顶管法施工方案(英文版)_第1页
顶管法施工方案(英文版)_第2页
顶管法施工方案(英文版)_第3页
顶管法施工方案(英文版)_第4页
顶管法施工方案(英文版)_第5页
已阅读5页,还剩6页未读 继续免费阅读

下载本文档

版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领

文档简介

1、顶管法施工方案(英文版)顶管法施工方案(英文版)顶管法施工方案(英文版)V:1.0精细整理,仅供参考 顶管法施工方案(英文版)日期:20 xx年X月 Method Statement for Pipe JackingConstruction of PitsThe jacking pit with a dimension of 6mx5 clear opening with depth of 250mm below invert level of the steel pipe.The floor will be leveled by 100mm thick concrete blinding f

2、ixing tow I beams in the center of the pit for fixing jacking frame.Installation of Jacking FrameAfter the construction of drive, the jacking rig will be lowered into the pit and adjust to the control line and level. The rig will be used on this contract consist of two number of hydraulic cylinders

3、with a capacity of 150 ton each to give a total jacking force of 300 tons. The rig will have guided rails, pushing plate and base plate to hydraulic power back with control unit. The hydraulic system will run through a diesel engine installed the top of the pit.The rig will installed to the correct

4、line and level and check by the consultant in respect to level and alignment.Thrust WallConstructing a concrete block behind the base plate of the rig to a dimension of will be provided to take and distribute the jacking load.Pipe Jacking OperationA steel shield is used at the front of the pipe to a

5、ccommodate the miner and to allow for steering of the pipe jack. The soil within the shield is manually excavated and loaded into a wheel skip for transport to the pit bottom. The miner does not dig outside the shield (both in front and radically) and the front, or cutting edge, of the shield is alw

6、ays kept buried in the face, so stability is maintained. The shield is thus used to trim the excavation to the size of the pipe thus minimizing the potential for settlement of the ground above the pipe jack.In the pit bottom, the skip is hoisted to the surface, emptied and returned to the used to lo

7、osen it prior to digging. The exact diameter of shield will be selected to suit the pushing pipes.As excavation continues, the shield is jacking forward using two hydraulic jacks thrusting from the back wall. When the shield is buried, the jacks are retracted and the first sleeve pipe lowered on to

8、the rails. This in then pushed up to the shield and excavation can then continue.When the sleeve pipe is pushed home, the hydraulic jacks are retracted and the services (lighting& ventilation) disconnected. The next sleeve pipe is lowered on to the rails and the services reconnected and the cycle re

9、peated until the shield is pushed into the receiving pit and the pipeline pushed into final position.Maintaining Line and LevelIn order to maintain the correct line and level, a graduated target plate is located within the shield. The site engineer notes the position of the visible sport on the targ

10、et, this initial position is used as reference value to locate the relative position of the shield at all times during the drive. At each push, the site engineer monitors the position reference value with the help of level instrument and theodalite, thus giving a shield position (high or low, right

11、or left) relative to the design position. Based on this information, the operator manipulates a correct course.Extending or retracting a combination of steering rams causing the front of the shield to articulate in the required direction carries out the steering. As the pipe follows the shield, the

12、correct line and level will be maintained. At all times, the amount steering applied is kept to minimum.Fixing Carrier PipesAfter completion of the pipe jacking , we check the line and level for the steel pipe and we take the exact line and level for the carrier pipe with the help of survey instrume

13、nts.A 3 steel angle bar fixed by welding in the correct bottom level of the carrier pipe, then 3mm thick flat bar half moon claps will fixed through wielding in the correct line after that we put neoprene rubber 3mm thick in the clamp to avoid the scratches of the carrier pipes.Then we start laying

14、the carrier pipe one by one and fix the clamps through nuts and bolts. After fixing the nuts and bolts we make angle support in between the top of the clamp and top of the pipe. Then we fix the other pipe in the same manner. The same procedure will continues up to the requirement.GroutingUpon comple

15、tion of pipe jacking we make 4 2 holes like ventilation in every meter, it helps the concrete fill the gap between the steel pipe and ground. Then we fixed six inch grouting pipe vertically one meter height in the top of the pipe both end jacking and receiving. One side will keep ventilation and the

16、 other side for connection and the concrete pump.After that we lay the carrier pipe in the correct line and level then check with the consultant and make the test required from the consultant then we close the both end between steel and carrier pipe by m/s plate welding or masonry, the gap between steel sleeve and ground in the both end we c

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论