版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、.PAGE :.;PAGE 德之馨上海新建研发 实验楼工程桩基工程Piling foundation project for Symrise(Shanghai)Co.,Ltd new lab施工方案Construction scheme编制人Prepare the peoele:汤春强审核人The reviewer:朱连忠技术担任人Technical director:汤春强总包单位General contractor:江苏南通二建集团Jiangsu Nantong NO.2 Construction Engineering Group Co.,Ltd施工单位Construction unit
2、:上海极基建立工程Shanghai Jiji Construction Engineering Co.,Ltd编制日期Date:20 Oct. 2021 2021年10月20日Index目 录Chapter 1 Project overview第一章 工程总体概述一、Basis编制根据Chapter2 Construction organization & responsibility第二章 施工管理组织机构及职责一、Construction organization施工管理组织机构Chapter3 Construction deployment第三章施工部署一、Preparation施工前预
3、备任务二、Site plan施工现场总平面图Chapter 4 Construction schedule & guarantee measures of project duration 第四章 施工方案及工期保证措施一、Construction machinery arrangement schedule施工机械配置方案表二、Manpower plan劳动力安排三、Construction progress schedule施工总进度方案表Chapter5 Construction scheme第五章施工技术方案一、Construction process flow施工工序流程二、Tran
4、sportation, hoisting, storage of PHC pile PHC管桩运输及吊装、堆放三、Construction technology of PHC pile PHC管桩的施工技术Chapter6 Main measures for project quality assurance第六章保证工程质量的主要措施一、Project quality goal工程质量目的二、Project organization工程组织机构体系三、Detailed measures for project quality assurance保证工程质量的详细措施Chapter7 HSE
5、control measures第七章平安、环境与安康HSE管理措施一、HSE guidelines, goals HSE方针、目的二、HSE system HSE管理体系三、Contigency plan for construction emergency施工紧急情况下应急预案四、JSA危险性分析报告Chapter 8 As-built documentation submittal第八章提交开工资料Appendix附表一:JSA危险性分析报告Chapter 1 Project overview第一章 工程概述一、Project profile工程概略1.Project name工程称号:
6、Piling foundation project for Symrise(Shanghai)Co.,Ltd new lab德之馨上海新建研发实验楼工程桩基工程2.Project location工程地点:No.30, Lonqiao Road, Pudong District,Shanghai上海市浦东新区陇桥路30号3、Client建立单位:德之馨上海4、Design unit设计单位:The IT Electronics Eleventh Design & research Institute Science and Technology Engineering Co., Ltd信息产业
7、电子第十一设计研讨院科技工程股份5、Jianli监理单位:上海创众工程监理6、General contractor总包单位:Jiangsu Nantong NO.2 Construction Engineering Group Co.,Ltd江苏南通二建集团7、Construction unit施工单位:Shanghai Jiji Construction Engineering Co.,Ltd上海极基建立工程8、Overview工程根本情况:Proposed location is within Symrise(Shanghai)Co.,Ltd, which is grassland. Pr
8、oject 0.000 is relatively to 4.4000m of Wusong elevation. This project adopts static-press piling, which is pre-tensioning method, pile model is PHC 500(100)AB-C80-15,15, total no. of piles is 89, album no. is 10G409 拟建场位置于德之馨上海厂区内,该场地原为绿化草坪。本工程0.000相对于吴淞高程4.400m,本工程采用静力压桩,采用先张法预应力混凝土管桩,管桩型号为PHC 500
9、(100)AB-C80-15,15,总桩数为89根,图集号:。二、Basis编制根据1、Bidding documents and drawings根据提供工程招标文件及招标图纸;2、Technical code for building pile foundationJGJ94-2021;3、Technical code for testing of building foundation pilesJGJ106-2021;4、Code for design of building foundationDGJ-11-2021;5、Code for acceptance of construc
10、tion quality of building foundationGB50202-2021;6、Pretensioned spun concrete piles DBJT08-92-2000;7、 Code for engineering surveyingGB50026-20078、Unified standard for construction quality acceptance of building engineeringGB50300-2021;9、Code for construction project document filing and arrangementGB5
11、0328-2001;10、Specification for welding and acceptance of reinforcing steel barsJGJ18-2021;11、Technical code for safety of temporary electrification on construction siteJGJ46-2005;12、Standard of construction safety inspectionJGJ59-2021;13、Technical code for safety of aerial work on construction siteJ
12、GJ80-91;14、Companys existing equipment, construction condition, technology in previous years for such project construction experience and achievement of the quality, safety, civilization, standardized management regulations, system and the enterprise standard我公司现有设备、施工技术力量情况,往年对此类工程的施工阅历及创呵斥果,有关质量、平
13、安、文明、规范化管理的条例、制度及各项企业规范。Chapter2 Construction organization & responsibility第二章 施工管理组织机构及职责PM工程经理Lianzhon Zhu朱连忠一、Construction organization施工管理组织机构HSE specialist专职平安员马跃军Project engineer工程工程师汤春强Construction manager施工经理汤春强Technology team技术组Document team资料组Surveying team丈量组Quality team质检组Material team资料
14、组Equipment team设备组Engineering team工程组All construction teams各施工班组二、Main construction staffs responsibilities主要施工管理人员职责 1、Project manager工程经理to carry out the relevant state laws and regulations, decrees, entrusted by the general manager, the implementation of company general manager to set up the qual
15、ity policy, policy, target, the contract within the scope of the project quality, time, cost, and will be entirely responsible for HSE management.贯彻执行国家有关的法规、法令,受公司总经理委托,执行公司总经理制定的质量方针、政策、目的,对合同范围内的工程质量、工期、本钱及HSE管理全面担任。The composition of organization planning programs, establish and improve the qual
16、ity assurance system, and guarantee the effective operation.组织谋划工程机构的组成、建立健全质保体系,并保证有效进展运转。control project cost.控制工程本钱。project manager is the first head of project HSE work during project construction, to organize the formulation of the HSE plan, the implementation of the HSE management, pays specia
17、l attention to the HSE management work.工程经理是工程施工期间工程HSE任务的第一担任人,组织编制HSE方案,落实HSE管理人员,抓好HSE各项管理任务。approval to carry out the project construction organization design, make sure to ensure the engineering quality, finish on time to complete the company issued the economic and technical indexes.同意落实工程的施工组
18、织设计,确保工程保质、保量如期完成,按时完成公司下达的各项经济技术目的。organization commissioning acceptance of completion of the project (including middle).组织交工验收含中间交工工程。 2、Construction manager施工经理 Under the leadership of project manager在工程经理指点下:responsible for the construction of converting, director of the construction team and to
19、tal project coordination.担任施工方面的实物量,主管各施工班组和工程总协调。unified command production and coordination of each construction team responsible for the management of the cooperative unit.一致指挥各施工班组的消费和协调任务,担任对协作单位的管理。responsible for organizing the formulation of the project construction plan and the implementati
20、on of production plan.担任组织编制工程的施工方案并实施消费方案。according to production plan organization and implementation of labor, to play equipment check, ensure the equipment in good condition.按消费方案组织劳动力并实施,对进场设备组织检查,确保设备处于良好形状。implement the project HSE plan and the implementation of project HSE measures.贯彻工程HSE方案
21、,实施工程HSE的各项措施。responsible for the progress and quality of construction projects.对工程的施工进度和质量担任。labor induction forensics and safety education work for the assigned project.担任工程劳动力上岗培训取证及平安教育任务。responsible for the completion of project review and follow-up services.担任开工工程回访和蔼后效力任务。3、Project engineer工程
22、工程师在工程经理的指点下:fully responsible for project construction technology and quality management and HSE related technical work.全面担任工程施工的技术和质量管理任务以及HSE的有关技术任务。to carry out national technical regulations, standards, procedures, etc.贯彻执行国家技术法规、规范规程等。to organize the formulation of technical solutions, quality
23、 planning and review, cooperate with the production plan in related technical work.组织编制技术方案、质量谋划并进展审核,配合消费方案进展相关的技术任务。decided not to conform to the treatment scheme of the project.决议不符合工程的处置方案。quality work conference, and make technical decisions on important issues.参与有关质量任务会议,并对重要问题作出技术决策。solve var
24、ious technical problems occurred in field construction.处理现场施工中出现的各类技术问题。 responsible for the management of the interface with the design institute.担任与设计院的接口管理。build project quality assurance system, make its normal operation.建立工程部质保体系,使其正常运转。responsible for organize the formulation of quality planni
25、ng, and to carry out the implementation.担任组织编制质量谋划,并落实实施。responsible for interface management and supervision company.担任与监理公司的接口管理。above shall have the right to report to quality assurance, quality inspection, maintenance and ensure the normal operation of quality control, and seriously endanger the
26、 quality problem有权越级报告质保、质检任务,维护和保证质控任务的正常运转,制止严重危及质量的问题。collect, sort out band data, quality evaluation system.搜集、整理交工资料,完成质量评定任务。for completed project quality review and follow-up service work.参与开工工程质量回访和蔼后效力任务。 4、HSE specialist专职平安员职责familiar with and master safety production dynamic, collection
27、and the dyke construction site HSE information, timely report to the HSE manager.熟习和掌握平安消费动态,搜集和反溃施工现场HSE信息,及时向HSE经理汇报。check construction personnel at the scene at any time is properly carried out safety operation procedures and to observe the safety rules and regulations, to prevent illegal behavio
28、r随时在现场检查施工人员能否正确执行了平安操作规程和遵守平安规章制度的情况,制止违章行为。check and maintain the good scene safety facilities, to ensure the reliability of the site safety facilities.检查和维护好现场的平安设备,确保现场平安设备的可靠性。shall have the right to stop does not comply with the safety rules of construction personnel and mechanical equipment.有
29、权制止不符合平安规定的施工人员和机械设备上岗。organization staff post production safety education and shift safety activities.组织员工的岗位平安消费教育及班组平安活动。If any accident, rescue the wounded, protect the scene and immediately report, assist the accident investigation and analysis.发惹事故,抢救伤员,维护现场并立刻报告,协助事故调查分析。Chapter3 Construction
30、 deployment 第三章 施工部署一、Preparation施工前的预备任务 1、All procedures to be done per requirements按施工要求办理各种施工手续 Positively related to construction, the total package units to deal with the construction procedures, such as construction personnel safety education, ensure the legitimacy of the construction, make t
31、he project smoothly.积极与建立、总包单位办理有关的施工手续,如施工人员平安教育等,保证施工的合法性,使工程顺利开工。 2、Tech. preparation仔细做好技术预备任务(1) under the organization of the project manager, familiar with drawings carefully and deeply understand the design intent and design requirements, questions and Suggestions to the design drawings, and
32、 in conjunction with the owner, supervision and design institutes, the blue prints.the design so as to guide the construction.在工程经理的组织下,仔细熟习图纸,深化了解设计意图及设计要求,提出对设计图纸的疑问和建议,并会同业主、监理和设计院进展图纸会审,从而指点施工。(2) according to the requirements of construction actively equipped with all kinds of management inform
33、ation, technical data, construction specifications, acceptance criteria, under the organization of the project manager for the relevant construction technical clarificaiton work按施工要求积极配备各类管理资料、技术资料、施工规范、验收规范,在工程经理的组织下进展各有关施工技术交底任务。 (3) Carry out all tech. requirements贯彻施工方案的各项技术要求。 3、Equipments & ma
34、terial preparation仔细做好设备、资料的供应任务Do a good job, the supply of equipment, material is the basis to ensure the project completed on time.According to the project schedule, project department, plan well component product and material approach as planned by the materials department prepares materials pro
35、curement, the project according to the request of the construction unit choose inspection qualified pipe pile factory products, to provide qualified products on time with good quality.做好设备、资料的供应任务,是确保工程工程按时完成的根底。根据工程进度要求,工程部做好构件产品和资料的进场方案,由资料部门按方案进展备料采购,本工程根据建立单位要求选用调查合格的管桩厂产品,保质保量按时提供合格产品。Equipment
36、 maintenance and inspection by the regulation, check it again for main equipment before entry to ensure the performance of play equipment is in good condition.设备按规定维修、检验,进场前对主要设备再次检查确认,以保证进场设备处于良好的性能形状。 4、Construction electricity preparation仔细做好施工用电预备任务 The project plans to input 1 YZY - 300 type pi
37、le machine, total power consumption of not less than 120 kw.本工程方案投入1台YZY-300型桩机,总用电量不少于120kw。 Construction units to provide the total power in construction planning red line within the scope of my project department from the total package units to provide construction distribution box, and then supp
38、ly power to piling area construction power cable will be used for access to the site to establish distribution box, with a cable from the construction of electricity, electricity box to set up a good grounding device and the leakage switch, prevent to get an electric shock.建立单位提供总电源位于施工规划红线范围内,我工程部从
39、总包单位提供的施工配电箱引出,然后向打桩区域供电,采用电缆将施工用电接入到现场增设的配电箱,再用电缆接到各施工用电点,电箱要设置良好的接地安装及漏电开关,防止触电。 Site construction electricity lines and distribution box set adopts three-phase five wire system, construction of electricity power box location layout.现场施工用电线路及配电箱设置均采用三相五线制,施工用电的电源箱位置见平面布置图。 5、Surveying preparation丈
40、量放样的预备任务 According to the level of the construction unit to provide the coordinates of control points and control points, in strict accordance with the design and construction drawings, axis control point positioning in J2 theodolite.根据建立单位提供的座标控制点和水准控制点,严厉按设计施工图纸,用J2经纬仪进展轴线控制点定位。Axis to the axis of
41、 the piles with solid protection, then every axis of each axis arranged according to the axis of the pile pile, with J2 theodolite measuring out the pile engineering samples, requirements have to be lofting 6 round steel, the error shall not be greater than 1 cm.对现场轴线的各个轴线桩进展稳定维护,再根据轴线桩布设各条轴线的各分轴线桩,
42、用J2经纬仪测放出各工程样桩,要求要6圆钢进展放样,其误差不得大于1cm。Axis positioning also completes the review work, each time to review the measurement data should be archived for future reference, and please build supervision and owner unit check, and make the book visa face to face.轴线定位还做好复核任务,每次复核丈量数据应存档备查,并请建监理及业主单位核验,并做好书面签
43、证。 6、Site preparation场地预备1Construction site must be flat topography, venue is not flatness should be 1%, construction areas around open drain, field with blind ditch, asking for a flat, the rain stopped not water施工现场地势必需平坦,场地不平整度应1% ,施工区域周围开设排水沟,场内设盲沟,要求到达雨停场平,不积水。二、Site plan施工现场总平面布置表示图 1、in accord
44、ance with the total package units construction layout plan, ready to live life, construction of temporary facilities.按照总包单位施工平面布置规划,做好现场生活、施工的暂时设备。 2、considering of the need to transport goods pile, the construction site to north and south road, the goods can transport to the whole construction area
45、.Road turning radius shall meet the operation of the truck.思索到商品桩运输的需求,在施工现场道路要南北向贯穿,使商品桩能运输到整个施工区域。道路的转弯半径应满足载重车的运转。Chapter 4 Construction schedule & guarantee measures of project duration 第四章、施工方案及工期保证措施一、 Construction machinery arrangement schedule施工机械配置方案表 SEQ序号NAME称号MODEL型号UNIT单位QTY数量COMMENT备注1
46、Piling machine打桩机YZY-300台1For piling打桩主机2Truck crane汽车吊50T辆1Load & unload piling machine装、卸桩机3Welding machine焊机NBC-400台2Pile following接桩4Theodolite经纬仪J2台2Setting out放样、校正垂直度5Level水准仪S3台1Control elevation控制标高6Tool box工具箱个1Store tools储放桩机配件工具7Tape50m卷尺把1Measuring丈量8Distribution box配电箱只1Matched cable电缆
47、配套9Pile follower送桩杆500根11 spare usage送桩备用1根1Piling machine arrangement桩机安排:a 300T static pressure machine will be adopted for construction, equipped with pile follower本工程安排一台300吨静压桩机进展施工,配置相应的送桩杆。2Construction progress plan施工进度方案:commence date is set on 25 Oct,2021 for time being, details shall be u
48、p to written notice of tender, planned duration is 10 calendar days开工日期暂定为2021年10月25日,详细以建立单位书面通知为准,方案工期为10日历天。二、Manpower plan劳动力安排方案 Seq序号Type of work工 种Qty人 数Seq序号Type of work工 种Qty人 数1PM工程经理17HSE specialist安 全 员12Tech. director技术担任18Documenter资料员统计13Forman机 长19Electrician电工、机修14Construction engin
49、eer施 工 员110Instructor指 挥 员15Quality specialist质 量 员111Welder电 焊 工26Measureman测 量 员112Operator机 操 工1PAGE PAGE 三、Construction progress schedule施工总进度方案表Construction progress schedule施 工 进 度 计 划 表序Seq号Content工程内容Qty数量根 天数Day任务内容ContentDuration 施工天数21011Mobilization and assembly桩机进场组装Preparation预备任务2天day
50、2PHC-AB500(100)89Piling工程桩施打 10天day3Disassembly桩机装配Demobilization桩机撤场 1天dayNote阐明:一:This plan is according to the needs of the bidding documents and design documents, piling progress to meet the pile machine production and overall progress as a premise for compilation本方案根据招标文件及设计文件要求进展编排,打桩进度以满足桩机日产
51、及总体进度为前提进展编制。二:1 piling machine is proposed, commence date is 25 Oct.2021for time being, details shall be up to written notice of tender本工程拟安排一台桩机进展施工,开工日期暂定为2021年10月25日,详细以招标单位书面通知为准。三:Pile no. and spec shall be in accordance with construction drawing, planed duration is 10 calendar days桩数量、规格以设计施工
52、图为准,进度方案仅作表示,方案工期为10日历天。PAGE PAGE 36 Chapter5 Construction scheme 第五章 施工技术方案一、Construction process flow施工工序流程图PHC pile sinking process PHC管桩沉桩工艺流程Construction site plan施工现场平面布置和处置Mobilization, assembly of machinary施工机械进场、组装和就位Prefabrication工厂预制PHC桩Surveying丈量放线、定桩位Demobilzation退场Pile inspection桩身检查
53、Unqulified不合格Inserting插桩 Qualified合格Perpendicularity inspection桩身垂直度桩位校正 不合格Unqualified Sinking沉桩 合格Qualified焊接设备及资料预备桩身垂直度校正Pile following接桩Welding接桩焊接Weld joint dealing焊缝处置Welding inspection焊接质量检验 Unqualified不合格Keep sinking继续沉桩 Qualified合格If pile following能否送桩 是YesPile follwing送桩Sinking report出沉桩记
54、录报告Pile following to design elevation桩送至设计标高Pull out pile follower, cap拔出送桩器、填盖桩孔Elevation of pile top桩顶标高丈量二、PHC piling route PHC管桩打桩线路Bitmap according to the design of pile, the engineering pile foundation according to decorate a pile machine, 3 root pile test it first, after the play, according t
55、o the total floor plan, location close to the building of engineering pile construction first, try to reduce the vibration and compaction pile due to the negative impact of the surrounding facilities arrangement principles for piling process根据设计桩位图,本工程根底桩施打布置1台桩机,3根试桩先施打,施打终了后,根据总平面图,接近建筑物位置的工程桩先施工,
56、尽量减少因打桩产生的震动和挤土对周围设备的不利影响为打桩流程安排原那么。三、Transportation, hoisting, storage of PHC pile PHC PHC管桩的运输及吊装、堆放This foundation piling engineering of the main component is: choose jiashan county new suitable prefabricated company production of PHC pipe piles, models for PHC - 500 (100), AB, as shown in the pi
57、le construction drawing, the number for 89.本根底打桩工程的主要构件是:选用嘉善县新顺预制构件公司制造的PHC管桩,型号为PHC-500100AB,详见桩位施工图,数量为89根。Pile of lifting, transport and storage requirements to meet the technical specification for the building pile foundation JGJ94-2021 and the pre-stressed concrete pipe pile atlas of the 10 g4
58、09 regulation. Because of PHC pipe piles for the factory, the manufacturer in supply transportation and pile driving construction schedule and supply plan, must work closely, ensure supply quantity and quality of pipe pile.桩的起吊、运输及堆放的要求要满足JGJ94-2021及图集10G409中的规定。因PHC管桩为工厂预制,厂方在供应运输方面与打桩公司的施工进度及供应方案相
59、吻合,必需亲密配合,保证管桩的供应数量及质量。1、Requirements进桩要求:Pile driving unit materials and plant materials, both sides must be opened according to the driving unit into a pile of schedules, strictly implement for pile and ensure timely supply of pipe pile. Construction personnel to engage in serious appearance to ap
60、proach the pile quality check and inspection of quality information, nonconforming product shall be determined to return.打桩单位资料员与桩厂资料员,双方必需按打桩单位开出的进桩方案表,严厉执行供桩,保证管桩的及时供应。施工人员要对进场的桩质量进展仔细的外观检查及质量资料的检查,不合格品应坚决退回。2、Pile inspection requirements管桩验收资料要求:Material Certificate and material test report原资料质量合
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 会计人员的职业成就与反思计划
- 信阳师范大学《大学物理》2022-2023学年第一学期期末试卷
- 地震应急避险技能培训
- 《机械零件加工》立项改革课程结题申报表
- 新余学院《英语语音》2021-2022学年第一学期期末试卷
- 西华大学《外国美术史》2021-2022学年第一学期期末试卷
- 六年级校园安全我知道
- 西北大学《光电子学》2022-2023学年第一学期期末试卷
- 西安邮电大学《信息系统分析与设计》2021-2022学年第一学期期末试卷
- 汽车维护与保养 课件 项目1 汽车维护基础认知
- 项目报备合同范本
- 药剂科考核标准(临床药学室)
- 小班数学《帮瓢虫找家》课件
- 上海市华二附中2024届高一上数学期末预测试题含解析
- 论教育在人的发展中的主导作用
- 现代化工HSE技能大赛考试复习题库大全-中(多选题汇总)
- 勿忘国耻国家公祭日主题班会课件
- 七年级语文上册期末测试卷及答案
- 企业审计大数据分析方法及案例
- 2023届上海市高考各区一模语文考试试卷汇编(附答案15套)
- 冀美2011版二年级美术下册《壮美的长城》教案及教学反思
评论
0/150
提交评论