DL5190.6-2012
TechnicalSpecificationforThermalPowerErectionandConstruction
Part6:WaterTreatmentandHydrogenGenerationEquipmentSystem
Contents
1Generalprovisions4
2Terms4
3Basicrequirement6
3.1Generalrequirement6
3.2Constructionengineering7
3.3Inspectionandstorageofequipmentandmaterials8
3.4Leaktestofequipmentandsystem9
3.5GreenConstruction10
4Waterpretreatmentequipment11
4.1Conventionalequipment11
4.2Ultrafiltrationandmicrofiltrationequipment15
4.3Wastewaterdisposalequipment16
5Waterpre-demineralizationequipment17
5.1Reverseosmosisunit17
5.2Seawaterdesalinationandevaporationequipmentand
thermalcompressionandjettingequipment20
5.3Stainlesssteelequipmentandpipelineprotection22
6Boilerfeedwatertreatmentequipment23
6.1Ionexchangeequipment23
6.2Carbondioxideremovaldevice25
6.3Electricdeionizationdevice25
7Condensatedwaterprocessingequipment26
7.1Generalrequirement26
7.2Filters27
7.3Ionexchangersandregenerationdevice27
8Coolingwatertreatmentequipment27
8.1Sterilizationdevice27
8.2Scaleandrustinhibitiondevice29
8.3Makeupwaterandby-passflowtreatmentequipment29
9Samplinganddosingsystem30
10Boxes,drumsandtanks33
11Rotatingmachineryandotherequipment34
11.1Hydratedlimemachinesandlimecrane34
11.2Watertreatmentpumps34
11.3Aircompressorsandaccessoried37
11.4Agitators39
12Specialpipingandvalves39
12.1Generalrequirement39
12.2Specialmediapipeline40
12.3Pipemadeofspecialmaterials41
12.4Specialvalves45
13Anticorrosiveconstruction45
13.1Generalrequirement45
13.2Anticorrosiveconstructionprocess46
13.3Constructionofplastics49
14Startupandadjustmentofwatertreatmentsystem51
14.1Generalrequirement51
14.2Waterpretreatmentandpre-demineralizationsystem51
14.3Desalinationsystem54
14.4Condensatetreatmentsystem54
15Hydrogenstation55
15.1Generalrequirement55
15.2Inspectionandinstallationofequipmentinhydrogen56
15.3Inspectionandinstallationofpipinginhydrogen57
15.4Startupandadjustmentofhydrogengenerationequipment..60
1Generalprovisions
1.0.1Thistechnicalspecificationiscompiledforconstructionofwatertreatmentandhydrogengenerationequipment.
1.0.2Thispartapplytonew-build,extensionandrebuildwatertreatmentandhydrogengenerationequipmentandsystemof1000MWandunder1000MW
thermal
power
plant
,cyclegas-steamturbineunits,conventionalislandofnuclearpowerstationandBOPsystem.
1.0.3Watertreatmentandhydrogengenerationequipmentandsystemconstructionmeetthepartandrelevantprovisionsofnationalstandardsandcurrentstandards.
2Terms
2.0.1Waterpretreatment
Processingwaterbyprecipitation,coagulationandclarification.
2.0.2Clarification
Producewaterwithlittleparticlesbyprecipitationofsuspendedparticlesinlargetank.
2.0.3Filtration
Removeparticlesbypassingfitterstrainer.
2.0.4Ultrafiltration
Ultrafiltrationisinbetweenmicrofiltrationand
nanofiltration
,filteringrecisionbetween0.01μmand0.10μm.Thetypesincludevacuumandpressure.
2.0.5Microfiltration
Microfiltrationisinbetweengeneralfilterandultrafiltration,filteringrecisionbetween0.1μmand1.0μm.
2.0.6Reverseosmosis
Wedoforciblyhigherthantheosmoticpressureofthesolutionatthesideofthemembrane,thatisthesideofrawwater,allowingwaterandsomecomponentsselectivetransmission,andothermaterialcan'tthroughthemembrane.
2.0.7Recycledwater
Wastewatercanbeusedafterpropertreatment,ofwhichqualityisinaccordancewithstandard.
2.0.8Wastewater
Thewaterdischargedwhichfrompowerplant,thewatercanbeusedaftertreatment.
2.0.9Tightnesstestwithvacuumbox
Themethodofcheckingleakfor
welding
ofwatertankbaseplatewithvacuumbox.
2.0.10Lowtemperaturemulti-effectdistillationunit(LT-MED)
UsethespraAniongtechnologyoflowtemperaturehorizontaltubefordistillation,ofwhichmaximumtemperatureofsaltwaterlessthan70℃.
2.0.11
Desalination
Theprocessofremovingthesaltinthewater,desaltedwatercanbeusedof
drinking
water
,productionwatersupplyand
cooling
water
.
2.0.12Electrodeionization
Inthefreshwatercompartmentofelectrodialyzerfillinganionandcationmixedionexchangeresin,combiningelectrodialysisandionexchange,removeioninwater,makeuseofpolarizationphenomenonintheprocessofelectrodialysis,doelectrochemicalregenerationforionexchangeresin.
2.0.13Ionexchange
Theprocessofsomeanionorcationinwaterthroughthefilterbed.
2.0.14Perforated-steelandplasticcompositepipe
Perforated-steelandplasticcompositepipeisreinforcementofporous
sheet
steel
pipe
throughhydrogenarcwelding.Anewcompositepipeof
two-sided
compositethermoplasticplastics.
2.0.15Electricalfusionbellandspigotconnection
A
connection
method
thatconnectedpipeinsertedintomuzzlebellandcontactareaofmuzzlebelltogetherbyfusionwelding,makeuseofGreatheatproducedby
electrical
heating
element
insertedintoinnerwallofmuzzlebellwithelectricity.
2.0.16Stainlesssteellinedcompositesteelpipe
Adopting
compound
technology
,steelpipeusedforfluidtransport,suchasweldedpipe,seamlesspipe,ect,theirinnerwallliningwith
stainless
steel
anticorrosivelayer,whichmakeupCompositestructurewallpipe.
2.0.17Electrolysisthesaltsolution
ElectrolysisIndustrial
sodium
chloride
solution
,ChemicalMethodsthatproduce
sodium
hypochlorite
and
chlorine
.
3Basicrequirement
3.1GeneralRequirement
3.1.1Thepartincludetherequirementsofwatertreatmentandhydrogengenerationequipmentandsystem,involvesmechanicalinstallation,pipeinstallation,weldingconstruction,monitoringinstrumentandprogrammedcontrolect,itshouldmeettherelevantprovisionsofnationalstandardsandcurrentstandards.
3.1.2Themainequipmentmanufacturersshouldhave
manufacturing
licence
issuedbystate,province(autonomousregion),Direct-controlledmunicipalityorthestateadministrative
supervision
and
administration
department.Qualityacceptanceof
equipment
manufacture
onthebasisofthecurrentrelevantstandardsofthestateorindustry,ifnorulers,inaccordancewiththecontract.
3.1.3Allkindsofequipmentconstructionaccordingtorequirementsofdesignandtechnicaldocumentationoftheproduct.Tomodifythedesignorusealternativeequipmentsorthematerials,itshouldbeapprovedbydesignedunits,supervisorandconstructionunits,andthanitcanbeimplemented.
3.1.4Non-standardequipmentconstructionwhichisnotincludedinthispartshallbeinaccordancewiththecontractagreementordesignrequirements.Forimportedequipment,weshouldformulatetechnicalmeasuresforconstructionaccordingtothecontractagreementorrelevanttechnicalrequirements.
3.1.5Orderingcompletesetofdevicesshouldsign
technical
agreement
andacceptanceasanattachmentofthecontractandthebasisofconstructionacceptance.
3.1.6ThereareSupervisionandinspectionreportsbeforeinstallingcompletesetofdevices.
3.1.7
Liquid
level
measurement
and
analysis
meter
installationafterrinsthesystemandcleanandqualified.
3.1.8
Drainage
pipeline
ofthecontainershouldbearrangedinthetrench,itsdirectionshouldbethesamewithdraindirections.
3.1.9Dosingroomshouldbeequippedwiththerinsewater.
3.1.10Storingor
conveAniong
equipment
foracid-basemediaaswellassystemsoperationmuststrictlyobservethesafetyrules.
3.1.11Storage,handlingandinstallationofstainlesssteelpipesandpipefittingsshouldnotbecontactwiththeferritematerials,betweenthestainlesssteelpipeandcarbonsteelhangershouldbeSeparatedwithStainlesssteelskinorlessthan50mg/kgofnon-metallicgaskets.
3.1.12Frameinstallationqualityofultrafiltration,reverseosmosis,electrodeionizationdevicesshouldcomplywith
relevant
regulation
ofGB50205CodeforAcceptanceofConstructionQualityofSteelStructures.
3.2Constructionengineering
3.2.1
Beforeequipment
installation
intoplace,theconstructionunitorsupervisionunitshouldorganizeinstallationwork,thecontractorscheckconstructionprojectwiththem,meetthefollowingrequirements:
1Geometricdimensioning,locationandelevationofequipmentfoundationsshouldmeetthedesignrequirements.
2Geometricdimensioning,locationandelevationofembeddedinsertandreserveholesshouldmeetthedesignrequirements.
3Asphaltsandcushionshouldbepavedonthefoundationoftheflatbottomtank,thedirectionandgradientofslopeshouldmeetthedesignrequirementsorrelevantprovisionsofGB50128Codeforconstructionandacceptanceofverticalcylindricalsteelweldedstoragetanks.
3.2.2Acceptanceofconcretestructuresinaccordancewithdesigndrawings.Acceptanceofanti-corrosionrequirementsofreinforcedconcretestructuresandbuildingsshouldbeinaccordancewithDL5190.1Technicalspecificationforthermalpowererectionandconstruction-Part1:CivilEngineering,GB50212Specificationforconstructionandacceptanceofanticorrosiveengineeringofbuildings,GB50224Codeforacceptanceofconstructionqualityofanticorrosiveengineeringofbuildings.
3.2.3WeshoulddowaterfillingtestforreinforcedconcreteContainers.Beforethetest,theinstallationofpipejointsshallmeetthedesignrequirements,thetimeofwaterfillingtestisnotlessthan24h,thereshouldbenoleakage.Installationofequipmentandpipingcanbecarriedoutafterpassingthewaterfillingtest.
3.2.4Beforewatertreatmentequipmentoperation,buildingconstructionshouldbecompletedthefollowingtasks:
1Ananti-corrosiongroundofindoorandoutdoorofwatertreatmentroom,anti-corrosionditchandneutralizationtank,wastepondconstructionaccordingtodesignrequirementsandpassacceptanceinspection:drainagetrench,slagdraintrenchtotallyunimpeded:Acompleterangeoftrenchcover,trenchcoverandgroundareinaplane
2Whitewash,paint,floors,platforms,stairs,doors,windowsandlightingofindoorandoutdoorofwatertreatmentroom,theconstructionofthemaccordingtodesignrequirement.
3Thewater,heating,ventilation,lighting,aircondition,powersupplyandexperimenttableoftestroomconstructioninaccordancewithdesignrequirements.
4Structure,corrosionprotection,ventilationandsafetyfacilitiesofacid-basereservoirpoolconstructionworkiscompletedandthenpassacceptanceinspection.
3.2.5Beforeadjustingcommissioningofhydrogenstationequipmentandsystems,buildingandelectricalconstructionshallcomplywiththefollowingProvisions:
1Lightningrod,groundinggridofhydrogenstationconstructionworkiscompletedaccordingtodesignrequirementsandthenpassacceptanceinspection.
2Roads,fencesandgates,doorsandwindowsofHydrogenStationconstructionworkiscompletedaccordingtodesignrequirementsandthenpassacceptanceinspection.
3Thewater,heating,ventilation,lighting,aircondition,powersupplyofhydrogenstationconstructionworkiscompletedaccordingtodesignrequirementsandthenpassacceptanceinspection.
4Safety,firefightingfacilitiespassacceptanceinspection,meetoperatingcondition,acompleterangeofSafetywarningmark.
3.3Inspectionandstorageofequipmentandmaterials
3.3.1
Open-box
inspection
ofequipmentincludesthefollowingcontents:
1Packinglist,certificateofproductquality,CertificateofApproval,generaldrawingofproduct,theproductinstructionsandotherrandomfileshouldbecomplete.
2Productqualitycertificateincludesthemainpressurepartsmaterialwarrantybook,hydrostatictestreports,forequipmentofNDTrequirements,thereshouldhaveweldjointNDTreports.
3Accordingtolists,checkquantity,specifications,packagingandappearanceofthematerialsandequipments,andmake
open-box
inspection
records.Ifthereiscorrosion,cracking,deterioration,damageandotherdefectsequipmentormaterials,itshouldbeanalyzethecauseswithrelevantunits,findouttheresponsibilityanddealwiththeseissuestimely.
3.3.2StorageofmaterialsandequipmentsinaccordancewiththeregulationsofDL/T855-Thecodeformaintenanceandsafekeepingofthermalpowerequipmentinelectricpowerconstructionandrequirementsofthetechnicaldocumentationofproducts.
3.3.3Anticorrosiveequipmentandmaterialstransporttotheconstructionsite,do
appearance
inspection
andleakagetestinspection,anditshallmeetthefollowingrequirements:
1Aliningmaterialsanditsthicknessshallmeetthedesignrequirements.
2Therearenofloatingandhollowingforanticorrosivecoating.
3Dotheleakagetestforallanticorrosivecoatingwithhigh-frequencysparkdetector,itshouldnotproducespark.Detectionprobestayatanyonelocationarenottoolongtime,thespeedofdetectionprobeis3m/min~6m/min.thevoltageseeTable3.3.3.
Table3.3.3Theleakagetestforvoltagecheckofanticorrosivecoating
Anticorrosivecoatingmaterials
Theleakagetestforvoltagecheck
Rubberlining
Slab
rubber
3KV/mm
Liningplastic
Steelpipeconnectedcathode,
positive
pole
connectedliningplasticlayer,Lowestleakdetection
voltage
U=7843,
U-minimumvoltagefordetection,V
T-Thicknessofliningplasticlayer
Glass
fiber
reinforced
plastics
Checkingvoltage3KV--3.5KV
Others
Checkingvoltageshouldbemeetdesignrequirement:therearenorequirements,thethicknessofcoatingmultiplyby5V/um
4Qualitydefectsarefound,dealwithitaccordingtothecontract,aftertreatmentshouldbetestedagain,afterqualifiedforinstallation.
3.3.4Specialmaterialsforwatertreatmentandpotionwhichtransporttosite,andthendosamplinginspection,thequalityshouldmeetthetechnicalrequirementsandtherelevantprovisions,Storethembycategory,safekeeping.
3.4Leaktestsofequipmentandsystem
3.4.1Afterinstallationofvarioustypesofpipesandequipmentiscomplete,Testpressureofsteelpipes,testmethodsand
announcements
shouldbeinaccordancewithrelevantregulationsofDL5190.5-ThespecificationoferectionofelectricpowerconstructionPart5:Pipingandsystem.
3.4.2Rubberlining,liningplastic,
glass
fiber
reinforced
plastics
,plasticsandothernon-metallicmaterialsteelpipe,thepressureofleaktestisratedworkingpressure.Differentratedworkingpressureequipment,pipinginstalledinthesamesystem,doleaktesaccordingtoratedworkingpressureofthelowestratedworkingpressureofequipmentorpipesinthesystem.Whentheworkingpressureisambiguous,powerequipmentheadcanberegardedastheworkingpressure.
3.4.3Leaktestofstainlesssteelpipingwithcleanwater,itschlorideioncontentbelessthan25mg/L.
3.4.4Ionexchange,regenerationdevicesofwatertreatment,afterinstallation,itshoulddo
hydrostatic
test
ofsingleworkingpressure.
Singleworkingpressureshouldbecompletedafterthehydrostatictest.
3.4.5Pressure-bearingequipmentaccordingtorelevantprovisionsofTSGR0004-SupervisionRegulationonSafetyTechnologyforStationaryPressureVesselpressurevesselpressuretest.Ifthereiscertificateofhydrostatictestqualified,thistestcannotbedo,butweshoulddoleaktestofpipewhichconnectedwithpressure-bearingequipment
3.4.6Dowaterfillingtestfor
normal
pressure
vessel
,itshouldbeensurethatitdoesnotleak.
normal
pressure
vessel
smadeon-site,allweldingseamof
normal
pressure
vessel
bottomshoulddoleaktestofvacuumboxmethod,negativepressureisnotlessthan53kPa.
3.4.7
Float
bowl
inequipmentandcontainershoulddowaterfillingtesttomakesurethatthefloatbowldoesnotleak.
3.4.8CheckingvesselsandequipmentofconcretestructureshouldbeinaccordancewiththerelevantprovisionsofGB50300-Unifiedstandardforconstructionqualityacceptanceofbuildingengineering
3.4.9Allequipmentsandsystemsshoulddowaterfillingtest,oil-leakagetestorleaktest,afterqualified,wecandoanti-corrosionandinsulationwork.
3.5GreenConstruction
3.5.1Theconsructionshouldbeinaccordancewiththefollowingregulations:
1Optimaltheconstructionprocess,andpromoteenergyconservationandemissionreduction.
2Adoptingnewtechnology,newprocess,newequipments,newmaterials,high-pollutiontechnologyshouldnotbeused.
3Environmentalprotectionandenergysaving,thedevicesandmachineries,andincreasingutilization.
4Recyclingexperimentalwater.
5Wastegeneratedbytheconstructionshouldbeclassifiedanddisposed.
6Prohibittheuseofmaterialsandtechnologiesprohibitedbythestateregulations.
3.5.2WastewaterdischargeofWatertreatment,wastewatertreatmentshallcomplywithIntegratedwastewaterdischargestandardGB8978andlocalpollutantdischargestandard.
3.5.3Prohibittheuseofoverflow,seepagewells,leachingcesspool,wastemine
attenuation
orothermeanstodilutethedischarge
poisonous
andhazardouswastewater.
3.5.4Wasteorsludgefromwaterandwastewaterdisposalshouldbestoredin
specialized
stackingarea
,theyshouldbecomprehensiveutilized.
specialized
stackingareaadoptmeasurestopreventdustandlixivatedwater.
3.5.5Constructionprojectsputintoproductionoruse,atthesametime,environmentalcontrolfacilitiesbeingputintouse.
4Waterpretreatmentequipment
4.1Conventionalequipment
4.1.1Theinstallationofdefecatormeetthefollowingregulations:
1
Steel
catchwaterchannel,afterwaterfillingwatertest,assemblingthosedevices
.Theholeofcatchwaterchannelcenterlineshouldbeatthesamelevel,
allowable
deviation
is2mm.
2catchwaterchanneland
clapboard
shouldbeweldedtight.
3Theinstallationofsamplingtube,valveshallcomplywiththefollowingrequirements:
1)samplingtubeendinsertedintotheinsideofthevesselshouldbedownwarping,verticalinsertiondepthis50mm~100mm.
2)Thetextureofsamplingtubeshallmeetthedesignrequirements.
3)Theelevationofsamplingtubeshouldmeetthedesignrequirements,allowabledeviationis:±10mm
4)Samplingvalvesshouldbearrangedinpositionforeasyoperationandsolidinstallation.
4Installationofcellularinclinedtubeorinclinedboardshallmeetthedesignrequirementsandinagoodorder,clingcloseeachother,notbeloose.Theintervalbetweenthecomponentsshouldnotbelagerthantheporesize.
5Elevationofoverflowpipeandoutletpipeshouldmeetthedesignrequirements,andits
allowable
deviation
is±5mm.
4.1.2ladderofclarifiershouldbefullweldedandittreatedwithpreservatives.
4.1.3Inflowdistributionboxofclarifier,its
allowable
height
deviation
ofneighbouring
crest
of
weir
is5mm.
4.1.4Filterwithwatervalvebonnet,checkingitsgapsandcompletenessbeforeyoucaninstallit,watervalvebonnetshouldbetightenedwhenitisinstalled,Wheninstalled,waterspraytestshouldbedone,thewatervalvebonnetwon'tcomeoffordamaged.
4.1.5Physicalandchemicalproperties,gradation,particlesize,uniformitycoefficientoffiltermaterialsandthegradedgravellayertextureshouldmeetthedesignrequirements.Nodesignrequirements,itshallmeettheprovisionsofAppendixofthispart.
4.1.6Whenthefilterisinstalled,Measuringequipmentcenterisbasedontheoutletflangecenter,
allowable
deviation
is10mm;theelevationoffilterisbasedoninflowflangecenter,its
allowable
deviation
is10mm,itsverticaldeviationisnotmorethan0.25%ofdeviceheight.
4.1.7Airseparatorinstallationshallmeetthefollowingregulations:
1Thecenterandelevationofairseparatorshouldmeetthedesignrequirements,allowabledeviationofverticaldegreeforshellisitsheightof0.4%,andthemaximumdeviationis20mm.
2allowabledeviationbetweenseparatorcenterlineoftheoriginalpipecenterextendedintotheairandcenterlineofairseparatoris5mm,
horizontal
andallowabledeviationupperedgeofthe
water
pond
is2mm.
4.1.8Suspendingclarifierinstallationshallmeetthefollowingrequirements:
1Thegapbetweensupportringand
foundation
shouldbe30mm~40mm.Thesupportringshouldbehorizontal,allowabledeviationis0.1%ofitsdiameter,andthemaximumdeviationis5mm.
2verticalandallowabledeviationofitsshellis0.25%ofthedevice,andthemaximumdeviationis5mm.
3Thecenterlineoftheuppercatchwaterchannel,theinnercylinderandtheinnercylindertubethatcollectedslagshouldbeonthesameaxis,theallowabledeviationis0.5%ofitsshelldiameter,andthemaximumdeviationis20mm.
4Internalhorizontalandverticalsteadyflowplateweldingshouldbefirm,aperturepitch-rowshouldmeettheprovisionsofthedesigndrawings,edgeoftheholeshouldbesmooth.
5Machiningdimensionsoftaperedpartforinletnozzleshouldmeetthedesignrequirements,theinternalsurfaceshouldbesmoothandclean.Whenitisinstalled,thenozzleandthecasingshouldbelevel.Twonozzlesareparalleltoeachother
andbeperpendiculartothetaperedpartoftheclarifier.
6Attachmentbracketofinnerandoutertubeshouldbeweldedsecurely.Theholeof
internal
cylinder
andtaperedpartshouldnotleak.
7Theupperorloweredgesoftheinnercylinderareparalleltoeachother,theedgeoftheholeshouldbesmooth.
8Experimentalwaterofclarifier
water
filling
test
shouldbeflowinto
internal
cylinder
andthen
outer
cylinder
4.1.9Installationofclarifiershallmeetthefollowingregulations:
1Circulatorclarifier
1)verticalcenterlineallowabledeviationofReactionchamberis0.25%ofthediameterofclarificationtank,Centerlineallowabledeviationof
hollow
throat
,nozzlesis0.5%ofthereactionchamber
inner
diameter
,flaredpipeovalityofthereactionchambershouldbenomorethan1%,perpendicularityofreactionchamber,levelnessshouldmeetthedesignrequirements.
2)Thenozzlesizeshouldmeetthedesignrequirements,theinnersurfaceshouldbesmooth.
Allowable
deviation
ofnozzleand
hollow
throat
centerlineis3mm.
3)Verticalslidebaofhollowthroatisinstalledaftertakingnozzle,hollowthroatandriserinplace,hollowthroatslidesupanddowneasily.
2Mechanicalstirringclarifier:
1)Thefirstreactionchamber,asecondchamberandthecenterlineoftheclarifieris0.25%oftheclarificationtankdiameter.
2)Theinstallationforbearingofmechanicalstirringdevicesandtransmissionpartsis
on
the
basis
of
therelevantregulationofDL5190.2-Technicalspecificationforthermalpowererectionandconstruction-Part2:boilerunit.
3)Forspindlecenterlineofstirringdeviceandthecenterlineofsecondreactionchamber,theirallowabledeviationis0.5%ofthesecondreactionchamberdiameter.
4)Processingsizeofpulpboardandconnectingangleshallmeetthedesignrequirements.
5)Setting
slushing
equipment
placeandhollowthroatangleofimpellerregulatorbottom
6)Insertedheightatthebottomofchemicalfeedpipe,sludgethickeningcone,blowdownpipeand
clarification
tank
shouldmeetthedesignrequirements.
7)Thedistancebetweenthe
scraping
fender
andthe
bottom
of
the
pool
shouldmeetthedesignrequirements,ifnorequirement,itshouldnotbelessthan5mm,allowabledeviationis+4mm.
8)Thelevelnessoftheumbrellaboardshouldmeetthedesignrequirements.
4.1.10Filterinstallationshouldmeetthefollowingrequirements:
1Theelevationofauxiliary
pipe
orifice
,filteroutlet,
crest
of
weir
ofinlet,thebottomofinletpipedistributionbox,thebottomoftheu-shapedpipeaccordingtothedesigndrawingsor
standard
drawing
forconstruction,itsallowabledeviationis±10mm.
2Waterfenderthatunderthefiltercovershouldremainlevel,itsallowabledeviationis±2mm.
3Wheninstallingsiphonauxiliarypipe,itshouldnotbeusesquareelbow,
pipe
orifice
shouldbeinsertedintothesiphonelbow.bleedingpipeorificethatonthetopofsiphonbendshouldbeinsertedintosiphonpipeabout10--20mm.
415°inclinedtubeusedforflushingconstructionshouldbefollowdesigndrawingsor
standard
schematic
handbook
,allowabledeviationof
inclind
tube
is2degrees.Inclinedpipeorificeshouldclosetotheexhaustpipe,theinstallationofthemshouldbeonthesamesideofthesiphontube.
5siphonpipe,LiquidIndicator,siphonauxiliarypipe,exhaustpipe,siphontubeshouldnotleak.
6Thebackwashingintensityadjustmentboardshouldbeeasytoadjustandflexible.
4.1.11filterinstallationshouldmeetthefollowingrequirements:
1Mechanicalfilter:
1)Thefiltershouldbeinstalledvertically,verticalallowabledeviationofshellis0.25%ofitsheight,andthemaximumdeviationis5rnm,shellupright,thenweldingsupportingfoot,padironwithPre-buried
pipe
fitting
firmlyandgoingonsecondarygrouting.
2)ThecenterlinebetweenmainandbranchpipeofFilterthewaterdistributionsystem,drainagesystemandairdistributionsystemsshouldbeperpendiculartoeachother,thelevelallowabledeviationofthebranchpipeis±2rnm.
3)Thecenterlineofdraincapseatperpendiculartothe
horizontal
plane
ofbranchpipe,alldraincapshavethesameheight,allowabledeviationis±3mm,thespacebetweendraincapsaswellasthespacebetweendraincapandbottomplateofcontainershouldmeetthedesignrequirements,andsolidinstallation.
4)Filterusesmainpipeandbranchpipetypeof
water
distribution
system
,pipeholeshouldbesmooth.Meshofbranchpipeshouldmeetthedesignrequirementsandsolidlashing.
5)Thereisairswagingdeviceinfiltermechanicalfilter,theupperplanofcushionatthebottomofitandeyeletorstrainerareonthesameplan
6)Whenthereis
anticorrosive
coating
insideoffiltershell,beforefillingmaterials,weshouldcheckthequalityof
anticorrosive
coating
accordingtotheprovisionsofarticle3.3.3.
7)Filledwithactivatedcarbonorfiltersofother
fragile
filter
material
sforreverseosmosissystem,thecushionatthebottomofitshallcomplywithAppendixAofthispart.
2Fabricfilter
1)Installingfabricfiltershallconformtoprovisions
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 五年级数学上《小数除法竖式计算题》练习
- 昆明医科大学《民族器乐欣赏》2023-2024学年第一学期期末试卷
- 江苏医药职业学院《乒乓球教学与实践》2023-2024学年第一学期期末试卷
- 湖南三一工业职业技术学院《宠物医学》2023-2024学年第一学期期末试卷
- 湖北中医药大学《营养护理学》2023-2024学年第一学期期末试卷
- 【物理】《力》(教学设计)-2024-2025学年人教版(2024)初中物理八年级下册
- 重庆工商职业学院《市场营销模拟实验》2023-2024学年第一学期期末试卷
- 郑州电力高等专科学校《项目管理设计与创业精神》2023-2024学年第一学期期末试卷
- 浙江警官职业学院《化工热力学实验》2023-2024学年第一学期期末试卷
- 中国民用航空飞行学院《舞台实践》2023-2024学年第一学期期末试卷
- 牧场物语-矿石镇的伙伴们-完全攻略
- 2024-2030年中国汤圆行业销售动态及竞争策略分析报告
- 2024年中国智能客服市场研究报告-第一新声
- 人教版六年级上册解方程练习300道及答案
- 《健全全过程人民民主制度体系》课件
- 住院证明模板
- 园区物业管理合同协议书
- 《人体损伤致残程度分级》
- 港口流体装卸工职业技能竞赛理论考试题库500题(含答案)
- QCT1067.5-2023汽车电线束和电器设备用连接器第5部分:设备连接器(插座)的型式和尺寸
- 轮式智能移动操作机器人技术与应用-基于ROS的Python编程 课件 第4章 机器人运动应用实例
评论
0/150
提交评论