分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第1页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
,,铸铁管及管件部分,,,,,891412.72
1,040501003001,铸铁管,"1.材质及规格:球墨铸铁管K9DN300*7.2mm(工作压力为0.6MPa,试压压力1.1MPa。)
2.垫层、基础材质及厚度:150mm厚中粗砂垫层
3.接口方式:梯唇形橡胶圈接口
4.外壁采用环氧煤沥青涂料防腐,防腐等级为四油一布;内防腐采用离心水泥砂浆衬里,内防腐技术标准参照CECS10:89。
5.管道检验及试验要求:冲洗、消毒、试压",m,1988.350,418.35,831826.22
,W5-70,非定型井、渠、管道基础垫层.砂,,10m3,27.618,2696.59,74477.51
,W1-115,球墨铸铁管安装(胶圈接口)公称直径300mm以内,,10m,198.835,2775.53,551895.37
,W1-254,管道消毒冲洗公称直径350mm以内,,100m,19.884,363.55,7228.95
,W1-233,管道试压公称直径300mm以内,,100m,19.884,606.38,12057.46
,W4-4,环氧煤沥青漆加强级一底一布三油,,10m2,203.535,914.63,186166.93
2,040501003002,铸铁管,"1.材质及规格:球墨铸铁管K9DN200*6.4mm(工作压力为0.6MPa,试压压力1.1MPa。)
2.垫层、基础材质及厚度:150mm厚中粗砂垫层
3.接口方式:梯唇形橡胶圈接口
4.外壁采用环氧煤沥青涂料防腐,防腐等级为四油一布;内防腐采用离心水泥砂浆衬里,内防腐技术标准参照CECS10:89。
5.管道检验及试验要求:冲洗、消毒、试压",m,120.950,277.97,33620.47
,W5-70,非定型井、渠、管道基础垫层.砂,,10m3,1.491,2696.59,4021.02
,W1-113,球墨铸铁管安装(胶圈接口)公称直径200mm以内,,10m,12.095,1737.57,21017.99
,W1-251,管道消毒冲洗公称直径200mm以内,,100m,1.210,211.42,255.74
,W1-232,管道试压公称直径200mm以内,,100m,1.210,507.36,613.71
,W4-4,环氧煤沥青漆加强级一底一布三油,,10m2,8.431,914.63,7712.01
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第2页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
3,040501003003,铸铁管,"1.材质及规格:球墨铸铁管K9DN100*6.1mm(工作压力为0.6MPa,试压压力1.1MPa。)
2.垫层、基础材质及厚度:150mm厚中粗砂垫层
3.接口方式:梯唇形橡胶圈接口
4.外壁采用环氧煤沥青涂料防腐,防腐等级为四油一布;内防腐采用离心水泥砂浆衬里,内防腐技术标准参照CECS10:89。
5.管道检验及试验要求:冲洗、消毒、试压",m,19.350,165.90,3210.17
,W5-70,非定型井、渠、管道基础垫层.砂,,10m3,0.208,2696.59,560.90
,W1-112,球墨铸铁管安装(胶圈接口)公称直径150mm以内[柔性离心球墨承插铸铁给水管DN100],,10m,1.935,983.47,1903.06
,W1-250,管道消毒冲洗公称直径100mm以内,,100m,0.194,134.53,26.03
,W1-231,管道试压公称直径100mm以内,,100m,0.194,332.73,64.38
,W4-4,环氧煤沥青漆加强级一底一布三油,,10m2,0.717,914.63,655.80
4,040502001003,铸铁管管件,"1.材质:球墨铸铁K9
2.规格:DN300*200异径全承三通",个,14.000,552.39,7733.46
,W2-258,铸铁管件安装(胶圈接口)公称直径300mm以内[DN300*200异径全承三通],,个,14.000,552.39,7733.46
5,040502001001,铸铁管管件,"1.材质:球墨铸铁K9
2.规格:DN300*100异径全承三通",个,16.000,477.62,7641.92
,W2-258,铸铁管件安装(胶圈接口)公称直径300mm以内[DN300*100异径全承三通],,个,16.000,477.62,7641.92
6,040502001004,铸铁管管件,"1.材质:球墨铸铁K9
2.规格:DN30045°双承弯头",个,16.000,461.28,7380.48
,W2-258,铸铁管件安装(胶圈接口)公称直径300mm以内[DN30045°双承弯头],,个,16.000,461.28,7380.48
,,PE管及管件部分,,,,,861.21
7,040501004001,塑料管,"1.垫层、基础材质及厚度:150mm厚砂垫层
2.材质及规格:HDPEPE100dn60PN=1.6MPa
3.连接形式:电熔连接
4.管道检验及试验要求:管道试压、冲洗、消毒",m,12.650,68.08,861.21
,W5-70,非定型井、渠、管道基础垫层.砂,,10m3,0.176,2696.59,474.52
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第3页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
,B1-33,聚乙烯燃气管安装(电熔连接)管外径(mm以内)63[HDPEPE100dn60PN=1.6MPa],,10m,1.265,262.85,332.45
,W1-231,管道试压公称直径100mm以内,,100m,0.127,332.73,42.08
,W1-249,管道消毒冲洗公称直径50mm以内,,100m,0.127,96.15,12.16
,,消火栓、阀门及阀门井,,,,,230686.88
8,040502010002,消火栓,"1.名称:室外地上式新型防撞式消火栓
2.规格:SS100/65-1.0
3.安装部位:室外
4.C20混凝土支墩400x400x100
5.做法详见13S201-13",个,18.000,802.07,14437.26
,W3-120,地上式消防栓安装[室外地上式新型防撞式消火栓SS100/65-1.0],,个,18.000,787.21,14169.62
,W5-64换,管道支墩(挡墩)无筋(每处)5m3以下,,10m3,0.029,9229.12,267.64
9,040502005003,阀门,"1.种类:软密封闸阀Z45X-1.0
2.规格:DN300
3.加装伸缩节",个,6.000,4871.32,29227.92
,B3-47,焊接法兰阀门安装公称直径300mm以内[软密封闸阀Z45X-1.0DN300],,个,6.000,3102.21,18613.26
,3081-311,法兰式套筒伸缩器安装(焊接)DN300,,个,6.000,1769.11,10614.66
10,040502005001,阀门,"1.种类:软密封闸阀Z45X-1.0
2.规格:DN200
3.加装伸缩节",个,12.000,2445.16,29341.92
,B3-45,焊接法兰阀门安装公称直径200mm以内[软密封闸阀Z45X-1.0DN200],,个,12.000,1456.48,17477.76
,3081-310,法兰式套筒伸缩器安装(焊接)DN200,,个,12.000,988.68,11864.16
11,040502005004,阀门,"1.种类:铜杆闸阀Z45T-1.0
2.规格:DN60",个,2.000,246.43,492.86
,B3-39,焊接法兰阀门安装公称直径50mm以内[铜杆闸阀Z45T-1.0DN50],,个,2.000,246.43,492.86
12,040504002001,混凝土井(DN300),"1.名称:地面操作钢筋混凝土矩形立式闸阀井(井深1.8m)
(2)规格:1300*1300mm
(3)做法详见07MS101-2-66",座,6.000,7305.91,43835.46
,P3-4,非定型井混凝土垫层,,10m3,0.192,6533.05,1254.35
,P5-19换,现浇钢筋混凝土半地下室平池底.厚度50cm以内[C25预拌普通混凝土(粒径20mm)],,10m3,0.307,6085.76,1868.33
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第4页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
,P5-29换,现浇钢筋混凝土池直、矩形池壁.厚度20cm以内[C25预拌普通混凝土(粒径20mm)],,10m3,0.941,7353.47,6919.62
,P7-81,现浇构件钢筋.直径10mm以内,,t,1.980,4988.89,9878.00
,P3-98换,井室盖板预制[C25预拌普通混凝土(粒径20mm)],,10m3,0.156,8260.54,1288.64
,P3-109,矩形井室盖板安装.每块体积在0.3立方米以内,,10m3,0.156,3084.91,481.25
,P3-24,非定型井圈制作,,10m3,0.360,6526.44,2349.52
,Q5-3,预制砼钢筋制作、安装φ10mm以内,,t,0.642,5754.63,3694.47
,M3-62换,"井盖安装铸铁盖、座[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时),湿拌砌筑砂浆m7.5设计稠度60~90(凝结时间8-12小时)]",,套,6.000,553.60,3321.60
,B2-128,刚性防水套管制安公称直径300mm以内,,个,12.000,1052.15,12625.78
,独立费,塑钢踏步,,个,30.000,5.13,153.90
13,040504002002,混凝土井(DN200),"1.名称:地面操作钢筋混凝土矩形立式闸阀井(井深1.8m)
(2)规格:1300*1300mm
(3)做法详见07MS101-2-66",座,12.000,6701.41,80416.92
,P3-4,非定型井混凝土垫层,,10m3,0.384,6533.05,2508.69
,P5-19换,现浇钢筋混凝土半地下室平池底.厚度50cm以内[C25预拌普通混凝土(粒径20mm)],,10m3,0.614,6085.76,3736.66
,P5-29换,现浇钢筋混凝土池直、矩形池壁.厚度20cm以内[C25预拌普通混凝土(粒径20mm)],,10m3,1.882,7353.47,13839.23
,P7-81,现浇构件钢筋.直径10mm以内,,t,3.960,4988.89,19755.98
,P3-98换,井室盖板预制[C25预拌普通混凝土(粒径20mm)],,10m3,0.312,8260.54,2577.29
,P3-109,矩形井室盖板安装.每块体积在0.3立方米以内,,10m3,0.312,3084.91,962.49
,P3-24,非定型井圈制作,,10m3,0.720,6526.44,4699.04
,Q5-3,预制砼钢筋制作、安装φ10mm以内,,t,1.284,5754.63,7388.94
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第5页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
,M3-62换,"井盖安装铸铁盖、座[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时),湿拌砌筑砂浆m7.5设计稠度60~90(凝结时间8-12小时)]",,套,12.000,553.60,6643.20
,B2-126,刚性防水套管制安公称直径200mm以内,,个,24.000,749.90,17997.60
,独立费,塑钢踏步,,个,60.000,5.13,307.80
14,040504002003,混凝土井(DN60),"1.名称:地面操作钢筋混凝土矩形立式闸阀井(井深1.2m)
(2)规格:1100*1100mm
(3)做法详见07MS101-2-66",座,2.000,4830.73,9661.46
,P3-4,非定型井混凝土垫层,,10m3,0.052,6533.05,339.72
,P5-19换,现浇钢筋混凝土半地下室平池底.厚度50cm以内[C25预拌普通混凝土(粒径20mm)],,10m3,0.078,6085.76,474.69
,P5-29换,现浇钢筋混凝土池直、矩形池壁.厚度20cm以内[C25预拌普通混凝土(粒径20mm)],,10m3,0.180,7353.47,1323.62
,P7-81,现浇构件钢筋.直径10mm以内,,t,0.432,4988.89,2155.18
,P3-98换,井室盖板预制[C25预拌普通混凝土(粒径20mm)],,10m3,0.036,8260.54,297.38
,P3-109,矩形井室盖板安装.每块体积在0.3立方米以内,,10m3,0.036,3084.91,111.06
,P3-24,非定型井圈制作,,10m3,0.148,6526.44,965.91
,Q5-3,预制砼钢筋制作、安装φ10mm以内,,t,0.224,5754.63,1289.04
,M3-62换,"井盖安装铸铁盖、座[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时),湿拌砌筑砂浆m7.5设计稠度60~90(凝结时间8-12小时)]",,套,2.000,553.60,1107.20
,B2-122,刚性防水套管制安公称直径80mm以内,,个,4.000,386.59,1546.36
,独立费,塑钢踏步,,个,10.000,5.13,51.30
15,040504001003,排泥阀井φ1200,"1.名称:砖砌排泥阀井(井深1.5m)
2.规格:D1200
3.阀门井内球墨铸铁爬梯需刷环氧煤沥青两道
4.dn100钢筋混凝土排泥管安装
5.具体做法详见07MS101-2/58",座,2.000,4911.98,9823.96
,P3-4,非定型井混凝土垫层[C10预拌普通混凝土(粒径20mm)],,10m3,0.068,6533.05,444.25
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第6页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
,W5-79换,非定型井、渠、管道基座.混凝土基础,,10m3,0.112,10344.10,1158.55
,P3-5换,砖砌圆形非定型井[湿拌砌筑砂浆m10设计稠度60~90(凝结时间8-12小时)],,10m3,0.608,6605.20,4015.99
,3112-80换,一般钢结构沥青漆第一遍,,100kg,0.516,55.67,28.72
,3112-81换,一般钢结构沥青漆第二遍,,100kg,0.516,55.19,28.47
,P7-82换,现浇构件钢筋.直径20mm以内[φ12-14螺纹二级钢筋],,t,0.122,4001.26,488.15
,P3-12换,非定型井内侧砖墙抹灰[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时)],,100m2,0.126,4035.19,509.24
,P3-12换,非定型井外侧砖墙抹灰[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时)],,100m2,0.181,4035.19,728.35
,P3-98换,井室盖板预制[C25预拌普通混凝土(粒径20mm)],,10m3,0.044,8260.54,363.46
,P3-106换,盖板安装[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时)],,10m3,0.044,1957.83,86.14
,Q5-3,预制砼钢筋制作、安装φ10mm以内,,t,0.082,5754.63,471.88
,M3-62换,"井盖安装铸铁盖、座[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时),湿拌砌筑砂浆m7.5设计稠度60~90(凝结时间8-12小时)]",,套,2.000,553.60,1107.21
,P1-90,平接(企口)式管道铺设.人工下管.管径200mm以内[dn100钢筋混凝土排泥管],,100m,0.100,3935.48,393.55
16,040504001004,排泥湿井φ1000,"1.名称:砖砌排泥湿井(井深1.5m)
2.规格:D1000
3.阀门井内球墨铸铁爬梯需刷环氧煤沥青两道
4.具体做法详见07MS101-2/59",座,2.000,2366.89,4733.78
,P3-4,非定型井混凝土垫层[C10预拌普通混凝土(粒径20mm)],,10m3,0.056,6533.05,365.85
,W5-79换,非定型井、渠、管道基座.混凝土基础[C25预拌普通混凝土(粒径20mm)],,10m3,0.088,10344.10,910.27
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第7页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
,P3-5换,砖砌圆形非定型井[湿拌砌筑砂浆m10设计稠度60~90(凝结时间8-12小时)],,10m3,0.224,6605.20,1479.54
,3112-80换,一般钢结构沥青漆第一遍,,100kg,0.190,55.67,10.58
,3112-81换,一般钢结构沥青漆第二遍,,100kg,0.190,55.19,10.49
,C7-8换,"水泥砂浆抹面[1:2水泥防水砂浆,湿拌抹灰砂浆m10设计稠度90~110(凝结时间8-12小时)]",,100m2,0.187,4547.20,849.86
,M3-62换,"井盖安装铸铁盖、座[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时),湿拌砌筑砂浆m7.5设计稠度60~90(凝结时间8-12小时)]",,套,2.000,553.60,1107.19
17,040504001005,砌筑井(排气井)Φ1200,"1.名称:砖砌圆形排气井(井深1.75m)
2.规格:D1200
3.阀门井内球墨铸铁爬梯需刷环氧煤沥青两道
4.具体做法详见07MS101-2/52",座,2.000,4357.67,8715.34
,P3-4,非定型井混凝土垫层,,10m3,0.068,6533.05,444.25
,W5-79换,非定型井、渠、管道基座.混凝土基础,,10m3,0.112,10344.10,1158.54
,P3-5换,砖砌圆形非定型井[湿拌砌筑砂浆m10设计稠度60~90(凝结时间8-12小时)],,10m3,0.686,6605.20,4531.20
,3112-80换,一般钢结构沥青漆第一遍,,100kg,0.582,55.67,32.40
,3112-81换,一般钢结构沥青漆第二遍,,100kg,0.582,55.19,32.12
,P7-82换,现浇构件钢筋.直径20mm以内[φ12-14螺纹二级钢筋],,t,0.122,4001.26,488.15
,P3-98换,井室盖板预制[C25预拌普通混凝土(粒径20mm)],,10m3,0.044,8260.54,363.46
,P3-106换,盖板安装[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时)],,10m3,0.044,1957.83,86.14
,Q5-3,预制砼钢筋制作、安装φ10mm以内,,t,0.082,5754.63,471.88
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第8页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
,M3-62换,"井盖安装铸铁盖、座[湿拌抹灰砂浆m5.0设计稠度90~110(凝结时间8-12小时),湿拌砌筑砂浆m7.5设计稠度60~90(凝结时间8-12小时)]",,套,2.000,553.60,1107.20
,,标志桩及支墩,,,,,44132.52
18,040503002001,混凝土支墩,"(1)C20混凝土支墩
(2)支墩尺寸和做法详见标准图集10S505.",m3,46.000,922.92,42454.32
,W5-64换,管道支墩(挡墩)无筋(每处)5m3以下[C20预拌普通混凝土(粒径20mm)],,10m3,4.600,9229.12,42454.32
19,040503002002,混凝土支墩(阀门支墩),"(1)C20混凝土支墩
(2)支墩尺寸和做法详见图集",m3,20.000,83.91,1678.20
,W5-64,管道支墩(挡墩)无筋(每处)5m3以下,,10m3,0.187,8973.60,1678.20
,,六、新旧管连接,,,,,33707.97
20,040501014001,新旧管连接,"1.名称:碰口
2.规格:DN300*400",处,1.000,4612.90,4612.90
,W1-181,铸铁管新旧管连接(青铅接口)公称直径400mm以内,,处,1.000,4612.90,4612.90
21,040501014003,新旧管连接,"1.名称:碰口
2.规格:DN300*300",处,1.000,3239.91,3239.91
,W1-180,铸铁管新旧管连接(青铅接口)公称直径300mm以内,,处,1.000,3239.91,3239.91
22,040501014004,新旧管连接,"1.名称:碰口
2.规格:DN200",处,12.000,1944.18,23330.16
,W1-179,铸铁管新旧管连接(青铅接口)公称直径200mm以内,,处,12.000,1944.18,23330.16
23,040501014005,新旧管连接,"1.名称:碰口
2.规格:DN60",处,2.000,1262.50,2525.00
,W1-178,铸铁管新旧管连接(青铅接口)公称直径100mm以内,,处,2.000,1262.50,2525.00
,,路面拆除及恢复,,,,,679552.16
24,041001001001,拆除混凝土路面(市政机动),"1.材质:混凝土路面及垫层
2.厚度:65cm
3.切缝机切缝",m2,1885.910,66.91,126186.24
,C8-13换,液压岩石破碎机破碎混凝土类面层.厚底15cm内(实际厚度:65cm),,100m2,18.859,4471.66,84324.88
,L4-78,水泥混凝土路面伸缩缝锯缝机锯缝,,每10延米,409.034,102.35,41861.36
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第9页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
25,040103002002,余方弃置(市政机动),"1.废弃料品种:松散石方
2.运距:15km",m3,1225.840,46.78,57344.80
,C1-123换,挖掘机挖、自卸汽车运松散石方.运距1km以内(实际运距:15km),,1000m3,0.471,50164.29,23641.15
,C1-121换,挖掘机挖石碴、自卸汽车运碴.运距1km以内(实际运距:15km),,1000m3,0.754,44697.94,33703.65
26,040202001001,路床(槽)整形(市政机动),"1.工作内容:夯实基层
2.密实度:≥95%",m2,1885.910,1.43,2696.85
,C1-105,机械原土夯实(槽、坑),,100m2,18.859,143.02,2696.85
27,040202003002,水泥稳定土(市政机动),"1.水泥含量:4%水泥稳定石粉渣
2.压实厚度:20cm",m2,1885.910,41.29,77869.22
,L3-9换,"拌合机沿路拌合水泥石粉渣基层,水泥含量4%,压实厚度15cm(实际厚度:20cm)",,100m2,18.859,4128.40,77869.22
28,040202003001,水泥稳定土(市政机动),"1.水泥含量:6%水泥稳定石粉渣
2.压实厚度:20cm",m2,1885.910,44.11,83187.49
,L3-11换,"拌合机沿路拌合水泥石粉渣基层,水泥含量6%,压实厚度15cm(实际厚度:20cm)",,100m2,18.859,4410.70,83187.49
29,040203007001,水泥混凝土路面(市政机动),"1.名称:水泥混凝土路面
2.混凝土强度等级:C35,抗折45#
3.压实厚度:25cm
4.路面养生",m2,1885.910,166.07,313193.07
,L4-69换,水泥混凝土路面现浇水泥砼路面厚度24cm(实际厚度:25cm),,100m2,18.859,16319.44,307781.25
,L4-81,水泥混凝土路面水泥混凝土路面养生、真空吸水草袋养护,,100m2,18.859,286.95,5411.82
30,041001001002,拆除混凝土路面(社区机动),"1.材质:混凝土路面及垫层
2.厚度:42cm
3.切缝机切缝",m2,47.640,53.36,2542.07
,C8-13换,液压岩石破碎机破碎混凝土类面层.厚底15cm内(实际厚度:42cm),,100m2,0.476,2846.21,1355.77
,L4-78,水泥混凝土路面伸缩缝锯缝机锯缝,,每10延米,11.592,102.35,1186.30
31,040103002001,余方弃置(社区机动),"1.废弃料品种:松散石方
2.运距:15km",m3,20.010,47.55,951.48
,C1-123换,挖掘机挖、自卸汽车运松散石方.运距1km以内(实际运距:15km),,1000m3,0.010,50164.29,525.60
,C1-121换,挖掘机挖石碴、自卸汽车运碴.运距1km以内(实际运距:15km),,1000m3,0.010,44697.94,425.88
分部分项工程量清单报价表,,,,,,,
,,,,,,,,
工程名称:新湖路给水管网改造工程,,,,,第10页,共12页,,
序号,子目编号,子目名称,项目特征,单位,工程量,综合单价,合价
32,040202001002,路床(槽)整形(社区机动),"1.工作内容:夯实基层
2.密实度:≥95%",m2,47.640,1.43,68.13
,C1-105,机械原土夯实(槽、坑),,100m2,0.476,143.02,68.13
33,040202003003,水泥稳定土(社区机动),"1.水泥含量:6%水泥稳定石粉渣
2.压实厚度:20cm",m2,47.640,44.11,2101.40
,L3-11换,"拌合机沿路拌合水泥石粉渣基层,水泥含量6%,压实厚度15cm(实际厚度:20cm)",,100m2,0.476,4410.70,2101.40
34,040203007002,水泥混凝土路面(社区机动),"1.名称:水泥混凝土路面
2.混凝土强度等级:C35,抗折45#
3.压实厚度:22cm
4.路面养生",m2,47.640,147.75,7038.81
,L4-68,水泥混凝土路面现浇水泥砼路面厚度22cm,,100m2,0.476,14486.31,6902.09
,L4-81,水泥混凝土路面水泥混凝土路面养生、真空吸水草袋养护,,100m2,0.476,286.95,136.72
35,041001001003,拆除混凝土路面(社区非机动),"1.材质:混凝土路面及垫层
2.厚度:35cm
3.切缝机切缝",m2,29.360,50.13,1471.82
,C8-13换,液压岩石破碎机破碎混凝土类面层.厚底15cm内(实际厚度:35cm),,100m2,0.294,2351.53,690.44
,L4-78,水泥混凝土路面伸缩缝锯缝机锯缝,,每10延米,7.634,102.35,781.38
36,040103002003,余方弃置(社区非机动),"1.废弃料品种:松散石方
2.运距:15km",m3,10.280,47.04,483.57
,C1-123换
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 保险公司销售工作计划范文
- 工作总结和下一年工作计划
- 客服个人工作计划制定
- 小学六年级班级工作计划模板
- 关于新学期教师工作计划集合
- 小班第一学期班务计划范文
- 2025年护理培训工作计划例文
- 高中教师个人工作计划班主任工作计划
- 《螺纹的主要参数》课件
- 《融资服务方案》课件
- 美国经典动画解析-以《蓝精灵》为例
- 防护材料生产企业现场审核表
- 超星尔雅学习通《舌尖上的植物学》章节测试答案
- 国家开放大学《会计学概论》形考任务1-4参考答案
- 复合材料细观力学课件
- 某工厂总配变电所及配电系统设计论文
- 学前融合教育的理想与现实课件
- 肾素-血管紧张素系统药理课件
- oppo其它-lpdt工作手册
- 土传病害的发生规律和危害课件
- 中医诊所规章制度(完整版)
评论
0/150
提交评论