龙门吊安拆专项施工方案
编制人:
审核人:
审批人:
日期:
0
目录
第一章编制说明...............................................................................................................1
1.1编制依据...............................................................................................................1
1.2编制原则...............................................................................................................2
1.3编制范围...............................................................................................................2
第二章工程概况.................................................................................................................3
2.1工程基本情况.......................................................................................................3
2.2工程地质概况.......................................................................................................4
2.3气象、水文...........................................................................................................4
第三章施工安排...............................................................................................................5
3.1项目管理组织.......................................................................................................5
3.2项目管理目标.......................................................................................................5
3.2.1工期目标.....................................................................................................5
3.2.2安全目标.....................................................................................................5
3.2.3文明施工目标.............................................................................................5
第四章施工计划...............................................................................................................6
第五章施工准备与资源配置计划...................................................................................6
5.1施工准备...............................................................................................................6
5.1.1技术准备.....................................................................................................6
5.1.2施工准备.....................................................................................................7
5.2龙门吊主要部件技术参数...................................................................................8
5.3资源配置计划.......................................................................................................8
第六章施工方法及工艺要求.........................................................................................10
6.1安装流程.............................................................................................................10
6.2轨道安装.............................................................................................................11
6.2.1轨道基础...................................................Error!Bookmarknotdefined.
6.2.2走行轨道安装...........................................................................................11
6.3龙门吊组装.........................................................................................................13
6.3.1主梁及支腿的组装...................................................................................13
6.3.2大车的组装...............................................................................................14
6.3.3小车的组装...............................................................................................14
6.4支腿吊装.............................................................................................................14
6.4.1钢性支腿吊装工序...................................................................................14
6.4.2柔性支腿吊装工序...................................................................................17
6.5主梁吊装.............................................................................................................17
6.6安装天车.............................................................................................................20
6.7附属设施的吊装.................................................................................................21
6.8电气安装.............................................................................................................21
6.9临时设施拆除.....................................................................................................22
6.10试车...................................................................................................................23
6.11龙门吊拆除.......................................................................................................24
6.11.1拆除顺序.................................................................................................24
6.11.2安全技术交底.........................................................................................24
6.11.3场地要求.................................................................................................24
6.11.4拆解人员.................................................................................................25
6.11.5主要起重设备、机具的配置.................................................................25
6.11.6缆风绳及锚固.........................................................................................26
6.11.7起重小车吊装拆除.................................................................................26
6.11.8刚性支腿副支腿(包括电气控制柜及钢爬梯)拆除.........................26
6.11.9刚性支腿主支腿和柔性支腿固定.........................................................27
6.11.10主梁吊装拆除.......................................................................................27
6.11.11刚性支腿主支腿吊装拆除...................................................................27
6.11.12柔性支腿吊装拆除...............................................................................27
6.11.13大车走行拆除.......................................................................................27
6.11.14主梁和支腿解体...................................................................................27
6.11.15清点入库...............................................................................................27
第七章安全检查及验收.................................................................................................28
7.1龙门吊整体安全检查及验收内容.....................................................................28
7.2吊钩安全检查及验收内容.................................................................................28
7.3滑轮与护罩安全检查及验收内容.....................................................................29
7.4制动器安全检查及验收内容.............................................................................29
7.5安全防护装置安全检查及验收内容.................................................................30
7.6架体安全检查及验收内容.................................................................................30
7.7传动系统安全检查及验收内容.......................................................................31
7.8龙门吊验收要求.................................................................................................31
7.9龙门吊安全检查记录表.....................................................................................32
7.10龙门吊验收程序及验收人员...........................................................................32
第x章施工安全保证措施.............................................................................................33
8.1组织保障.............................................................................................................33
8.1.1应急组织机构与职责...............................................................................33
8.2技术措施.............................................................................................................34
8.2.1技术要求...................................................................................................34
8.2.2安全技术措施...........................................................................................35
8.3龙门吊施工应急预案.........................................................................................35
8.4危险源辨识及危险源原因分析.........................................................................36
8.4.1人为因素...................................................................................................38
8.4.2施工临时用电...........................................................................................39
8.4.3机械设备...................................................................................................40
8.4.4高空作业...................................................................................................41
8.4.5电焊与气焊安全保证措施.......................................................................42
8.5应急救援措施.....................................................................................................43
8.5.1物体打击急救措施...................................................................................43
8.5.2机械伤害急救措施...................................................................................43
8.5.3高处坠落急救措施...................................................................................44
8.5.4触电事故急救措施...................................................................................45
8.6应急响应.............................................................................................................46
8.6.1应急救援程序...........................................................................................46
8.6.2现场保护...................................................................................................47
8.6.3警报与紧急公告.......................................................................................47
8.6.4事态检测...................................................................................................47
8.6.5警戒与治安...............................................................................................48
8.6.6人群疏散与安置.......................................................................................48
8.6.7医疗与卫生...............................................................................................48
8.6.8公共关系...................................................................................................48
8.6.9应急救援人员的安全...............................................................................48
8.6.10应急终止与现场恢复.............................................................................49
第九章计算书及图纸.....................................................................................................49
9.1龙门吊荷载基础计算.........................................................................................49
9.2龙门吊图纸.........................................................................................................49
第一章编制说明
1.1编制依据
表1.1编制依据
序号类别文件名称编号
1中华人民共和国安全生产法
2中华人民共和国环境保护法
3国家法律建设工程质量管理条例
法规、行
4危险性较大的分部分项工程安全管理规定
政文件
住房城乡建设部办公厅关于实施《危险性较大的分
5
部分项工程安全管理规定》有关问题的通知
6交通部关于加强公路工程标准规范工作的若干意见
7《起重机械安全规程第5部分:桥式和门式起重机》GB6067.5-2014
8《起重机设计规范》GB/T3811-2008
9《通用门式起重机》GB/T14406-2011
10《起重设备安装工程施工及验收规范》GB50278-2010
国家行业
11《建设工程施工现场供用电安全规范》GB50194-2014
规范
12《施工现场临时用电安全技术规范》JGJ46-2005
13《公路工程施工安全技术规范》JTGF90-2015
14《建筑机械使用安全技术规程》JGJ33-2012
15CJJ37-2012
16设计文件《合同协议书》
17合同《两阶段设计图》
招投标文
18《招标文件》及答疑
件
19
企业管理
20中国建筑企业形象视觉识别规范手册
文件
21中建股份《项目管理手册》2015年修订版
企业技术局基字[2018]438
22线性基础设施项目机构设置及人员配置指引
标准号
1
序号类别文件名称编号
23
24
25《施工组织设计》
其他
26《质量安全标准化工地建设实施方案》
1.2编制原则
(1)安全第一原则
以人为本,坚持安全发展,坚持安全第一、预防为主、综合治理。
(2)坚决执行规范、规程原则
贯彻执行各项技术标准、安全技术规程,执行业主针对本工程建设制定的各项安全
管理办法、细则和规程。确保龙门吊安装质量,为工程顺利进行提供机械保障,以适应
安全生产和施工组织安排的要求。
(3)杜绝事故原则
有效对龙门吊安装、拆除过程实施监控,杜绝一般及以上安全事故的发生。
1.3编制范围
表1.3龙门吊配置情况
序号型号数量备注
1MG100/10T-36M100t2
2台龙门吊布置于主线标准箱梁段,详见图1.3平面布置。
2
图1.3平面布置
第二章工程概况
2.1工程基本情况
快速路工程(一期)是一环九联”中的“一环四联”,由任兴路快速路、济宁大道快速路、
西外环快速路和宁安大道快速路4条快速路及其延伸线组成。一期工程快速路总长约
84km,其中“一环”中心城区快速路环线长度约42.3km,“四联”快速路射线总长约
41.7km。快速路主路采用双向6车道,设计速度80km/h;环线内辅路采用双向6车道,
环线外辅路双向6-8车道布置,设计速度40-50km/h。拟新建高架快速路长度约42.9km、
地下道路快速路长度约6.3km、地面快速路长度约34.8km、该拓建地面辅路长度约
84km。推荐实施互通立交8座,配套建设菱形立交12处,实施快速路出入口匝道共34
对。
由我部负责施工的总承包七标段位于山东任城大道。合同段西起任城大道/新华路
(RK22+721),东至任城大道建设路(RK26+140),长度约3.4km,辅路范围与主路范围相
同。主路高架在任城大道上采用整幅式高架布置于老路中央分隔带。本标段范围内共设
置济安桥路高架出入口匝道2对、共青团路高架出入口匝道1对。
。
3
图2.1项目地理位置(蓝线)
2.2工程地质概况
.3m。地貌单元为冲积洪积平原。场地内存在对工程安全有影响的采空区、地面沉降
等不良地质作用,未发现影响地基稳定性的古河道、古墓等对工程不利的埋藏物。场地
地层由第四系全新通~中更新新冲积成因的黏性土、粉土及砂土组成;杂填土及素填土层;
填筑成分为粉质黏土、局部夹杂碎砖块、碎石子等,层厚0.3~8.0m;粉质黏土:灰黄色~
褐黄色、黑灰色,可塑,含铁锰质氧化物,偶见姜石,局部夹黏土薄层、粉土、砂土薄
层,中等压缩性,干强度中等,韧性中等,层厚0.3~9.7m,底层深度2.6~11.9m;黏土层:
灰褐色~灰黑色,含铁锰锈斑,有机质,夹少量姜石,长石,含铁锰质团块,砂质不纯,
偶见小颗粒姜石,中等压缩性,底层深度13.8~21.0m;地下水:场地地下水主要为第四
系空隙潜水和微承压水,地下水埋深6.5~12.6m主要贮存于个粉土、黏土层中,主要接
受地表水侧向径流及大气降水的下渗补给,排泄途径主要为蒸发和地下径流,各含水层
主要靠地下径流相互补给。根据水质分析资料显示,拟建场地地基对混凝土结构具有微
腐蚀,对钢筋混凝土中的钢筋具有弱腐蚀性。
2.3气象、水文
m(1988年),极值比达2.99倍。降水量年内分配不均,降水主要集中在汛期,6-9月
份降水量约占年降水量的70%。济宁地区年内1月最冷,平均-0.6℃,7月最热,平均
27.0℃。历年平均气温14.2℃,极端最高气温40.30℃(1996年7月19日),极墙最低气温
-18.1℃(1967年1月25日)。多年平均蒸发量为1768mm,5-7月份,月蒸发量最大为
4
250-300mm;12-2月份,月蒸发量小50m
本项目沿线属淮河流域南四湖水系,水系发育。
第三章施工安排
3.1项目管理组织
表3.1项目管理组织
序号职务姓名备注
1项目经理王国磊负责龙门吊安拆全面工作
2技术负责人陈帅负责施工队对安拆方案执行的监督工作
3生产经理范俊强按照龙门吊安拆专项方案进行现场管理
4安全总监王思农负责龙门吊安拆安全监督工作
5质量总监叶久化负责龙门吊安拆人员安全交底及培训工作
6工程技术部部长杨广亭负责对龙门吊安拆人员工作监督
7物资工程师张灵志负责对龙门吊安拆设备调度工作
8测量负责人王中耀负责对龙门吊安拆过程实时监控
9施工现场负责人潘亮现场管理
3.2项目管理目标
3.2.1工期目标
进度满足业主的工期目标。
3.2.2安全目标
。
3.2.3文明施工目标
控制噪声、粉尘、固体废弃物、有毒有害气体、污水污染,排放达标;无严重扰民;
无环保事件发生。
5
第四章施工计划
根据总体施工计划安排,龙门吊安装计划开始时间为2023年7月10日,拆除时间
为2023年9月20日。
第五章施工准备与资源配置计划
5.1施工准备
5.1.1技术准备
(1)地基承载力必须满足要求,我项目部已对对龙门吊基础数据进行了验算,结
果符合要求。附件1《龙门吊轨道基础计算书》。
(2)对参加拼装及拆除施工人员进行安全技术交底。
龙门吊简图如下:
图5.1.1-1龙门吊
龙门吊主要有主梁、支腿、上横梁、下横梁、起重小车及大车运行机构等部件组成。
主梁两侧均设有悬臂,便于从跨中转运物品到跨外。100t龙门吊梁高23m。
6
图5.1.1-2龙门吊
1--电气部分2---主梁3----天车4---小车(5/10吨电葫芦),5---刚性支腿
图5.1.1-3龙门吊吊装示意
5.1.2施工准备
(1)布设龙门吊拼装、拆除安全施工警戒范围、设置各类施工警示标志。
(2)龙门吊轨道基础做好防、排水设施,轨道基础不得有雨水浸泡。
(3)龙门吊拼装、拆除起重机械用吊装钢丝绳等经检查合格,各类辅助钢丝绳使
7
用前严格检查,起重机械操作人员持证上岗。
(4)吊装指挥人员具备多年吊装经验,且持证上岗,吊装现场设专人安全监护。
(5)配备足够的安全防护用品安全带、安全绳等,防护用品验收合格。
(6)龙门吊主梁重为24t,吊装用2台120t汽车吊。
(7)任城大道主线范围内场地平整宽敞,可以用作组装场地。
5.2龙门吊主要部件技术参数
表5.2-1一台100t龙门吊各部件数量及重量表
序号部位数量单件重量(t)
1主梁124
2支腿28
3小车15
表5.2-2100吨龙门吊技术性能参数表
名称起升机构名称运行机构
项目主提升副提升项目小车运行机构大车运行机构
起重量(t)100/轨距(mm)250036000
起升速度(m/min)0.9/运行(m/min)6.98.9
工作级别M3/工作级别M3M3
缓冲行程
最大提升高度(m)23/40120
(mm)
三相交流电50Hz
电源钢轨型号35x65P50-QU120
380v
车轮直径
结构6W(37)-21.5-155i400X120400X150
(mm)
钢丝绳
最大轮压
支数16245295
(KN)
BLD220-BLD270-
型号型号YEZ100L1-4YEZ112L1-4
8787电
减速器
动功率
传动比i87872X2.2KW2X4.5KW
机(KW)
卷扬机JM6.3t转(r/min)14001400
限位开重锤LX10-31
限位开关LX10-12LX10-12
关旋转LX7-1
5.3资源配置计划
表5.3-1龙门吊安装施工机械设备配置
8
序号设备名称数量备注
1汽车吊2台120t
2全站仪1台徕卡
3水准仪1台
4500V兆欧表1台
5手拉葫芦8件
6万用电表1台
750m钢卷尺1把
8千斤顶4台
91m钢直尺1把
10交流电焊机2台
11100mm塞尺1把
12气割设备2套
13框式水平仪1件
14切割机1台
150~200mm游标卡尺1把
16角向磨光机2台
170~200mm弹簧称1把
18安全带5条
19手虎钳2把
20力矩扳手2把
表5.3-2劳动力配置计划
序号名称数量备注
1管理人员2
2信号工2持证上岗
3起重工4持证上岗
4安拆工8持证上岗
5电工1持证上岗
6合计17
9
第六章施工方法及工艺要求
6.1安装流程
施工准备工作地基处理
走行轨道安装
走行轨道固定
支腿的地面组装支腿的整体吊装及树立缆风绳及地锚的固定
主梁的地面组装主梁、大车的整体吊装
小车的地面组装起重、小车的整体吊装
安装机电系统安装夹轨器
拆除各种临时设施安装各种安全设施
龙门吊试吊
龙门吊安装完成
图6.1龙门吊安装流程
表6.1龙门吊各部件安装标准
序号项目内容允许误差(mm)
主梁高度差±10
对角线误差±5
1主梁轨道接缝高差0.5
轨道接缝间隙≤5
主梁顶面高差5
横向错位差≤1
2小车轨道接缝高差≤1
轨道接缝间隙≤2
支腿间距误差2
支腿垂直度误差≤3
3支腿
支腿对角线误差≤5
横梁顶面高度误差2
10
6.2轨道安装
6.2.1轨道基础
龙门吊轨道基础采用装配式型钢轨道基础,轨道梁下布设I14工字钢焊接成的框架,
通过在工字钢上焊接夹轨钢板与轨道连接。为防止地面沉降工字钢下满铺宽100cm厚
15mm钢板,两条龙门吊基础间距36m。具体尺寸如图6.2.1-1、6.2.1-2所示。
图6.2.1-1龙门吊基础横断面
图6.2.1-2龙门吊基础平面
6.2.2走行轨道安装
待龙门吊基础安装完成后,再进行行走轨道的安装。龙门吊支腿走行轨道采用钢轨,
走行轨道采用50kg/m钢轨。走行轨道的安装,应注意做好走道基础的竣工测量,确保其
轨道的间距、轴线等无误,轨道安装应控制轨道的平顺、轨道接头处的顺接,并利用基
础预埋件牢固固定轨道,同时在轨道两端尽头设置限位装置。
轨道应可靠固定,螺栓不得松动,压板不得变形,轨面不得有裂纹、疤痕和影响安
全运行等缺陷。具体安装标准以相关规范要求为准。
轨道基础按要求铺设完成,确定轨道中心线和基础水平距离。轨道由安装负责人、
11
技术负责人、质检部门三级已复测验收。安装前应测量轨道的实际情况,选择最佳位置
作为门式起重机的安装基准位置。使用工具:水准仪、钢卷尺、弹簧秤、塞尺,具体检
测要求如下。
(1)大车轨距的极限偏差10mm。
(2)轨道接头间隙不大于2mm,轨道接头高低差及侧向错位不大于1mm。
(3)轨道顶面对其设计位置的纵向倾斜度不大于3/1000,全程内高差不>10mm。
(4)轨道顶面基准点的标高相对于设计标高允差±10mm。
(5)同一截面内两平行轨道的标高差,不大于10mm。
(6)两平行轨道的接头应错开,其错开距离不应等于起重机前后车轮的基距。
(7)轨道上的车挡在吊装前装好,同一跨端的车挡与起重机缓冲器均应接触。
图6.2.2-1轨道固定
12
图6.2.2-2轨道夹板器
6.3龙门吊组装
6.3.1主梁及支腿的组装
主梁在地面组装完成,然后整体吊装。主梁一般采用销轴连接,现场施工只需将销
轴打入主梁上下弦的阴阳接头中,在打销子时应调整好主梁的直线度,各主梁的高低不
能相差10mm,绝对不能将销轴用蛮力打入。最后组装好的主梁的直线度、上拱度、旁
弯值、悬臂端上翘度、对角线相对差等均应符合设计及验收要求。
主梁上的平台构件也宜在地面就组装好,并应留出位置进行吊装时绑扎钢丝绳用,
在绑扎钢丝绳处应设好保护钢丝绳的包角措施。
支腿在施工场地进行拼装完成。
图6.3.1龙门吊构件地面组装
13
6.3.2大车的组装
在厂内安装好的大车现场稍经调整即可安装上大车轨道上,由于超长而分开运输的
大车,则需要重新安装,组装完成后应做以下检查:
(1)检查基准;
(2)检查车轮端面的水平偏斜;
(3)车轮找平(包括直线度、垂直度及同位差)。
6.3.3小车的组装
在厂内安装好的小车到现场稍经调整即可安装上小车轨道上,由于超宽而分开运输
的大吨位或特殊起重机的小车,则需要重新安装,应检查小车轨道、小车车轮的平行度、
垂直度及同位度,是否符合有关技术要求,具体规定见以下:
小车轨道要求:轨道在接头处高低差不大于1mm,间隙不大于2mm,横向错位差不
大于1mm。
6.4支腿吊装
6.4.1钢性支腿吊装工序
(1)吊装前把选用6×37-1550-φ17.5型号钢丝绳(缆风钢丝绳)在支腿上端设
定点固定好,己备支腿立起后能快速将支腿固定;
(2)选用直径6×37-1670-φ36,长度为2m钢丝绳2根(吊装支腿用),将钢丝
绳用卸扣固定在支腿上端吊耳上固定好,检查卸扣与钢丝绳安装是否牢固可靠。吊装前,
应进行试吊,由指挥人员发出起吊信号,把刚性支腿吊离开地面0.3m,静止悬2分钟,
检查钢丝绳以及地基是否存在异常,检查完毕无异常后,然后用120t汽车吊为主要吊装
设备,将钢性支腿吊装就位,吊装过程中严禁拖拉起吊;
(3)调整支腿垂直度,垂直度误差偏向轨道内侧;
(4)将缆风绳的一端拉向地锚用3T手拉葫芦与承台预埋的钢筋连接,另一端用
1.8*1.6*2m的混凝土块固定;
(5)缆风绳角度应控制在45度。
(6)缆风绳受力计算:
按支腿重心偏移1m计算,
支腿最大重量8t,高度23m。
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 隋唐课件 教学课件
- 2024至2030年中国合成石回焊炉治具行业投资前景及策略咨询研究报告
- 2024至2030年中国热泵热水器压力开关行业投资前景及策略咨询研究报告
- 2024至2030年起动链项目投资价值分析报告
- 2024至2030年中国无毛边四方针行业投资前景及策略咨询研究报告
- 2024至2030年挂模铝条项目投资价值分析报告
- 2024至2030年中国全自动充气控制盘行业投资前景及策略咨询研究报告
- 2024至2030年包装管项目投资价值分析报告
- 2024年中国鬃刷市场调查研究报告
- 2024年中国脉冲宽度控制器市场调查研究报告
- 2020年厦门轨道交通地铁2号线列车脱轨应急救援综合演练脚本1009
- 装饰工程施工重难点分析和解决措施
- 肿瘤科头颈部肿瘤介入治疗技术操作规范
- 战时心理应激与心理救护
- 自动化设备调试规范
- 2023年北京大学深圳研究生院教务处招聘1人笔试参考题库(共500题)答案详解版
- 第二单元-社会服务-主题活动三《走进盲人世界》-教案
- 外国文学研究方法(视频课)智慧树知到课后章节答案2023年下湖南师范大学
- 社区食堂投投标方案(技术标)
- 物流公司安全生产责任制
- 品类创新:成为第一的终极战略
评论
0/150
提交评论