1、利雅得水泥厂石灰石预均化堆场施工方案Riyadh Cement Company Limestone Preblending Stockpile Construction Scheme说明:Instructions:该方案编制依据:This Scheme is compiled according to:1、 石灰石预均化堆场施工图纸 Drawings for limestone preblending stockpile2、 总承包合同要求 Requirements of General Contract3、 施工现场环境、机具,施工经验等 Site environment, equipmen

2、ts, and our construction experiences4、 建筑施工手册(第四版) Construction Manual (fourth edition)一、 工程概况 Brief Introduction of the Project1、 工程性质和作用该工程为利雅得水泥厂石灰石预均化堆场,其功能是储存和运输石灰石,建筑工期:土建部分计划92天。质量要求:土建工程范围是按照业主提供的文件所进行的交钥匙模式施工,在施工的每一步都要业主的质量认可,达到业主的满意。Nature of the Project and its functionThe Project is the

3、limestone preblending stockpile of Riyadh Cement Company whose function is to store and transport limestone, and the time limit for the foundation is 92 days. Quality requirements: The Civil Works Scope is a Turnkey pattern executed as per the documentations offered by the Owner with each step to be

4、 approved by and to the satisfaction of the Owner. 2、 建筑的结构特征该工程主要由网架基础、堆取料机轨道基础和石灰石运输廊道组成,网架基础由40个钢筋混凝土基础组成的半径为56m的环形基础,基础之间用基础梁连接,供上部施工金属网架。堆取料机轨道基础是半径为51m的环型钢筋混凝土基础,基础底宽1.2m,高1.3m,设置8道混凝土后浇带以降低混凝土收缩应力,基础上部设计有预埋螺栓,用于堆取料机轨道的安装。石灰石运输廊道为本工程施工的重点,其主要部位是位于场内的箱体结构进料仓,外部结构尺寸;高11m,宽8m,长40.5m,壁厚1m,底标高-11m,

5、局部-12m,因为是地下工程,施工时要考虑防水,防潮措施。Structure Characteristic of the ConstructionThe Project consists of net frame foundation, stocking and reclaiming track foundation and limestone belt conveyor. The net frame foundation is made up of 40 reinforced concrete foundations. The foundations will be connected wi

6、th beams. The foundation of stocking and reclaiming track is a round one of a semidiametre 51 m. The width of foundation is 1.2 m, length 1.3 m. 8 concrete rear casting belts are installed to reduce the contraction stress of the concrete. Pre-embedded anchor bolt is installed on the upper part of th

7、e foundation. The limestone conveyor is the highlight of the project, with the bin as its main part, the dimension of which is as follows: height 11m, width 8m length 40.5m, thickness 1m, bottom elevation 11m, part 12m . Water proofing and moisture proofing should be taken into consideration since i

8、t is an underground project. 二、 施工目标 Objective of the Construction1、 工期目标计划2005年8月25日开工,2005年11月25日结束,工期92天。Time limit of the Construction The Construction begins on Aug 25, 2005 and will finish on Nov 25,2005 with the period of 92 days.2、 质量目标确保优质工程,达到业主工程师满意。Goals of QualityQuality is to be of sup

9、erior and to the satisfaction of the Owners engineer.3、 安全生产目标坚持:“安全第一,预防为主”的方针,保证一般事故率小于0.15%,工亡率为0,在施工期间杜绝一切重大安全事故。Objective of SafetySafety and precaution from accidents will always be put in the first place. Common accident rate will be controlled within 0.15% and death rate 0%.Any major safety

10、accident will be shunned.4、 文明施工和环保目标强化施工现场科学管理,满足现场环保要求,达到业主工程师满意。 Pursuit of order and environmental protection It is our goal to reinforce the scientific management of the site construction, to meet with the environmental protection requirements and to make our Owner and Engineer satisfactory.5、

11、服务目标建造业主满意工程。Target of our serviceA project to the satisfaction of the Owner三、 管理组织机构本工程根据其特点,在现场成立项目经理部,实施总承包管理模式,由项目经理、项目总工程师、项目经济师组成,负责对工程的领导、决策、指挥、协调、控制等事宜,对工程的进度、成本、质量、安全和现场文明施工等负全部责任。Administration By virtue of the characteristic of this project, the business pattern of General Contracting is

12、brought into effect and the Project Management Department is to be established on the Site which is made up of Project Manager, Project Chief Engineer and Project Economist, who are responsible for the leading, decision-making, superintending, coordinating and controlling of the project, and who are

13、 also in full charge of the procedure, cost, quality, safety and orderly execution of the project. 四、施工方案1、 土方工程1-1、 室外自然地坪平整后-0.2m,网架基础土方挖深为1.1m,堆取料机轨道基础土方挖深0.6m,采用机械破碎挖土,如遇回填土石方,需继续挖至原土层,石灰石运输廊道基础挖深11m,土方开挖前,先爆破,后采用反铲分两层开挖,边坡坡度根据岩石性质,层理特性和挖方深度确定,一般为1:0.351:1.5,基底根据构筑物尺寸每边留置不少于1m的工作面,挖出的土方用自卸汽车运至场外

14、,并平整好场地。Outdoor natural leveling -0.2m, net frame foundation excavation depth 1.1m. stocking and reclaiming track foundation excavation depth 0.6m. adopt machinery crushing excavation. If meet refilling soil, should dig to the original layer. Limestone conveyor foundation depth 11m, blasting before

15、excavation, sloping is between 1:0.351:1.5. 1m of working place is reserved. The excavated soil and rocks are removed by dumper to the outside and leveling is done. 1-2、 土方回填采用铲运机运土分层回填,每层回填厚度不大于30cm,用蛙式打夯机夯实,并夯实后达到干燥时的密度的确90%,上表面用振动压实机压实地表。Refilling is done by carry scraper and the refilling is don

16、e by layers, each layer the thickness is less than 30cm. and the frog hammer is used for tamping. And the density when being dry is 90%, vibrating compactor is used to compact the soil surface. 2、 网架基础和堆取料机基础工程施工方法Net frame foundation and reclaimer foundation construction2-1、 基础摸板利用多层胶合板、木支撑,棱角用小木方制

17、成45度角,棱角直角边长20mm,支撑方式如下图: Foundation mould board will use ply-board, wood supporter, and angle will be filled with small wooden cube with 45, the length of angle is 20mm which is shown by the following diagram:2-2、 堆取料机基础螺栓可采用预留孔洞或沟槽,后栽螺栓的方式施工,保证螺栓的位置准确,后灌注的混凝土掺加膨胀剂,膨胀剂的使用参照使用说明书,并经业主工程师确认后施工。 The f

18、oundation bolts will be embedded in the concrete to guarantee that it is installed at the appropriate place. The concrete will be added sweller whose usage will follow instructions, and with the approval of engineer.3、石灰石运输廊道工程施工;Limestone conveyor corridor construction3-1、 施工步骤;从进料仓开始以设计的变形缝划分,分四个施

19、工段,进行流水施工。Process: four parts altogether from the entrance of the materials.3-2、 模板工程施工方法;模板采用18mm厚木质胶合板,50100(mm)松木方制作,木楞间距300mm,用483.5钢管做支架固定,参见“墙体模板施工图”施工,通廊内侧用483.5钢管架设满堂脚手架,外侧架设双排脚手架,脚手架同时当作钢支架支撑模板,脚手架横杆和立杆的间距均设为600mm,保证模板支撑强度和刚度,双排脚手架外侧与基坑壁靠紧,使其不会因混凝土侧压力产生横向变形,保证混凝土墙壁的截面尺寸,模板内可用木方支撑,待混凝土浇注到此位置

20、时将其取出。Mould board will be 18mm thick 50x100(mm) pine wook cubes, and the distance between wooden cubes will be 300mm, and fixed with frame of steel tubes of483.5, see the “Drawings of Wall Mould Board”. The inner place of corridor will be filled with scaffold, and the outer place will be installed w

21、ith two roll scaffold, and the scaffold will be used at the same time as supporter to support the board. The distance is 600mm to guarantee the strength and severity. The two roll scaffold will be close to the pit side to avoid deformation. 以上模板支撑方案适用于地下部分,有基坑壁支护的位置。地上部分廊道的墙体模板采用14对拉螺栓固定,间距600mm,每侧用

22、两根50100(mm)木方做横楞,横楞间距600mm。The above mould supporting plan is apt to underground part, with pit side supporter parts. The wall mould board above ground will be fixed with bolts of14, distance 600mm, two wooden cubes of 50x100(mm) will be used with the distance of 600mm3-3、 钢筋工程施工 Reinforced bars 1、

23、钢筋加工,现场设置一台钢筋切断机,一台钢筋弯曲机,二台电焊机,一台钢筋调直机,一处钢筋制作棚。钢筋质量需经业主工程师确认合格后加工制做。One set of bar cutter, one set of bar bender, two sets of welder and one set of bar straighter. And erect a shed for the work. The quality of the bars should require the Owners approval.2、 钢筋安装:水平设置纵向钢筋连接采用单面搭接焊,搭接长度10倍钢筋直径,竖向钢筋采用电渣

24、压力焊,接槎相互错开,距离为钢筋直径的35d以上,底板上排钢筋用铁马登架起,间距1.5m,侧壁双排钢筋间用10拉筋固定间距。侧壁竖向钢筋长度大于6m的采取在底板处设置插筋,后焊接上部钢筋的方式施工。插筋留设方式参见标准图集,并经业主工程师确认后施工。Reinforcing bar :The level establishes lengthways reinforcing bar conjunction adoption the one side takes to connect the welding, taking to connect the length 10 times reinfor

25、cing bar diameter, the upright faces reinforcing bar adoption electricity pressure , connect the to shunt mutually, distance of reinforcing bar the diametral 35 ds above, lining up the reinforcing bar to ascend with the iron on the scaleboard rises, is apart from 1.5 ms, side wall double row the rei

26、nforcing bar uses the 10 pull fix .The side wall upright faces the over and above a way for adopting in the scaleboard establishing bar , behind welding upper part reinforcing bar construction in reinforcing bar length.Putting the bar stays to establish the way pays to the standard diagram gathers,

27、combining after owner engineer confirm start construction.3-4、 混凝土工程 Concrete Project1、 混凝土等级B25,提供混凝土用的砂、石、水泥试验后经业主工程师认可,由试验确定混凝土配合比,该工程混凝土采用罐车运输,混凝土泵送浇筑,要求混凝土初凝时间不少于3小时,保证连续浇筑。Concrete grade B25, the sand, stones, cement should be tested and approved by Owners Engineer. Trial mix cube is to be tes

28、ted. The concrete is transported by transport mixer, and conveyed by pump. Initial setting time is not less than 3 hours, and continuous casting is required.混凝土浇筑施工缝的布置,该工程按设计变形缝分四个流水段施工,每一施工段底板与墙面之间设置一道施工缝,施工缝距底板上表面300mm高,施工缝制作成齿形防水带,如图所示,侧壁与顶梁板浇注时,在侧壁浇筑完毕后停歇1-1.5小时,使混凝土获得初步沉实后在继续浇筑,以防止接缝处出The conc

29、rete sprinkles to build the construction sews of arrange, that engineering transforms to sew to divide four flowing waters a construction according to the design, each a construction a scaleboard establishes with wall construction sews, starting construction to sew to be apart from scaleboard top th

30、e surface 300 mms high.The construction stitches to make the permanent teeth form watertightness,shown as diagram, the side wall sprinkles with crest beam plank to note, stop 1-1.5 hours after side wall sprinkle build to complete, make the concrete acquire the first step to sink solid the empress sp

31、rinkling to build continuously, in order to prevent joint.3、4、 混凝土浇筑顺序,底板混凝土浇筑应从一侧开始纵向连续浇筑,侧壁混凝土分层连续浇筑每层300-400高,并且在下层混凝土初凝之前浇筑上一层混凝土。Concrete casting order: it should be lengthwise and continuously, with 300-400 thickness, and the upper layer should be cast before solidification of the lower layer.

32、4-4、 混凝土养护 concrete curing混凝土用混凝土养护液养护和浇水湿润的方式进行养护。The concrete is cured with chemical liquid and water curing.五、 施工准备计划 Preparation of construction1、 供水和供电:现场施工用水主要考虑木模板湿润、混凝土养护、土方压实等工程施工使用,配备60立方米水箱满足施工用水。施工用电采用自备发电机组,供电量450KW,满足该工程的施工临时用电。Power supply and water supply60 cubic meter water tank sho

33、uld be prepared for the use of water on the site, mainly for moisture of wooden board, curing of concrete and compressing of soil.Power supply: generator, capacity 450KW, to meet with the requirement on the site.2、 场内道路 Road on the site现场临时道路,场地平整已施工完,符合施工要求。Leveling and profiling of road has been f

34、inished.3、 房屋设施 housing 现场利用一间原有的房屋修建后作为现场办公、休息、小型材料、机具储备等用房。To use the existing house for office, rest, and storeroom of materials, and small equipments.4、 现场劳动力组织 labour allocation 4-1、以工程处为主,组建一个综合性施工队伍,在结构施工阶段,组成木模、钢筋、混凝土三个专业班组,设木工工长两人,钢筋工长二人,混凝土工长两人。Three groups will be established: wood mouldi

35、ng, reinforced bar and concrete, with two chiefs for each group.4-2、现场劳动组织需求量:结构施工阶段,木工20人,钢筋工15人,混凝土工12人,其他工种5人。Labours needed: 20 carpenters, 15 bar labors, 12 concrete labors, and 5 of other labors.六、施工进度计划progress 在保证施工质量的前提下,实行快速流水作业,做好本工程施工进度计划。1、 廊道工程在平面上划分为四个施工流水段,施工网络计划如图:2、 网架基础和堆取料机轨道基础施工

36、计划安排:首先施工网架基础,后施工堆取料机轨道基础计划工期40天。施工进度计划见附表。Conveyor is divided into 4 parts.Net frame foundation and reclaimer track construction will be 40 days.七、施工质量保证措施 Measures of Quality Guarantee 1、加强技术管理,认真贯彻各项技术管理制度,开工前要落实各级人员岗位责任制,做好技术交底,施工中要认真检查执行情况,开展全面质量管理活动,根据工序报验程序,及时报请咨询工程师审核。 We are to enhance the

37、technical management, earnestly carry through each technical and management regulation. Expressly stipulate the responsibility of each posting and well manage the shift, examine thoroughly during the execution and report to the Consultants for their approval.2、认真进行原材料检验,钢材和水泥等材料,必须提供质量保证书,并按规定做好抽验,各

38、种强度等级的混凝土,要认真确定设计配合比,规定减水剂掺量,按规定制作试块。 Steels, cement and all other raw materials should be well tested before access into the site and their quality certificate and random test are required according to relevant stipulations. Trial mix cubes should be made for various grades of concrete.3、加强材料管理,建立工

39、料消耗台帐,实行“当日记载,月底结帐”制度,钢筋工程采用现场集中配料,冷拉和对焊措施,降低钢材损耗。 Establish account book for raw materials and claims for the same are to be journalized every day .4、严格控制标高和垂直度,用经纬仪把轴线、边线投到基础底面,并做好控制点,外模安装必须用线锤和经纬仪双重检查,模板安装完毕后,须经质量检验人员验收合格后,报业主工程师批准后进行下道工序施工。 Strictly control elevation and vertical.5、加强工序间配合,在结构施工

40、中,水、电等工种,应与其密切配合,设专人检查预留孔洞,埋件等的位置。 All the relevant sections should have good cooperation such as water supply and power supply. 八、施工安全保证措施 1、超过3m深的基坑,土石方开挖完成后,距基坑1.2m处和出入口设置一道高0.9m的护栏,施工用机具材料不准存放在护栏内,非本专业施工人员不准随便进入工作区。 A 0.9m railing is to be erected around pits which are more than 3m deep, and any

41、 tools or materials are forbidden within the railing, and only workers of the pit shall be permitted into the railing. 2、加强放火工作,现场设置灭火装置和灭火器具。 Fire hydrant and fire extinguisher are to be placed on the site.3、 做好安全生产教育和职工安全素质培养,做好分部分项作业时的安全交底工作,施工班组每天召开班前会,对工人进行针对性安全教育,新工人未经教育不得上岗。Do the safety trai

42、ning, hold a short meeting about safety every morning, discuss and solve existing safety problems. New workers must have a safety training before working on the site. 专业工长在分项工程施工前,以书面形式向班长交底,在涉及重大安全问题时,召集全体操作人员现场交底,并且全员签字。 Written delivery receipt is a must in shifting, and signatures of all are req

43、uired for safety cases.4、加强机械设备接地,建筑物及设备的避雷装置和其他安全限位的管理和整改。Earthing of equipment is strictly requested. And lightening conductor is also required. 5、机械操作人员,特殊工种必须经过培训,持证上岗上班,非操作人员不准动用机电设备。Machine operators must have a training before operating.九、文明施工管理措施 orderly execution of the construction 1、现场成立文

44、明施工领导小组,由项目经理负责现场文明施工,以创文明施工样板工程为奋斗目标。 Specific department is to be established for the orderly execution and it is our tenet to establish the system to keep a orderly and proper execution for the construction. 2、现场布置按计划安排,建筑材料堆放整齐,构件材料分门别类,道路通畅,临时设施整齐有序,垃圾及时清扫,做到随做随清,现场内无施工垃圾,文明整洁。 Keep the site cl

45、ean and tidy, categorize all the materials and spare parts. Make the roads always accessible, temporary buildings neat, construction waste cleared in time. 十、施工资源计划 construction plans 1、主要施工机具需用量计划表 Equipments and machines needed 序号机具名称型号及规格单位数量1钢筋切断机气短直径32mm台12钢筋弯曲机弯曲直径32mm台13钢筋调直机台14电焊机BX-300台25气割

46、工具套26木工圆盘锯台27平刨机台28自动压刨机台19混凝土运输车、输送泵台210搅拌机台111切割机台212电渣压力焊机具套413汽车吊20T辆114运输汽车辆115蛙式打夯机台216震动器台617震动棒条20ItemName of equipmentsSpecificationsunitQuantity1Bar cutterDia 32mmset12Bar benderBending dia 32mmSet 13Bar straightening machineSet 14 Welding machineBX-300set25Gas cutterset26Carpenters rotary

47、 sawSet 27Trying planeset28Automatic Thicknessing machineset19Concrete mixer and conveying pumpSet 210mixerSet 111Cutting machineset212Electroslag press welderSet 413Truck crane20tSet 114carrierset115Frog rammerSet 216jolterSet 617vibratorbar202、施工工具需用量计划表序号工具名称型号及规格单位数量1双轮推车台102打气筒个23修补工具、材料套14羊角锤把

48、205手锯把206斧子把107钉袋个208尖镐把59尖锹把2010平板锹把2011铁挫把1012综绳M10013手板葫芦套2014对拉螺丝个10015眼镜扳子个20Tools needed ItemName of toolsspecificationsunitquantity1Two wheel trolleyset102inflatorpiece23Tools and materials for repairSet 14Nailhammer piece205Hand sawpiece206axepiece107Nail bagpiece208Acute hammerPiece59Acute

49、shovelpiece2010Flat shovelpiece2011filePiece 1012cordM10013Handpulling blockset2014screwpiece10015spannerpiece20主要施工材料计划表序号材料名称型号及规格单位数量1钢筋T3052混凝土m343003模板木材50100木方m315018厚胶合板m31204脚手工具483.5管T70直角扣件T17对接扣件T7旋转扣件t2底座个1500Materials neededItemName of materialspecificationsunitquantity1Reinforced bart3

50、052concretem343003Mould board50x100cubicm315018 thickness plywoodm31204Scaffold facilities483.5tubet70Right angle fastenert17Abutting joint fastenert7Rotary bucklet2basepeice1500十一、施工平面布置图 Construction layout模板结构设计1) 混凝土侧压力值:concrete side pressure混凝土自重 concrete self weight 24 KN/m2 强度等级 strength gra

51、de B25F=0.22c to12v1/2 F=c.H其中: F - 新浇筑对模板最大侧压力 maximum pressure to the mould board (KN/m2) c-混凝土的重力密度 gravity of concrete(KN/m2) to -混凝土初凝时间表time of initial solidarity of concrete (h) 实测或to=200/(T+15) T为混凝土温度temperature of concrete:取20度. 20 V -混凝土浇筑速度 casting speed of concrete(m/h): 取1.2(m/h) H -混凝土侧压力位置处至混凝土顶面的

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论