend,cablejoint,bendandinterlayer,atbothendsoftunnelandshaft,itshouldbeinstalled.

Setupasignboard,indicatingthelinenumberonthesignboard.Whenthereisnonumber,thecablemodel,specificationandtheoriginanddestinationshouldbestated;

Parallelcablesshallhaveserialnumbers,andthehandwritingofsignsshallbeclearandnoteasytofalloff;Signsmustbeuniforminspecificationsandmaterials.

Qualitycanbeanti-corrosive,andhangingshouldbefirm.

2)Whenlayingthecableintheonlinetrough,thecross-sectionalareaofthelaidcableshouldnotexceed40%ofthecross-sectionalareaofthetrough.In

Layinginthetrunkingshallbearrangedneatly,withoutcrossing,overlapping,twistingorjoint,andshallbeboundevery1.5M,

Bindingshouldbefirm.

3)Whenstrongandweakcablesarelaidtogether,thereshouldbeclapboards.

eight

4)Beforelaying,thecableinsulationshallbemeasuredbyshaking,andtheinsulationresistancevalueat500Vshallnotbelessthan2mω,whichshallberequiredbeforetransmission.

Shakeitagain.

5)Whenlayingthecable,thecableshouldbeledoutfromthetopofthetray,andthecableshouldbepreventedfromrubbinganddraggingonthebracketandtheground.

Pull.Theremustbenomechanicaldamageonthecablethathasnotbeeneliminated(suchaspinflattening,cabletwisting,sheathbreaking,etc.).

6.3.4Manufactureandinstallationofcablehead

Thecableterminalsareallmadeofheat-shrinkablecableterminals,andtheheaterismadeofliquefiedgasbakinggunorblowtorch.make

Selectheat-shrinkableplasticglovessuitableforthecablecrosssection.Wheninstallingthetrigeminalgloves,itisadvisabletopreheatthemfirst.

Positionthecable,putonthebranchgloves,laythecoreaccordingtotherequiredbifurcationangle,andthenheatit.Avoidinthree

Aftertheforkglovesareheat-shrunk,theforkangleofthecablecoreisgreatlychanged,resultingintheforkmouthandfingerofthegloves.

Crackingattherootofthesleeve.Whenheatingandshrinking,itshouldgraduallyextendfromthemiddleofthepipetobothends,orfromoneendtotheother.

Inordertoexhausttheairinthetubeduringcontraction,theheatingflameshouldadvancespirally.Heatshrinkablecableheadisshowninthefigure.

6.3.5.Connectionofcables

1)Forcableslargerthan6squaremeters,itisnecessarytousepressedcopperterminalsforbusconnection,andtheterminalsshouldbeconnectedwithcables.

Thecoresectionsarematched,andmanualhydrauliccrimpingpliersareusedforcrimpingcopperterminals,asshowninthefigure.

2)Afterthecableterminalismade,theinsulationtestshallbeconductedbeforeconnectingwiththepowerdistributioncabinet.

3)Toconfirmthattheinsulationstrengthmeetstherequirements.Atthesametime,thecableshouldbemarkedwithloopandphasecolor.Cable

Cutproperlytoensurethatthecablewillnotgenerateexcessivemechanicalstressafterbeingconnectedwiththebusorterminalofthedistributioncabinet.Beforeconnection,

nine

Cleanthelapsurface,andatthesametime,applyaproperamountofpowercompoundgrease,andthetighteningtorqueisinlinewiththeapplicationofbuildingelectricalengineering.

ThequalityacceptancegaugeX(GB50303-202)ensuresreliableconnectionandconductivity.

6.3.6,cableidentification

1)Thelayingofcablesshallbemarkedintime,andthesignsshallbemadeofplasticsheetsandfixedwithcabletie.mark

Thesignshouldindicatethelinenumber,cablemodel,specification,voltagelevel,startingandendingpoints,cablestartandend,terminalandswitch.

Signsshouldbehungatbendsandintersections,andsignsshouldbesetevery20minstraightsections.Afterthecableislaid,checkthattheloopnumberis

No,completetherelevantinformation.

2)Signsshouldbeconsistentinspecifications,haveanti-corrosionfunction,andbefirmlyhung.Thesignshouldindicatethecable.

Number,specificationandvoltagegrade.Signsshouldbehungonbothendsofburiedcablesenteringandleavingbuildings,cableshaftsandcables.Applyalongthestent

Setcables,andsignboardsshallbehungatbothendsandintersections,andsignboardsshallbeappropriatelyaddedatstraightsections.

3)Powercablesandcontrolcablesshouldbearrangedseparately;

4)Whenthepowercableandcontrolcablelaidsidebysidearelaidonthesamesidebracket,thecontrolcableshouldbeplaced.

Underthepowercable,thepowercablebelow1KVshouldbeplacedunderthepowercableabove1KV.

5)Thenetdistancebetweenthepowercableslaidsidebysideshallmeetthedesignrequirements.

6)Afterthecablelayingiscompleted,thesundriesshouldberemovedintime.Coverthecoverplate,andifnecessary,thegapofthecoverplateshouldbecovered.

Sealtopreventwater,steam,oilandashfrominvading.

6.3.7,distributionboxinstallationconstructionscheme

Theinstallationprocessisasfollows

Positioningembeddedparts,makingembeddedpipelinedistributioncabinet,acceptance

Installcableheadinpowerdistributioncabinettomakecableconnection.

Testinsulationandelectrifyingoperation

1)windingofswitchboxfoundation:a)earthworkexcavation,b)embeddedpipeline,c)formworksupport,d)openingembeddedchannelsteel.

Closetheboxtoinstalltheunderframe,e)pourconcrete,f)makethelightningprotectiongroundinggrid.

10

2)Unpackinginspectionofequipment:a)Theinstallationunit,supplierorconstructionunitshalljointlycarryouttheinspection.

Record.B)Checkthespecificationsoftheequipmentbody,accessoriesandsparepartsaccordingtotheequipmentlist,constructiondrawingsandequipmenttechnicaldata.

Themodelshouldmeettherequirementsofdesigndrawings;Completeaccessoriesandspareparts;Productcertificates,technicaldata,andspecificationsareinorder.

All.C)Theappearanceinspectionofcabinet(panel)shouldbeundamagedanddeformed,andthepaintshouldbeintact.D)Internalinspectionofcabinet(panel):

Electricalappliances,componentsandinsulatingporcelainarecomplete,freefromdamage,cracksandotherdefects.

3)Installationofcabinet(panel):a)Installationoffoundationsteel:thecabinet(panel)isinplace,andthecabinetbodyisremovedafteralignmentandleveling.

Fixedwithfoundationsteel.Cabinetandcabinet,cabinetandsidebaffleareconnectedbygalvanizedscrews.

4)Groundingofcabinets(panels):eachcabinet(panel)isconnectedwiththefoundationsteelseparately.Eachcabinetisfromthebottomleftoftheback.

Thenoseisweldedonthesideofthefoundationsteel,andthegroundingterminalonthecabinetisfirmlyconnectedwith6mm2copperwire.

5)Secondarysmallwireconnectionofcabinet(panel):a)Checkallelectricalcomponentsonthecabinet(panel)onebyoneaccordingtotheschematicdiagram.

Whetheritisconsistent,itsratedvoltagemustbeconsistentwiththecontrolandoperationpowersupplyvoltage.B)laythecontrolbetweencabinetsaccordingtothedrawing.

Makecableconnectingline.See"CableLaying"forcablelayingrequirements.C)Afterthecontrollineiscalibrated,simmereachcorewireintoacircle,

Connecttoeachterminalboardwithgalvanizedscrews,eyerimsandspringpads.Generally,oneterminalpressesonewireoneachsideoftheterminalboard,

Nomorethantwo,andaddeyesocketbetweentwolines.Multi-strandwiresshouldberinsedwithtin,andnobrokenstrandsareallowed.

6)Cabinet(panel)testadjustment:a)secondarycontrolsmallwireadjustmentandsimulationtest,screwallterminals

Tightenthesilkagain.B)insulationshakingtest:usea500Vshakingtabletotesttheresistanceofeachcircuitattheterminalboard,andtheresistancemustbelarge.

Small2mω.C)turnonthetemporarycontrolpowersupplyandoperationpowersupply;Fusethecontrolandoperationpowercircuitsinthecabinet(panel)

Disconnectthephaselineattheupperendofthebreakerandconnectittothetemporarypowersupply.D)Simulationtest:accordingtotherequirementsofthedrawings,respectivelysimulatethetestcontrol,

Interlocking,operatingrelayprotectionandsignalactionarecorrect,sensitiveandreliable.E)Removethetemporarypowersupply,whichwillberemoved.

Resetthepowercordof.

7,theconstructionsequenceofeachcomponentproject

7.1SubprojectofStreetLampFoundation

Thesequenceflowofstreetlampsub-projectconstructionisasfollows:

11

On-sitereconnaissancefoundationlofting,reasonableadjustmentandpositioning

Excavationofembeddedpartsandplacementofsupportingformwork

Pouringconcretecuring

7.2Cablelaying

Protectioninspection,inspectionandcablelaying

Self-inspectionofcableheadmanufacture

7.3Streetlampinstallation

Thelamppoleisplacedtothelampinstallation,fixed,calibrated,liftedandinstalled.

Testlamp

7.4Anti-theftmeasures

Concretepouringofcable,concretepouringofcableshaft,concretepouringofdistributionbox

7.5Installationofdistributionbox

Manufactureandmaintenanceofbasicdistributionbox,installationanddebuggingofdistributionbox

12

8,technicalmeasurestoensurethequalityoflightingengineering

8.1Mainmeasuresofqualitycontrol:

1,accordingtotherequirementsoftheconstructionorganizationdesign,full-scalepreparation,partialprojectpreparation.

Andthepreparationofworkingconditions.

2.Strengthenthequalitycontrolofconstructiontechnology,andmaketechnicaldisclosurestepbysteptomakeallconstructionpersonnelfamiliarwiththiswork.

Process,mainfeatures,designintent,technicalrequirements,qualitystandardsandconstructionoperationprocedures.Constructionpersonnelshouldrecognize

Workaccordingtotherequirementsofrealprocess,soastostandardize,standardizeandinstitutionalizethequalitycontrolofconstructionprocess.

3,tocarryoutpre-workinspection,doagoodjoboftechnicalreview,checkandreviewtheimportantoperationprocess,avoid

Avoidmajormistakes.Suchasthemeasurementandpositioningoffoundationandaxis,thereservedholesandembeddedpartsofpipetrenchesandroads,andvarious

Re-measurementofelevationandslopeofroads,pipetrenchesandpipelines.

4.Strengthenthequalitycontrolofmaterials,equipment,finishedproductsandsemi-finishedproducts,andtakecorrespondingtechnicalandmanagementmeasures.

MaketheseunfavorablefactorsbecontrolledwithintheallowableXrange,includingordering,purchasing,packagingand

Transportation,allmaterialsenteringthesiteshallbestrictlycheckedandacceptedaccordingtothestandard.Allkindsofrawmaterials,semi-finishedproductsandfinishedproducts

Thereisawarrantyorcertificateofapproval.Afterenteringthesite,itshouldbestored,keptandprocessedaccordingtothespecifiedconditionsandrequirements,andaccordingtotheschedule.

Plan,specifythetime,andprovidetheconstructionneeds.Forimportantmaterialsandsemi-finishedproducts,thequalitycontrolshouldbeextendedforward.

Tothesupplyandproductionunits,checkinadvance.

5,payspecialattentiontotheconstructionprocesscontrol,implementthe"stoppoint"inspectionsystem,determinetheprocesscontrolpoints,clear

Thequalityobjectivesofeachprocesscontrolpointshouldbeachieved,andthequalityofprocesscontrolpointsshouldbetestedaccordingtoregulations,andfoundout.

Thequalitygapandthecausesofthegap,takecorrespondingtechnicalmanagementmeasurestoclearthegapandpreventthequalityproblem.

Question,neverletthenonconformingproductofthepreviousprocedurebetransferredtothenextprocedure.

6.Gothroughtheexaminationandapprovalproceduresfordesignchangesandmaterialsubstitutionintime,andtheprocedurescanonlybeimplementedaftertheyhavebeencompletelycompleted.

7.Carefullyorganizetheinspectionandacceptanceofconcealedworks,whichshallbejointlyconductedbythequalityinspectionandtechnicaldirectorandtheon-sitesupervisionengineer.

With,aftertheacceptanceofthesignature,canbehidden.

5.8Doagoodjobintheinspectionandacceptanceofpartialprojectsandtheinspectionandevaluationofconstructionqualityaccordingtoregulations.

8.2Qualityinspectionwork:

Dailyself-inspectionandmutualinspectionshallbeconductedbytheconstructionteam,andanyproblemsfoundshallbehandledintime;

Theheadoftheengineeringdepartmentshallorganizetheprocesshandoverinspectionandmulti-shiftoperationhandoverinspection,anddistinguishtheproblemsfound.

13

Handleresponsibilityatanytime;

Full-timequalityinspectorswillconductfull-timeinspections,especiallyfocusingontheinspectionofkeypartsandweaklinks.

Cooperatewithconstructiontechniciansandteamstosolveexistingproblems.

8.3Qualityevaluation:

Afterthecompletionofthepartialprojectorunitproject,thesitequalityinspectiondirectorandtheconstructiontechnicalengineerwilljointlyhaveit.

Closethefull-timequalityinspectionpersonnelforqualityevaluation,andasktheon-sitesupervisionengineertoapprovethevisa.

Aftertheabovequalityevaluation,therelevantstatementsofqualityevaluationshallbefilledoutandcarefullyfiled.

8.4Cons

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论