1、Method Statement for Double Surface Dressing rev 04UPGRADING PERAMIHO JCT TO MBINGA ROAD TO BITUMEN STANDARDMethod Statement for Double Surface DressingA. Personnel: Team leader 1 (Wang Shizheng)Mr. Zhang will be responsible for the works and all instruction issued on site could be directed to him.

2、He has a good command of English. He is able to brief in detail on this method statement before the works commence.1. Chainman 32. Surveyor 13. Chip Spreader Operator 14. Rubber Roller Operator 25. Mechanical Sweeper Operator 16. Dump Truck Driver 47. Bitumen Distributor Operator 18. Transport Light

3、 Truck Driver 19. Pick-up Driver 110. Flagman 211. Experienced Labor 8B. Equipment 1. Chip Spreader 22. Mechanical Sweeper 13. Rubber Roller 24. Bitumen Distributor 15. Dump Truck 46. Transport Light Truck 17. Pick-up 1Two thousand meters of half lane width are expected to be placed each day, that i

4、s to say, one thousand meters of full lane width per day.C. Method StatementLayer pavement method is adopted for double surface dressing. Usually by this method, a layer of bitumen shall be first spread followed by the spreading of a layer of aggregate. The construction procedure of double surface d

5、ressing is indicated below:Preparation of surfaceInitial rolling1st Layer:AggregateRolling1st Layer: 80/100 Bitumen2nd Layer: 80/100 Bitumen2nd Layer:AggregateBroom dragand final rollingThe details of procedure as following:1. Preparation of surfaceAhead of double surface dressing construction, clea

6、n surface should be prepared so as to expose the majority of aggregate. Meanwhile, bumpy and rough road sections must be repaired and leveled. The weatherglass will be used to monitor the temperature of the road surface, whenever the temperature of the road surface falls below the temperature that b

7、e depicted in section 4304(a) of the Standard Specification for Road Works, no blinder shall be sprayed. No bituminous work shall be done during foggy or rainy weather. Where newly constructed base or shoulder areas are to be sealed, the surfaces shall be checked for compliance with the surface tole

8、rances and all other requirements specified. Any portions that do not meet these requirements shall first be either corrected or removed and reconstructed before they are sealed.The road will be demarcated the area of the primed base to be sealed by means of setting out wire lines down each edge of

9、the specified seal width.2. Spreading of bitumenAfter the full seepage of the prime coat bitumen, the first layer of bitumen will be spread following the requirement of specification. The bitumen should be spread homogenously without the phenomenon of blank space or accumulation. Spreading length of

10、 bitumen shall corporate with the capacity of aggregate spreader and the spreading of aggregates long time after spreading of bitumen must be avoided. Concrete kerbing and channeling as well as any other structures adjacent to the road shall be protected against staining by bitumen being sprayed. Th

11、e test for spreading rate of the binder and aggregates shall be done before spreading works, the actual rates of application of binder and aggregate to be used in the construction will be determined by the engineer after finishing the test. The bitumen will be heated by bitumen heating plant in camp

12、 and be transported to site by the bitumen distributor, at the same time the bitumen can be heated whenever by bitumen distributors heating system on site.In the joints between binder sprays, the armor plate (length: 1.5m) or building paper (length: 1.5m) will be used to cover the joints to prevent

13、additional binder application onto the previously treated section.3. AggregateAggregates are to be spread once the bitumen spreading is completed. According to the specification, sufficient quantity shall be spread homogeneously. The superposition or blank space of aggregates should be prevented. In

14、 the occasion of aggregate gap in certain part, timely manual filling is to be conducted. The aggregate shall comply with the requirements given in Section 4502(b) in the Standard Specification for Road Works 2000 TANZANIA.4. Rolling Initial rolling of aggregateImmediately after the aggregate has be

15、en applied, rolling shall be commenced. A self-propelled 16 tons pneumatic-tyred roller shall be used to the case. Rollers shall operate parallel to the center line of the road, from the shoulders inwards the crown of the road, until the entire surface has been covered at least three times with the

16、wheels of the roller. Broom drag and final rolling of aggregateAfter the bituminous binder has set-up sufficient to prevent any aggregate from being dislodged, the surface shall be slowly dragged with a broom drag to ensure even distribution of the aggregate. After completing the spreading of the ag

17、gregate, the surface shall be rolled with the same procedure of initial rolling. 5. The joint between adjacent sectiona) Longitudinal joint:Double surface dressing construction is half width construction. One edge of first half width is the edge of base. After the completion of first half width cons

18、truction, it is required to treat the other edge: l Align this edge to make it regularl Utilize instruments to clear the parts beyond the alignment, inclusive of aggregate and excessive bitumen, so as to dress and tidy the edge.b) Transverse joint: Prior to construction the following day, same treat

19、ment like method a) needs to be performed for ending part of double surface dressing which was done last day.Construction of next half width and next day could be followed as items no.1- no.4 mentioned above. Provided that the third half width construction is required on site, previous working proce

20、dures can be repeated.D. Measurement and PaymentThe work shall be measured and paid for under section 4500: Double Surface Dressings.E. Environmental protection1. This work will be executed in accordance with Section 1700: Environmental Protection and Waste Disposal.2. The construction will also be

21、executed in accordance with the approved ESMP.3.F. Health & Safety The construction will be executed in accordance with the approved HSMP.G. Traffic ControlThe traffic will be a single lane when double surface dressing, half width will be constructed and another half width will be as diversion, traffic will be transferred from one half to another half. Few occasions may occur that there will be a diversion outside of the road, in which situation traffic will be transferred from road to the diversion. The assigned persons will ca

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论