版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1SiteReportofAuchanNingboXinxingPhaseII宁波新星二期项目现场报告23EastFacade东立面4SouthFacade南立面5NorthFacade北立面6ConnectionbetweenPhaseI&PhaseII一期、二期结合处B2地下二层Floorpouring地坪浇筑B1地下一层B1地下一层Wallplastering墙面抹灰B1地下一层FreezerRoom冷冻机房1F地上一层2F地上二层3F地上三层3F地上三层Exquisitemodelarea精装修样板区Roof屋面Rooftrussinstallation屋面大网架安装Lightingglasswindowinstallation采光天窗玻璃安装Outside室外RoadConstruction道路施工Outside室外Aluminuminstallation铝板安装Outside室外TheALCboardisongoing.ALC板安装Outside室外Cranedismantling塔吊拆除SanbaoProject三宝项目Sanbaoprojectiscurrentlyintheshutdown.三宝项目目前处于停工状态。24Mainstructurecompleted
100%主体结构完成100%Steelstructureworkcompleted100%
钢结构完成100%Wallmasonrycompleted100%砌体完成100%Exquisitecompleted10%精装修完成10%Outsideworkcompleted55%
室外工程完成55%M&Eworkcompleted87%
机电完成87%FFSworkcompleted70%消防完成70%Curtainworkcompleted60%
幕墙完成60%PhaseIIConstructionSchedule二期工程进度25Mainstructurecompleteon28thSeptember2013
2013年9月28日主体结构完成Steelstructurecompleteon10thDecember2013
2013年12月10日钢结构完成ForFFAcceptance,waitingforDAItoconfirmthepowerequipmentsupplyandPowerBureautoconfirmthedateofformalpowersupplyopening.
关于消防验收,等待非直采确认供电设备的供应以及供电局确认正式用电的开通日期。PhaseIIConstructionSchedule二期工程进度26PowerBureaurequireAuchantoberesponsibleforpowerpipetrenchwhichisoutofAuchanredline.Expansiondepartmentiscurrentlyoncoordinationwithgovernment.Weestimatetheopeningofformalpowersupplywillbedelayedto30thApril2014.
供电局要求欧尚负责建设欧尚红线外的电缆管沟。发展部正在与政府协商。我们估计正式供电要延期至2014年4月30日开通。AboutUtility关于市政配套Inthisyear,20meetingshasbeenheldamongtechnical,construction,gallerydepartment(on01/14、02/02、03/07、03/22、03/28、03/29、04/17、05/14、05/21、05/31、06/11、06/21、07/12、07/16、07/24、07/31、08/28、09/12、09/13、09/26),discussingallthemattersneededtobeconfirmedbygallery.Sofar,still7notconfirmed,pleaseseethelistmemobelow.今年,技术部、工程部、招商部门共同召开了20次的会议(分别在01/14、02/02、03/07、03/22、03/28、03/29、04/17、05/14、05/21、05/31、06/11、06/21、07/12、07/16、07/24、07/31、08/28、09/12、09/13、09/26),讨论了所有需要招商部门确认的事宜。截止目前,还有7条没有得到确认,详见后面的清单。AboutGallery关于招商Tobeconfirmed1/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact1confirmationforcommerciallayoutUpdatedDetaileddesignbaseonthefinallayoutGalleryTechnical2013/1/15-2013/1/23125-Jan-13Finishedonthe25thMarch2013
2PowercapacityfortenantsconfirmationUpdatedDetaileddesignGallery2013/1/15-2013/1/23125-Jan-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed3DesignSpec/parameter/interfaceconfirmationneedtobeincludedindetaileddesignGallery2013/1/25-2013/2/528-Feb-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed4ShoppingmallOperationandpropertymanagementrequirementsOperationandmanagementfacilitiesrequirementstobeinputintothedesignGallery2013/2/15-2013/4/20125-Mar-13Designconditionsandreservationneedtobeconfirmedbefore2013/1/31Constructiondrawingdelay5ITandmunicationfortenantsSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay6BuildingAutomaticManagementsystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay7SecurityandaccesscontrolsystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay8PublicaddresssystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelayColorinyellowmeansdelayTobeconfirmed2/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact9CATVforpublicandtenantsSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13NotconsiderednowConstructiondrawingdelay10Wi-FiandWirelesscoverageSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13
11gasneedsandapplicationforTenantsconfirmationengagethedetaileddesignerGallery2013/3/1-2013/3/31125-Apr-13Total600M/hourreservedat20130202
12ShoppingMallinformation/communicationinteractsystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/3/15-2013/4/311-Jun-13
13SMcustomerflowcalculationSystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/3/15-2013/4/321-Jun-13
14ParkingmanagementsystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/4/15-2013/5/3021-Jul-13
15TenantsconstructionmanagementandcommonzoneoperationprotocolandinterfacedetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/5/15-2013/7/30225-Sep-13
16TenantsconstructionpermitsdetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/7/15-2013/8/30225-Sep-13
ColorinyellowmeansdelayTobeconfirmed3/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact17TenantsopeningconditionsbySMdetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/7/15-2013/8/30225-Sep-13
18TrolleyflowlimitationdesignforthespaceandfacilitiesofthebarriersGallery2013/1/15-2013/1/23325-Jan-13
19SMStaffparking&accesscontrolneedindependsignandinputtoSecuritiessystemGallery2013/3/15-2013/4/3141-Jun-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed20stormwaterrecyclingReviewandconfirmtheproposalUMAN2013/3/15-2013/4/31415-May-13ProponedM&EDesignDelay21CoolingcapacityfortenantsconfirmationUpdatedDetaileddesignGallery2013/3/1-2013/3/20125-Jan-13Finishedonthe25thMarch2013MEPConstructiondrawingdesign22Landscape/Sign/LogodesignconfirmationCurtainwallDetaileddesignbaseontheSign/LogodesignconfirmationGallery2013/1/15-2013/3/20130-Apr-13
impacttheprogressofBMdesign23TenantssetbacktoCurtainwallinsidespacetoensuretheimageofentirefacadeGallery2013/7/201-2013/731431-Aug-13
24TenantsmoveinconditionsandscheduleNeedcommonunderstandingforthetenantsmoveinbeforeFFinspectionandtheconstructioncompletiondateGalleryTechnicalConstruction2013/5/15-2013/6/10120-Jun-13Itisnotsameunderstandingwithconstructiondepartmentimpactentireprojecttargetscheduleandsiteconstructionorganization.Tobeconfirmed4/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact25Tenantsdesignandconstructionmanagementplan&protocolfurtherclarificationneedfromthemanagementtoplanworkingscheduleGalleryTechnicalConstructionUMAN2013/5/15-2013/6/20225-Jun-13
26RequestofB1commercialUpdatedDetaileddesignGallery
TechnicalASAP120-Apr-13
27TheBridgeconnectionwithSanbao
ExpansionGallery
Technical2013/4/15-2013/5/1511-Jun-13pending
28FreshairandventilationofKitchenUpdatedDetaileddesignGallery2013/5/17-2013/5/31130-May-1329locationofthewastewaterofeachtenantUpdatedDetaileddesignGallery2013/5/17-2013/5/31130-May-13
30
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 全身多处骨折护理
- 公司级安全培训课件
- 前台员工服务意识培训
- 《责任心培训教材》课件
- 2024服装合同书范文
- 2024中外专利技术许可合同合同范本
- 2024商铺租赁合同(范本)
- 2024年邻硝基苯酚项目评估分析报告
- 2024至2030年中国重型九脚塑料托盘行业投资前景及策略咨询研究报告
- 2024至2030年中国高光透明面漆行业投资前景及策略咨询研究报告
- 专题09 完形填空 考点2 生活哲理类2024年中考英语真题分类汇编
- 项目验收通知书模板
- 2024年江西省高考物理试卷(真题+答案)
- 新版工贸企业重大事故隐患-题库
- 2024年四川成都铁路局招聘1015人历年(高频重点提升专题训练)共500题附带答案详解
- 工程认知实践体验智慧树知到期末考试答案章节答案2024年中国海洋大学
- DLT 5028.3-2015 电力工程制图标准 第3部分:电气、仪表与控制部分
- 人教版一年级数学上册第四单元《认识图形(一)》(大单元教学设计)
- 四川省城市(县城)建成区排水管网排查技术导则
- (正式版)HGT 6288-2024 聚酯树脂生产用催化剂 三异辛酸丁基锡
- 卡努斯丹之旅-团队协作与跨部门沟通沙盘模拟课程
评论
0/150
提交评论