吊装计算立柱吊装就位(1)吊装设备选型吊装设备选型按重量最大的预制立柱考虑,最重约为129t,吊装最大相对高度按15m考虑(立柱最大高度为13.597m,承台预埋钢筋伸出0.42m,求得吊装最大相对高度为13.597+0.42=14.017m)。考虑选用1台250t履带吊,配合翻转台将立柱翻转竖立,然后履带吊吊装、旋转、就位。根据《建筑机械使用安全技术规程》(JGJ33-2001)第4.2.10条款的要求:起重机带载行走时,载荷不得超过允许起重量的70%。表错误!文档中没有指定样式的文字。-1双机抬吊额定起重量比选作业半径(m)臂长(30m)带载不走行作业带载走行作业(0.7)6154.3108.07154.3108.08154.3108.0913091.010116.281.31292.364.6工况一:吊臂长选定为30m,配合翻转台翻转时最大作业半径按12.0m考虑,带载不走行作业,额定起重量92.3t。单机吊装按立柱重量的一半即64.5t考虑,250t吊钩重量4.11t,共计68.61t<92.3t,满足吊装要求。工况二:吊臂长选定为30m,整体起吊立柱时最大作业半径按8.0m考虑,带载不走行作业,额定起重量154.3t。单机吊装立柱重量129t,250t吊钩重量4.11t,共计133.11t<154.3t,满足吊装要求。表错误!文档中没有指定样式的文字。-2QUY250履带吊起重性能表

口国度配y182124273033363042454851544.S2505220215/5.56210190108L1ITT.Il154.S.'S.77185ISO178L1173.1F154.3150.18166.6160.4157.4154.5|154.3148.2137130.6110/8.89140.9136135l2133.2130131.8128.2128.61081059510121.2119.711812117.2116.2113.3112.8110.S1051029585.S史飞.二二1294.693.19392.8P92.389.488.387.286.184.883.883.680147675.975.975.S75.173.772.771.871.2706963.S67.S16S4.163.662.563.4FS2.661.961.560.86059.35S.55S.357.61053.653.653.653.652.052.652.252.251.350.650.449.02046.S46.646.245.945.645.345.144.744.344.343.62241.141.14140.540.139.739.539.3393S.73S.42437.236.23635.735.435.134.934.634.3342632.632.432.131.731.631.23130.630.42829.72928.728.528.227.927.627.3302726.526.22S25.625.32524.73224.62423.623.423.122.922.43422.521.721.421.220.920.5362019.S19.419.2IS.9301S.217.917.717.34017.1IS.516.3164215.315.114.84413.913.74612.74811.9吊钩250吨吊钩(411□kg)]150吨吊岗(2400kg)倍率201316151313121199077(2)钢丝绳选择查《路桥施工计算手册》附表3-34,钢丝绳选用公称直径为72mm、规格6X61结构、公称抗拉强度为1700MPa的钢丝绳,钢丝绳破断力P为3300kN,考虑钢丝绳之间荷载不均匀系数。按6X61钢丝绳取0.80,钢丝绳的安全系数K按机动起重设备取6,则:钢丝绳的容许破断拉力S:更/80*3300=440kNbK6履带吊起吊时立柱预制节段最大自重Q取129t,按2个吊点平均承受构件荷载,每个吊点按4根钢丝绳计算(钢丝绳采用单根绕环),钢丝绳与水平面的夹角。按不小于60°考虑,则钢丝绳内力:S=Qg-1=1290g~L=186kN<S=440kN,满足要求。nsin9 2x4sin60 b(3)吊架设计吊架由钢管、槽钢、钢板等型材焊接而成。(4)卸扣选择根据设计图纸,立柱最大重量129t,立柱顶部设置2个吊点。根据每个吊点承受的重量,吊点及吊架底部的卸扣选用100t级,吊架顶部的卸扣选用150t级,满足要求。(5)吊点设置竖向吊点采用立柱顶预留的2处钢绞线吊索进行,吊索在混凝土浇筑前预埋,锚固深度满足受力要求。(6)地基处理履带吊自重230t,负载129t,吊具按4.1人计,总重363.11t,动载系数取1.2。履带吊与地面接触面积A=9x1.2x2=21.6m2地基承载力。=上式=.X兆311X104=202kPa,立柱吊装过程中,吊机位于原混A21.6x103凝土路面,可满足吊装承载要求。(7)吊装作业立柱通过翻转台完成翻转工况。先采用单机抬吊,直接卸车、立柱翻转竖立,然后转吊装,旋转、就位。盖梁节段吊装(1)吊装设备选型吊装设备选型按重量最大的预制盖梁节段考虑,最重约为220t,吊装最大相对高度按22.1m考虑(立柱最大高度为19.4780,埋入地面按1.50计,盖梁最大高度为4.1m,求得吊装最大相对高度为19.478-1.5+4.1=22.078m)。考虑选用2台250t履带吊双机抬吊卸车、吊装就位。根据《建筑机械使用安全技术规程》(JGJ33-2001)第4.2.9条款的要求:采用双机抬吊作业时,单机的起吊载荷不得超过允许载荷的80%;第4.2.10条款的要求:起重机带载行走时,载荷不得超过允许起重量的70%。表错误!文档中没有指定样式的文字。-3双机抬吊额定起重量比选作业半径(m)臂长(30m)带载不走行作业(0.8)带载走行作业(0.7)单机双机单机双机6154.3123.4246.9108.0216.07154.3123.4246.9108.0216.08154.3123.4246.9108.0216.09130104.0208.091.0182.010116.293.0185.981.3162.7吊臂长选定为30m,最大作业半径按8.0m考虑,额定起重量154.3t,带载不走行作

业,双机抬吊折减系数取0.8,折减后额定起重量为123.4t。单机吊装盖梁重量110t,250t吊钩重量4.11t,共计U4.11t〈123.4t,满足吊装要求。表错误!文档中没有指定样式的文字。-4QUY250履带吊起重性能表幅度限作182124273033363942454851544.82505220215/5.56210190108L1ITT.11二国.377185ISO178L1173.1r154.3150.18166.G160.4157.4154.5|154.314S.2137130.6110/8.89140.9136135l2133.2130131.8128.2128.61081059510121.2119.711812117.2116.2113.3112.8110.S1051029585.Sa3.fi/lC,1234.693.19392.8P92.389.48S.387.28S.184.883.883.680147675.975.975.S75.173.772.771.871.2706963.S67.S16S4.163.662.563.4F62.661.961.560.859.35S.558.357.61S53.653.653.653.652.S52.652.252.251.350.650.449.S2046.S46.646.245.945.645.345.144.744.344.343.62241.141.14140.540.139.739.539.33938.733.42437.236.23635.735.435.134.934.634.3342632.632.432.131.731.631.23130.630.42829.72928.728.528.227.927.627.3302726.526.22625.625.32524.73224.62423.623.423.122.922.43422.521.Y21.421.220.920.5362019.019.419.210.9381S.217.917.717.34017.1IS.516.3164215.315.114.84413.913.74612.74811.9吊钩250吨吊钩(411Okg)150吨吊物(2400kg)倍率201816151313121199S77(2)钢丝绳选择查《路桥施工计算手册》附表3-34,钢丝绳选用公称直径为72mm、规格6X61结构、公称抗拉强度为1700MPa的钢丝绳,钢丝绳破断力P为3300kN,考虑钢丝绳之间荷载不均匀系数。按6X61钢丝绳取0.80,钢丝绳的安全系数K按机动起重设备取6,则:钢丝绳的容许破断拉力\=厘=0.80:3300=440kNbK6履带吊起吊时盖梁预制节段最大自重Q取220t,按3个吊点平均承受构件荷载,每个吊点按4根钢丝绳计算(钢丝绳采用单根绕环),钢丝绳与水平面的夹角。按不小于60°考虑,则钢丝绳内力:S=Qg-1-=2200g~L=212kN<S=440kN,满足要求。nsin0 3x4sin60 b(3)吊架设计图错误!文档中没有指定样式的文字。-1吊架大样图吊架由钢管、槽钢、钢板等型材焊接而成。巾108加孔孔PL=80一跳三角整板图错误!文档中没有指定样式的文字。-1吊架大样图吊架由钢管、槽钢、钢板等型材焊接而成。巾108加孔孔PL=80一跳三角整板PL=32/板的低打先:12.6槽钢板两侧加强—X18幽辆管汗/板两侧加每300025010x250=2500250(4)卸扣选择根据设计图纸,盖梁最大重量220t,立柱顶部设置四个吊点,根据《公路钢筋混凝土及预应力混凝土桥涵设计规范》(JTGD62-2004),当一个构件设有四个吊点时,设计时仅考虑三个吊点同时发挥作用。根据每个吊点承受的重量,吊点及吊架底部的卸扣选用100t级,吊架顶部的卸扣选用150t级,满足要求。(5)吊点设置①盖梁吊点计算根据设计图纸,盖梁最大重量220t,立柱顶部设置四个吊点,根据《公路钢筋混凝土及预应力混凝土桥涵设计规范》(JTGD62-2004),当一个构件设有四个吊环时,设计时仅考虑三个吊环同时发挥作用。吊点采用钢绞线材质。②钢绞线根数计算盖梁最大重量G=2200kN吊装过程中,钢绞线控制应力取。°「1395MPa单根钢绞线承载能力设计值Fp「&-。.=139x1395403=193.kN钢绞线吊索采用单根绕环,即一根吊索两端均锚固在立柱内,吊装立柱所需要的钢绞线根数n=G2F7=2200(2x193.9=5.艰,根据工程实际,盖梁采用四个吊点,考虑2倍的安全pk系数,钢绞线根数取12根,每个吊点布置4根。③锚固长度计算仅考虑钢绞线与混凝土之间的握裹力,根据《公路钢筋混凝土及预应力混凝土桥涵设计规范》(JTGD62-2004),最小锚固长度一cO.—一1395一l=P—ped=0.16c *152141南加,最小锚固长度需要1.414m仃f2.4仅考虑固定端锚板与混凝土之间的作用力,4孔锚板截面尺寸为220X70mm,假设混凝土发生剪切或冲切破坏,保守计算取最小破坏面发生剪切破坏,混凝土取最小轴心抗拉强度计算,单个剪切面周长l=580mm最小埋置深度hh=-G-=:2紫0\=264mm考虑2倍的安全系数并取整,h取600mm;61-f 6义580*2.4根据OVM产品手册要求,ovm.PB15-4最小锚固长度320mm。综上所述,盖梁吊装钢绞线锚固深度取800mm。(6)地基处理履带吊自重230t,负载110t,吊具按4.1人计,总重344.11t,动载系数取1.2。履带吊与地面接触面积A=9x1.2x2=21.6m

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论