Thestudyonthestageoftheprojectcostmanagement
(Jack(YanGenfeng);StudentID:11B310043;Administrationspecialty)
Abstract:Projectcostmanagementisthebasiccontentstodeterminereasonableandeffectivecontroloftheprojectcost.Describedthecurrentstageoftheprojectcostmanagementsituationonthestrengtheningofthevariousstagesofconstructioncostmanagementoftheimportanceofandraisedanumberofkeyinitiatives.
Keywords:costoftheconstructionproject;thestatusofconstructioncostmanagement;managementofinvestmentunderthemarketeconomyofdecision-makingstage;thedesignphase;theimplementationphase
Introduction
EvenundertheWTOandChina'saccessiontotheworldcommunity,China'sconstructionindustryhowtoeffectivelycontrolconstructioncostoftheconstructionandmanagementofanimportantcomponentpart.However,thecurrentbudgetfortheconstructionprojects-estimate,budget,Superbudgetaccountsforthe"superthree"isstillwidespreadandthateventuallyledtoaseriouslossofcontrolofprojectinvestment.Projectcostmanagementisthebasiccontentstodeterminereasonableandeffectivecontroloftheprojectcost.
Astheprojectcosttotheprojectrunsthroughtheentireprocess,stagebystagecanbedividedintoInvestmentDecisionstage,thedesignandimplementationphases.Theso-calledProjectCosteffectivecontrolistheoptimizationoftheconstructionplansanddesignprogramsonthebasisofinthebuildingprocessatallstages,useofcertainmethodsandmeasurestoreducethecostoftheprojectshaveareasonablecontrolonthescopeandcostoftheapprovedlimits.
Engineeringandcostmanagementworkofthecurrentstatusofprojectcost
Managementsystemwasformedinthe1950s,andperfecttogetherinthe1980s.
Itistheactivitiesthatthecountrydirectlyinvolvedinthemanagementofeconomic.Provisionsinthedesignstagetodifferentestimatesorbudgetpreparationaswellasgovernment;Nothingrelevantdepartmentstoformulateabudget,content,methodsandapproval,thebudgetwillprovidethefixedcostofequipmentandmaterialsandfixedpriceofthebudgetpreparation,approval,managementauthority,andsoon.
Withthehistoricalprocessofthereformanddevelopment,Itisformedarelativelycompletebudgetestimateofquotamanagementsystem.However,asthesocialistmarketeconomicdevelopment,thesystem'smanyproblemshavealsoexposed.Generallyspeaking,thebudgetestimateisbasedondirectparticipationinthemanagementofnationaleconomicactivityasaprecondition.Enterpriseisnottheactualeconomicentities.Duetothecharacteristicsoftheplannedeconomy,and,atthetimeundertheconditionsofproductivity,willinevitablybecomeashortageintheeconomy.
Insevereshortageofcommoditiesundertheconditions,aslongasacertainlevelofinvestment,willbecertainoutputs.Inthisenvironment,theprojectplanningandtechnicalargumentationtherecanbenoeconomicanalysis.Statecontroloftheprojectcost,thatconstituteskeyfactorsequipmentandmaterialsprices,wagesandtaxesofartificialdistribution.Inthisrelativelystableeconomicenvironment,thebudgetestimateforthesystemapprovedprojectcost,helpthegovernmenttocarryoutinvestmentplanstoplayamajorrole.
Asthesocialistmarketeconomicsystemestablished,requiresustopredictprojectinvestmentandcontrol.Inrecentyears,internationalinvestmentprojectdevelopedtotherequirementsofpriorpre-controlandinthemiddleofcontrol.China,thetraditionalpracticeinanobjectivelightonthecausedecision-making,implementationheavy,lighttheeconomyandtechnology,
First,theconsequencesofvictimization,Duetothetechnicalpersonneloftheprojecttechnicalandeconomicconceptsandaweakawarenessofcostcontrol,costmanagementmakesthequalitydifficulttoraise.ProjectCostcontrolisdifficulttoachievelong-termgoals.
Second,thevariousstagesoftheprojectmanagementviewoftheabovecircumstances,Myfirstacademiainthe1980smadethewholeprocessofcostmanagementandcontrolconcept,buildingdepartmentswillstudythefeasibilityofprojectsandthebudgetsandfinalaccountstotwoextendedattherequestofthecorrespondingregulationsputourcostmanagementconceptsandmethodsreferredtoanewheight.
OurtasknowistobemodernandcostmanagementinlinewithChina'snationalconditionsofthemarketeconomysystemgoal,learnfromtheadvancedexperienceofthedevelopedcountries,andestablishsoundmarketeconomiclawsofprojectcostmanagementsystem,effortstoincreasetheprojectcostlevels.Aninvestmentdecision-makingphaseoftheprojectcostmanagementconstructionprojectinvestmentdecision-makingstageisproposedprojectproposals;conductafeasibilitystudytodetermineinvestmentestimationandthefinalpreparationofdesigntask.Atthisstage,theproject'stechnicalandeconomicdecision-making,oftheconstructionprojectcostoftheprojectafterthecompletionoftheeconomicbenefitshaveadecisiveinfluence,Theconstructioncostisanimportantstagecontrol.
China'scurrentstageoftheprojectcostfortheprojectmanagementforthepurposeofclearingprice,andfocusingonlyontheconstructionprocessofcostcontrol,neglectedbeforethestartoftheprojectinvestmentdecision-makingstageofcostcontrol.Investmentdecision-makingphaseofinvestmentprojectsisestimatedanimportantbasisfordecision-making.Ithasadirectimpactonnationaleconomicandfinancialanalysisoftheresultsofthereliabilityandaccuracy.Becauseofthisphaseisthepreliminaryworkofprojects,theinformationcannotbefully,comparableworksmoreorlessthatinformationaccumulatedrelativelysmall,estimatedinadequateandunscientific.Makesprojectcostmanagementandcostworkersisdifficultatthisstagedosomething.
Thevariousstagesoftheprojectcostcontrolinthedecision-makingphaseprojectcostcontrol.Rightprojectplanningphaseofthecost,manyownershavethewrongunderstandingthatthelowerthecostthebetter.Costcontrolisnotaunilateralissue,andshouldbeanumberoffactors,acombinationofpractical,comprehensiveconsideration.Theconstructionprojectinvestmentdecision-makingstage,theproject'stechnicalandeconomicdecision-making,Costoftheprojectafterthecompletionoftheprojectandtheeconomicbenefits,withadecisiveroleinprojectcostcontrolisanimportantstage,rationallydefineandcontrolthedirectionoftheprojectcostofaccuratepositioningandbuildingOptimizationguidingrole.
Inthedecision-makingphaseofthemostimportantistodoagoodjobfeasibilitystudy,theworkisdonewell,returnsoninvestmentandcanformagoodproportion.Otherwise,investmore,lesseffective,resultinginlossofcontrolandwasteofinvestment.
Atpresent,someoftheprojectsplannedtheownersofdeparturefromthesubjectivedesiresofafeasibilitystudyonthelackofscientificproof.FeasibilityStudyuntrue,falseorengineeringfunctionsobtainingtheapprovaloftheirsuperiors,actuallyputintothefeasibilitystudywillbeawardedinthestudyfortheprojectafterthesmoothfunctioningburiedalotofhiddenproblems,leadtoinsufficientfollow-upfundsfortheprojectandhadtoextendthetimelimitsothattheprojectcouldnothaveplannedtheuseofcost-effective,evenbecomehopelesscompletionofthebeardworks.
Therefore,inordertophaseintheinvestmentdecision-makingeffectivelycontrolconstructioncosts,wemustdothefollowingaspects:
Implementationoftheconstructionprojectandcorporateaccountability,Constructionoftheprojectfromplanningtoimplementationoftheentireprocessandtheuseofthefundstorepayresponsibilitiestothepeople.inadditiontoestablishingalegalsystemandtheprojectsupervisionmatchingmechanismbythedepartmentsinchargeoftheindustryandsupervisiondepartmentsforsettingupamonitoringgrouptooverseetheuseoffunds.
Arealisticapproachtomarketanalysis,toavoidtheblindnessoftheprojectdecision-making,reducesandreducesinvestmentrisk.Fullyconsiderbuildingprojectsinthefuturemarketcompetitiveness,designtaskmorescientificandreliability.
Capitalfinancingmusthaveaformalcommitmentdocument,thepartiesmustdoinvestmentfundsinplace,andfundsmusthavedocumentstoensurethattheprojectcanbeapprovedafterthescheduledimplementation.Tothevariousloanconditionsshouldbecarefullyanalyzedtominimizetheburdenofinterestandrepaymentpressure.
Tostrengthentheengineeringgeology,hydrology,geologyandland,water,electricity,transport,environmentalprojectssuchasexternalconditionsfortheworkofdepthtomaketheinvestmentestimatetherearesufficientgrounds.
Afterfulltechnicalappraisalandeconomicevaluation,andthefinaltechnologicallyadvanced,functionalandreliable,reasonableeconomicprojects,thuscalculateamoreaccurateandrealisticestimationoftheamountofinvestment,sothattheprojectcostfromthestartpositioninginamorereasonablelevel.
Designphaseoftheprojectcostcontrol
Thedesignphaseoftheprojectcostcontrolforalongtime,China'sbuildingcontrolveryeffective,-investmentprojectsisnotuncommon,thiswillaffectownersof
investmentreturns,itaddstotheownersandwithinbudget,aswellasdifficultiesinfundowners,theimpactonthefuturemanagementortheownersmakepaymentsinarrears,andsoon.Hence,thecontroloftheprojectcostisofgreatsignificance,howevertheprojectcostistheprimarymeansofcontroldesign,
Currentlymostofthepropertyownersinthedesignstageseldomworksoncostcontrol,andtheyfoundthatthecostofthedesignwillnothaveagreatimpact,itiswrong,onthecontrary,Designphaseoftheprojectcostcontrolisthemostimportantstep.Becauseitdeterminesengineeringdesign,constructionmethods,materialsandequipmenttypes,modelsoftheprojectcostisofcriticalsignificance,designoptimizationphaseoftheprogramorminorchanges,projectcostwillhaveasignificantimpact,Designphaseoftheprojectcostcontrolofthetotalprojectcostof70%.FollowingishowtocontroltheprojectfromdesigntocreatetheLaw:
3.1Astheownersmustdesign
Thedesignselectedonthequalitylevelisadirectimpactonthequalityofproductdesignlevel,andthedesignqualityproductsinthelevelofdirectinfluenceonthepricingoftheworks.Differentdesignunitsonthesameprojectdesignaredifferent.thesameitemofdifferentdesigninstituteworksbetweencertainaspectsoftheprojectcostontheexistenceofdifferencesbetween,Weassumethatwithadesignfromtwodifferentdesigninstitutetodesign,Constructionplansafterthecompletionofarequestedadvisoryunitcosttodothebudget,certainlydifferentdesigninstitutethetotalcostoftheprojectisabsolutelynotthesame,andmostofthedifferencebetweenthetwoover10%evenmorethan30%,andnotnecessarilyhighcostthanthedesignoflowcost,andgooddesignisoftenlowcost,Weallknowthatdifferentpeoplehavedifferentdesignstylesanddifferentlevels,thedesignworksnaturally,thereforechosentodesignunitsisthecontrolonthefirststep.Throughtendertoselectthedesignoftheunitsisagoodmethod,thetenderdocumentstoelaborateonthisparticularaspectoftherequirements,costcontroltargets,andsoon.
Otherwise,inthesubsequentdesignprocessdesignunitswillputanincreaseinthecostofthedesignrequirements;throughtenderingtheprojectdesignintothemarket,comparedtoselectthebestdesignunits.
3.2Promotingthedesignbiddinganddesignoptimizationcampaignmode
DesignunitsassessedbyexpertsusingscientificgroupFrance,inaccordancewithapplicable,economic,aestheticprinciplesandadvancedtechnology,reasonablestructuretomeetbuildingenergyefficiencyandenvironmentalrequirements,comprehensiveassessmentofthemeritsoftheprogramdesign,selectionofthebestdeterminationofthesuccessfulprogram.
Successfulinvestmentprogramestimatedtobeclosetothegeneralconstructionprojectscopeofinvestment.Thismeanstwodesigncontractswillhelpdesigntheprogramofchoiceandcompetitiontoensurethattheselecteddesignadvancedtechnology,uniquenovelty,adaptability,aswellastocontrolthecostoftheproject.Designunitsshouldstrivetoimprovetheirqualityoftheprojectdesigncleveridea,contemporaryreducingtheprojectcostontoracktheirbrainstoimprovedesignquality,strivetoputthedesignphaseoftheprojectcostcontrolapprovaloftheinvestmentceiling.
3.3Strengtheningthedesignstage
ThedesignphasetostrengthensupervisionoftheCommissionertodetermineareasonabledesign,maturetechnology,reductionintheconstructionphasemajordesignchangesandchangesintheprogram,intheeffectivecontroloftheprojectcostwillplayarole.1tothedesignoftheprojectiftheprojectsupervisiontogetinvolved,excludingunfavorablefactorsmaygenerallyisexcludedfromthe80%errors.Intheentireprocessofbuildingcostcontrol,constructionbeganatbesttosaveandinvest20%,thekeyliesintheconstructionphaseoftheidentificationandcontrolcosts.Supervisionofthedesignphaseinclude:DesignInstituteunderthedesigndrawingsandnoteshelpownersdealwithdifferentdesignoptionsfortheeconomy,capitalexpendituretodevelopthepreliminaryestimates,toensurethattheinvestmentcanbemosteffectivelyutilized.WiththeownersoftheCommissionerinclude:
AccordingtotheDesignInstitutetoprovidedesigndrawingsandnotestohelpownersdealwithdifferentdesignoptionsfortheeconomy,capitalexpenditurestodevelopthepreliminaryplantoensurethatinvestmentcanbemosteffectivelyused;withtheownersofdifferentdesignoptions,theneedtocalculatetheirownmaterialsandequipmenttoconductacostanalysisandstudy,tothedesignstaffcosts,toassistthemintheinvestmentlimitwithinlimitsdesignedtosaveandinvest.Toseekaone-timesmallinvestmentandeconomicgooddesignprogrammadethemostrationaleconomicindicators.
3.4Designactivelypromotetheso-calledcaplimitdesign
Evenwiththeapprovalofthedesigntaskandinvestmentestimates,guaranteethefunctionalrequirementsofthepremise.Thepreliminarydesignandcontrolbudget,accordingtothepreliminaryapprovalofthetotalbudgetforthedesignandconstructiondesigncontrol.Limits,andeveryoneprofessional,eachofwhomhaveadesignthresholdofatarget.Inthedesignprocess,designersshouldprogresstomoreprograms,designoptimization,ensuringthatthedesignistechnicallyadvancedandreasonable,innovative,stylish,anddonotbreakthelimitinvestmentobjectives,thuseliminatingtheengineeringdesignraisethefactorofsafetyanddesignstandards,oronlyconsiderthetechnicalfeasibilityoftheprogram,ratherthaneconomicrationalityphenomenon,theprojectcosttoensureeffectivecontrol.
Alsoknownasthevalueofvalueengineeringanalysis,isamodernscientificmanagementtechnique,isanewtechno-economicanalysis,istheproductoffunctionalanalysistoconserveresourcesandreducethecostofthepurposeofaneffectivemethod.Itmadeupforthetraditionalcostmanagementsimplyfocusoncostreductionandqualitymanagementonlyemphasizesimprovingthequalitydeficiencies,constructionisconducivetoresolvingthelong-standinglongperiod,alotofwastage,poorquality,high-costproblems.ValueEngineeringlawsgenerallydividedintothreesteps:assessmentofthedesignofobjecttechnologyandeconomicScore;Calculationofthetargetgroupoftechnicalandeconomicindicators;calculatethegeometricdesignoftheobject,onaverage;fromcomparisonchoosethebestdesign.
Constructionphaseoftheprojectimplementationunitconstructioncostmanagement
Itisreasonabletocontrolthecostoftheprojectintheprojecttomeetqualitystandardspremise,intheinvestmentdecision-makingstage,thedesignphaseandconstructionphaseoftheprojectputtheprojectapprovaloccurredinthecontrollimits,striveinvariousconstructionprojectsrationaluseofhuman,materialandfinancialresourcestoachievegoodinvestmentreturnsandsocialbenefits.
Theprojectcostcontrolandmanagementisadynamicprocess.Thedynamicmarketeconomy,tomaketheinvestmentintheidentificationandcontrolbecomemorecomplex,thiswillrequiretheconstructionunitstothemanagementofprojectcosttotheprojectrunsthroughtheentireprocess,itisnecessarytohaveacomprehensivefocus.
Theimplementationphaseoftheprojectcostmanagementistheimplementationoftheentireprocessofprojectmanagement.Projectimplementationphaseoftheprojectcostmanagementcanbedividedintothreeparts:thetendermanagement,constructionmanagementandsettlementmanagement.
4.1Biddingfortheconstructionphaseoftheconstructionunits
Biddingsystemcontrolengineeringcosteffectivemeans,bidorganizationcanimprovethecost-effectivenessofconstructionprojectsandensurethequalityofconstructionprojects,shorteningtheconstructioncyclereturnontheinvestment,constructionunitscantakefulladvantageofbiddingfortheeffectivemeansofcostcontrol.
ConstructionNo.10onthe7thministerialdecreeissueda"contractwiththeConstructionContractPricingManagement."clearlypointedoutinbiddingforprojectsusinginventories.Thisrequiresthebuildingofunitsconductingthetenderexercise,inthetenderdocumenttoincludenotonlytheusualcontent,liketendernotesbeforeschedule,tendernotes,theconditionsofthecontract,thecontracttermsoftheagreement,contractformat,technicalspecifications,drawings,tenderdocumentsandotherreferenceformat,itisalsonecessarytoprovidetheengineeringinventory,Biddingasareferencedocumentoftheimportantcomponents.
Constructionunitsinthetenderdocumentfortheprojectinventory,inaccordancewithstateorlocalrulespromulgatedbythecalculationthatthereunificationofthedividedprojects,unifiedmeasurementunitsandthereunificationoftheengineeringcalculationrules,accordingtodesigndrawingstobecalculatedandstatisticalarranged,obtainthelist.Quantitiestobefollowedinthepreparationofanobjective,impartial,scientific,andrationalprinciple.Compilersmusthavestrongmanlybudget,andshouldhavecertainknowledgeoftheengineeringdesignandconstructionexperience,andthematerialandmechanicalconstructiontechnologyforcomprehensivescientificknowledge,inordertocalculatethevolumeoftheworkswithoutheavymissed.Thebasisofwhichmustbeinaccordancewithstateregulationsengineeringcalculationrules,andthesub-projectsdivisionengineeringunits,andinaccordancewithdesigndrawings,designessentialLovetenderdocumentationrequirementsarecalculated.
Quantitiesoftheprojectshouldhaveatestinggeneral,theentriesmustbesimple,whilenotappearLousingwrongitemsPricingshouldguaranteethecorrectnessoftheproject.Shouldtherequirementsofthedifferentgradesseparateengineeringdivision,thesituationwasdifferent;wemayhavedifferentpricesfortheitemsseparately.Thisrequiresthepreparationofthelistcompilers,seriouslystudydesigndrawings,Analysisofthetenderdocumentsincludetheelementsoftheworkandthedifferenttechnicalrequirements,allfamiliarwiththeprocess,andtothesceneofseriousinvestigation,isforecasttomakepossibletheconstructionofthecase,rightwillhaveanimpactonthePriceofprojectstobebrokendown.Inaddition,becausetheprojectinventoriestocalculatetheamountoftheprojectisnotcompleteengineeringandconsidertheinterestsoftheconstructionunits,clearlypayingthepriceforthesameoverallprice,thequantitylistbythenumberofactualconstructionisapracticalterms.
IntheevaluationandreviewofthetenderoffershoulddotheunitstotalindividualPricequotationsandthecomprehensiveassessment.PricedoesnotmeettherequirementsofindividualshowsPricemeetstherequirements,andthelowesttotalPricecouldnotexplainthesinglelowestbidder.Biddersoftenknowthetotalcosttomaintainthesamecircumstances;theprojectislikelytochangesmallerprojectstolowertheprice.
Changesmaybelargerprojectspriceincreasestoachievethecompletionofclearingworkswillbeaddedforthepurpose.Wewouldalsodopriceandthecorrespondingquantityofcomprehensiveengineeringassessmentofthelargevolumeofprojectstofocusonthepriceanalysis.Pricewilldowiththecontentsofthework,constructionprogram,acomprehensivetechnicalevaluationprocess,therebypreferredchoiceofaconstructionunit.Constructionoftheconstructionphaseofthecontractcostcontrolbasis.Signedtightconstructioncontract,whilestrengtheningtheconstructioncontractmanagementcanguaranteethatthecontractpriceisreasonable,legitimacyandreducetheperformanceofthecontractA,Bindisputesandsafeguardtheinterestsofboththecontract,effectivecontroloftheworksinvestmentcosts.
Afterthesigningofthecontract,todothemanagementcontractdocumentation,contractandthesupplementarycontractagreementuntiltheregularmeetingsiteinminutes.Workcontactssuchasasinglecontentofacontractextensionandexplainedthattheintegritymustbepreserved,inadditiontoestablishingatechnicalfiles,Implementationofthecontractfordynamicanalysis,resultsoftheanalysistotakeproactivemeasures.
4.2Constructionphase
IntheconstructionphaseconstructionplanisbasedonthebudgetorKenworkscontractpriceofthetarget,Kencontrolthecostoftheproject.Atthisstageofconservationhasroomforasmall,butthepossibilityofwasteisgreat.Therebytocontrolthecostoftheprojecttogivesufficientattention.
4.2.1Constructionprogram
Constructionprogramtostrengthenthecomparativetechnicalandeconomicconstructionprogramisconstructiondesignofare-tothecontentsofthework,areasonableconstructionplan,shortentheconstructionperiodandensurethequalityoftheproject,improvingeconomicefficiency,Constructionoftheprogramrightfromthetechnicalandeconomicevaluationwerecompared,throughqualitativeandquantitativeanalysis,thequality,time,Costthreetechnicalandeconomicindicators,berational,andeffectiveuseofmanpower,materialandfinancialresources,achievebettereconomicefficiency,goodconstructionmanagementrelations,acomprehensivecostmanagementisanimportantway.
4.2.2Strictlyrelatedchangestotheprojectbudgetcontrolintheproposedbudget.
Constructionofthechangescausedbymanyreasons,includingworkspoorlydesigned,sothattheengineeringcontractwiththedrawingsprovidedinconsistent;Thecurrentmarketsupplyofmaterialsdonotmeetthestandardspecificationsofthedesignrequirements.Theseissueshavetoleavebreadwinnerprojectcostfactors.Therefore,intheconstructionprocess,wemusttightencustomschange,throughnodesignchangestoexpandthescaleandimprovethedesignstandards;increasetheconstructionandcontents,thebestimplementationofthe"gradecontrol,visaquota"system.Righttochangethedesign,particularlyasitrelatestothecostofthedesignchangesmustbeapprovedbythedesignunits,constructionunitsscenerepresentatives,supervisionengineerscommonsignature,andshouldbeaheadofthistypeofchange,reducelosses,becauseithasbeencompletedorpartiallycompletedprojectwillentailthedemolitionofthecontents,itisboundtocausemajorchangestotheloss.Therefore,theconstructionunitsshouldbeassignedtotheprojectcostmanagementprofessionalsPermanentconstructionsite,tograspatanytime.Controlprojectcostofthechanges.
4.2.3Worksonthescenevisaformalities
Throughstrictcontroloftheconstructionprojectsupervisionsystem,theestablishmentofspecializeddepartments,Professionaluseoftheprofessionalmanagementofprojectsandtoavoidprojectmanagementpersonneljustvisas,noteconomicaccountofthephenomenon.Investmentoutofcontrolcausedseriousconsequences.Toseriouschangevisaprocedurestobetakentothebuilding,Supervisor,theconstructionsitetogetherrepresentativessignedthewaytoensurethatchange,visaauthenticity,legitimacy,economicandavoidfraudandtheresultingphenomenaarisingfromthedispute.
Inthecourseofconstruction,theconstructionunitstoenhanceon-siteconstructionmanagement,supervisionandconstructionsideaccordingtothedrawings,andstrictlycontrolthechangeofthenegotiations,materialssubstitution,thescenevisas,andvariousadditionalextrabudgetarylaborcostsforthenecessarychangesshouldbedonefirstafterwards,aftermoney,Changeeventonthetimelychangeinthecalculationoftheworkloadandthecostofchangeoccurredtograspatanytimecostoftheprojectlevel,thingstoavoidabacklogofworkthatthetruecostoftheproject.
Constructionunitrepresentativestothescenetosupervisedoingagoodjobrecord,particularlyconcealedrecordsandvisas,reduceclearingthepassingphenomenon.Manyworksvisasceneisnotasserious,workstobringaverylargesettlementofthetrouble,leadtoconsiderableeconomiclosses,thescenestrictvisamanagementoftheconstructionphaseoftheprojectcostcontrolkey.
Ofprojectlistrigorousreviewoftheprojectonthereviewofinventories
Engineers’monitorlistofmeasurestocontroltheproject.BOQtoprovidethelistofmeasuresistocompleteconstructionprojects,occurredinthepre-constructionengineeringandconstructionprocesstechnology,lifeandsafetyaspectsofnon-engineeringprojectsentities.Atthisstagebecausemanyprojectsareinconstructionplansandtheconstructionsiteoftheimperfectionsonthetenderwaituntiltheconstructiontenderoftheprojectdesignandactualscenehavebetteraccess.ManagementEngineeraddressesthegatheringfirst-handinformationontheoriginal,itemizedcheckingidentification,inconsistentmakerevisions.
Controlmaterialconsumption,rationallyd
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- CJ/T 531-2018生活垃圾焚烧灰渣取样制样与检测
- CJ/T 365-2011地铁与轻轨车辆转向架技术条件
- CJ/T 351-2010高位调蓄叠压供水设备
- CJ/T 179-2018自力式流量控制阀
- 习题集锦初级社会工作者考试试题及答案
- 极限挑战下的软件评测师考试试题及答案
- 中级社会工作者考试相关技术技能的提升及试题及答案
- 初级社会工作者是什么样的职业试题及答案
- 摩托转让合同协议书范本
- 2025年网络规划设计师考试详细解析试题及答案
- 《中华人民共和国医疗保障法》解读与培训
- 2025届辽宁省葫芦岛市第二次模拟考试二模英语试题(原卷版+解析版)
- 中国碳化硼陶瓷项目商业计划书
- 2025新疆交投集团所属子公司招56人笔试参考题库附带答案详解
- 2025年生物统计学考试题及答案详解
- 建筑智能化试题及答案
- 第五讲铸牢中华民族共同体意识-2024年形势与政策
- 2024结肠锯齿状病变诊断及治疗进展
- NB-T 47013.1-2015 承压设备无损检测 第1部分-通用要求
- (完整版)中国古代书法史课件
- 《新能源材料与器件》教学课件-04电化学能源材料与器件
评论
0/150
提交评论