1、tdi train - infrastructure electrical system installation mv cable pulling construction plan tditdi 联合装置联合装置- -基础设施电气系统安装基础设施电气系统安装 中压电缆敷设施工方案中压电缆敷设施工方案 b11/30/2009issued for comments a11/26/2009issued for comments rev date dd/mm/yy statusprepared bychecked byapproved by document revisions 目目 录录 con

2、tent 一一. 概况概况 overview.3 1.1 工程概况工程概况 project overview.3 1.2 施工范围施工范围 scope of work.3 二编制依据二编制依据 compilation basis .4 三三 施工工艺流程:施工工艺流程:construction process .4 四四. 前期准备前期准备 preparation.4 4.1 技术准备技术准备 technical preparation.4 4.2 材料准备材料准备 material preparation.5 4.3 主要机具准备主要机具准备 main equipment preparati

3、on .5 4.4 作业环境准备作业环境准备 work environment preparation.6 五五. 敷设施工敷设施工 work of cable pulling.6 5.1 电缆敷设施工工序电缆敷设施工工序 work procedure.6 5.2 机具布置机具布置 layout of tools.6 5.2.1 电缆的搬运及支架架设电缆的搬运及支架架设 cable removal and cable tray.6 5.2.2 卷扬机与滑轮的布置卷扬机与滑轮的布置 winch and pulley arrangement.6 5.3 电缆展放电缆展放 lay-off cable

4、.10 5.4 电缆敷设、固定电缆敷设、固定 cable laying and fixing.12 六六. 覆砂盖砖覆砂盖砖 spread sand and cover bricks.12 七七. 回填土回填土 backfill earth .13 八八. 埋标桩埋标桩 burying stake.13 九九. 挂标志牌挂标志牌 hanging signs.13 十十. 质量控制质量控制 quality control.13 10.1 主控项目主控项目 master items.13 10.2 一般项目一般项目 general items.14 十一十一. 成品保护成品保护 finished

5、protection .14 十二十二. 质量记录质量记录 quality record.14 12.1 质量保证资料质量保证资料 quality assurance information.14 12.2 施工记录施工记录 construction of record.15 十三十三. 安全生产、文明施工要求和措施安全生产、文明施工要求和措施 safety and civilized construction requests and measures .15 一一. 概况概况 overview 1.1 工程概况工程概况 project overview 项目名称: tdi 联合装置厂区中压

6、电缆敷设施工。project name: tdi train plant medium voltage cable pulling work. 本工程涉及三个变电站,分别是现有的 220/35kv a472 变电站、现有的 35/10kv b301s 变电站 以及新建的 35/10kv c581 变电站,工作内容为三个变电站之间和从三个变电站接至 mv 用户的 电力电缆、控制电缆、接地电缆的敷设。the project involves three substations, namely the existing 220/35kv a472 substation, the existing 3

7、5/10kv b301s the 35/10kv c581 substation and a new substation. this is the power, control and grounding cable pulling among three substations and for mv users connected to the three substations. 1.2 施工范围施工范围 scope of work 1) a472 建筑(建筑(220/35kv 变电站)出线回路:变电站)出线回路:a472 building(220/35kv substation) ou

8、tlet circuit 由 a472 变电站引出 3 路 35kv 出线。其中: 一路引至 b301s 建筑(35/10kv 变电站)原 1#主变,原 1#主变电缆将抽出,与新增 4#主变连接; 另两路引至 35/10kv c581 变电站 1#主变和 2#主变。回路采用 fs-yjy-26/35kv-1*300mm2单芯 电缆,直埋敷设。去 c581 的两路 35kv 线路,敷设时沿不同路径,以避免两回线路同时受损。 pull three 35v outgoings from a472 substation. of which: the first outgoing is led to b

9、301s building (35/10kv substation) the original one # main transformer, pull the original one # main transformer cable out, and connect to the adding 4 # main transformer; the other two outgoings are led to 35/10kv c581 # 1 and substation 2 # main transformer. use fs-yjy-26/35kv-1 * 300mm2 single-co

10、re cables for loop and buried pulling. two 35kv lines to c581 are laid along different paths to avoid damage of the two loops. 2) b301s 建筑(建筑(35/10kv 变电站)出线回路:变电站)出线回路:b301s building (35/10kv substation) outlet circuit: 由 b301s 变电站引出 7 路 10kv 出线。全部引至 b399 中心制冷站。回路采用 10kv 截面为 95mm2的三芯铠装电缆,由 b301s 南面现

11、有的电缆井引出直埋至装置。pull 7 10kv outgoings from b301s substation to b399central refrigeration station. loop uses 10kv three-core armored cable with cross-section 95mm2 and pull out from the existing cable well in the south of b301s then buried lay to the device. 3) c581 建筑(建筑(35/10kv 变电站)出线回路:变电站)出线回路:c581

12、building (35/10kv substation) outlet circuit: 由 c581 引出 10 路 10kv 线路,分别为 a507 的四台变压器,b551 的两台变压器,b553tda 装 置氢气压缩机 2 台,c521 盐酸装置氯气压缩机 1 台,盐酸压缩机 1 台提供电源。其中,变压器 回路采用 10kv 截面为 185mm2的三芯铠装电缆,马达回路采用 10kv 截面为 95mm2的三芯铠装 电缆。以上电缆线路均沿规划路径埋地敷设。10 10kv lines led from c581 are used to supply power to a507s four

13、transformers, b551 two transformers, b553tda 2 sets of hydrogen compressor unit, c521 hydrochloric acid chlorine gas compressor unit, and hydrochloric acid compressor unit respectively. among them, transformer circuit uses x 3-core armored cable with 10kv cross-section 185mm2, motor circuit uses thr

14、ee-core armored cable with 10kv cross-section 95mm2. all cable lines will be laid underground along the planning path. 4) 接地电缆回路:接地电缆回路:ground cable loop: 从 a472 敷设一根 95mm2裸铜线去 c581,同时从 c581 敷设四根 95mm2裸铜线,分别引至 b551、a507、b553 和 c521,作等电位联结。以上电缆线路均沿规划路径埋地敷设。lay a 95mm2 bare copper wire to c581 from a4

15、72. meanwhile lay four bare copper wires to b551, a507, b553 and c521 for equipotential bonding. all cable lines will be laid underground along the planning path. overview 5) 控制电缆回路:控制电缆回路: control cable circuit: 安装在 hcl 装置现场的 3.6mw 马达上的电流信号通过一根直埋敷设的铠装控制电缆直接接入 10kv 开关柜。the current signal installed o

16、n 3.6mw motor in the hcl devices site passes through a buried armored control cable direct access to 10kv switchgear. 由变压器出线柜去 c581 以外的变压器,采用两根分别为 10*2.5mm2、4*2.5mm2屏蔽铠装控制电 缆,由中压转接柜引出,与中压电缆同路径敷设至相关变压器室。其中,10*2.5mm2 电缆直接 接至温控箱,4*2.5mm2 电缆可集中从某间变压器室引出,沿桥架至相关 pcs 楼 ats 柜。 transformer outlet cabinets ar

17、e connected to other transformers not in c581 by using two 10 * 2.5mm2, 4 * 2.5mm2 shield sheathed control cable respectively. the 10 * 2.5mm2 cable directly is connected to the temperature control box and 4 * 2.5mm2 cable are led out from transformer room, along the bridge to the relevant pcs floor

18、 ats cabinet. 二编制依据二编制依据 compilation basis 1)根据电气包(中压部分)招标文件及招标图纸编制而成。according to electric package (mv) the tender and tender drawings. 2)在充分研究工程的客观情况和施工特点,结合我公司类似工程施工经验的基础上编制的。 based on full study on construction characteristics and objective situation and combined with similar construction experi

19、ence. 3)在本方案编制过程中,严格执行国家现行建筑和安装工程施工及验收规范、规程、标准、设 计规范。具体如下:in this compilation process, strictly implement current national construction and installation construction, acceptance norms, procedures, standards, and design specifications. as follows: 电气装置安装工程电缆线路施工及验收规范 gb50168-2006 electrical installat

20、ion cable construction and acceptance standards gb50168-2006 电气装置安装工程接地装置施工及验收规范 gb50169-2006 electrical installation earthing construction and acceptance standard gb50169-2006 建筑电气工程施工质量验收规范 gb503032002 building electrical construction quality acceptance gb50303-2002 三三 施工工艺流程:施工工艺流程:construction p

21、rocess 前期准备电缆直埋敷设施工铺沙盖砖回填土埋标志桩挂标志牌 preparation cable buried pulling spread sand and build bricks backfillbury sign stake hang signs 四四. 前期准备前期准备 preparation 4.1 技术准备技术准备 technical preparation 1) 针对本工程特点编审详细的电缆沟施工作业指导书,及时组织图纸会审。compile particular cable trench construction engineering guide book as pe

22、r project characteristics and organize promptly drawings joint examination. 2) 根据上海市电力建设工程施工工艺实施细则结合本工程实际编写电缆沟施工工艺卡,并组织实 施。compile construction technique cards according to the shanghai municipal electric power construction engineering construction technology implementation details and organize its

23、implementation. 3) 施工人员全面了解电缆敷设来路、终点及敷设路径。construction workers have comprehensive understanding antecedents, destination, and laying path of laying cables. 4.2 材料准备材料准备 material preparation 1) 所有材料规格型号及电压等级应符合设计要求,并有产品合格证。all material specifications, models and voltage level should meet design requi

24、rements and have product certificates. 2) 每盘电缆上应标明电缆规格、型号、电压等级、长度及出厂日期。电缆盘应完好无损。 each cable should be marked on specification, model, voltage level, length and manufacture date. cable tray should be in a good condition. 3) 电缆外观完好无损,铠装无锈蚀、无机械损伤,光泽明亮无皱折和扭曲现象。电缆外皮及绝缘展 无老化及裂纹。 the cable exterior conditi

25、on is intact .the armor has no rust and no mechanical damage. it is shiny and bright without wrinkles and distortions. cable jacket and insulation show no aging and cracks. 4) 电缆敷设前进行绝缘摇测或耐压试验。测量绝缘用兆欧表的额定电压,采用如下等级:before laying carry out insulation rolling test or voltage withstand test. use megger

26、rated voltage to measure insulation. take the following level: 10kv 和 35kv 电缆:用 2500v 兆欧表。10kv and 35kv cable: the 2500v megger. 电缆测试完毕,应立即用橡塑材料封头。 when cable testing is completed, cover it with rubber materials immediately. 5) 按设计和实际路径计算每根电缆的长度,合理安排每盘电缆,无电缆接头。calculate each cable length according t

27、o design and actual path. arrange each cable reasonably without cable joints. 6) 电缆保护套管已经预埋好,故只需要清理管内残渣,并作好管口保护。cable protection sleeve has been embedded. clean pipe residue and protect nozzles. 7) 其它附属材料:电缆标示桩、电缆标志牌、油漆、汽油、封铅、硬脂酸、白布带、橡皮包布、 黑包布等均应符合要求。other subsidiary material: cable marking piles, c

28、able signs, paint, gasoline, sealed lead, stearic acid, white belt, rubber cloth, black cloth etc. should meet the requirements. 4.3 主要机具准备主要机具准备 main equipment preparation 卷扬机、敷设电缆用支架及轴、电缆滚轮、转向导轮、吊链、滑轮、钢丝绳、大麻绳、千斤顶。 winches, bracket and shaft for cable laying, cable roller, transfer guide wheel, han

29、ging chain, pulleys, wire rope, large hemp rope, jacks. 绝缘摇表、皮尺、钢锯、电缆端接线工具、手锤、扳手、电气焊工具、电工工具、弯管机、砂 轮机、电缆走向牌打印机、电缆号牌机、喷灯。insulation shake watch, measuring tape, hacksaw, cable-side wiring tools, hand hammers, wrenches, electric welding tools, electrical tools, bending machine, grinding wheel machine,

30、printer, cable plate machine, blowtorch. 无线电对讲机、手持扩音喇叭。walkie-talkies, hand-held loud-speakers zc 型兆欧表(检测绝缘电阻用) 、高压试验设备(交流耐压及泄漏试验用)zc-type megger (insulation resistance test), and high-voltage test equipment (ac withstand voltage and leakage test) 4.4 作业环境准备作业环境准备 work environment preparation 厂区电缆沟的

31、开挖及过路管的预埋工作已经完成,电缆沟内无积水,其深度应满足规范要求, 底砂铺好,沟内无杂物。trench excavation and crossing cable tubes embedded have been completed. trench has no water and depth should meet the specifications. spread bottom sand and be debris-free. 场地清理干净、道路畅通。site clean up the roads unimpeded 放电缆用的设备安置完毕,且符合安全要求,电缆沿线照明照度满足施工要

32、求。 cable laying equipment has placed, and meets safety requirements. cable lighting illumination along the route meets the construction requirements. 五五. 敷设施工敷设施工 work of cable pulling 5.1 电缆敷设施工工序电缆敷设施工工序 work procedure 机具布置电缆展放电缆敷设、固定 equipment layout lay off cablelay cable and fix 5.2 机具布置机具布置 la

33、yout of tools 5.2.1 电缆的搬运及支架架设电缆的搬运及支架架设 cable removal and cable tray 1) 电缆搬运须用卡车或吊车运输。滚动时应按电缆轴上箭头指示方向滚动。如无箭头时,可按电 缆缠绕方向滚动,切不可反缠绕方向滚运,以免电缆松弛。use truck or crane to transport cables. roll cable-axis according to direction indicated by arrow sign on it. in long-distance transportation, use truck or cra

34、ne to transport heavy cable trays. if without the arrow sign, roll it according to its wrapping direction. 2) 电缆支架的架设地点应选好,以敷设方便为准,一般应在电缆起止点附近为宜。架设时,应注 意电缆轴的转动方向,电缆引出端应在电缆轴的上方。电缆放线架应放置稳妥,钢轴的强度和 长度应与电缆盘重量和宽度相配合。敷设电缆的机具应检查并调试正常,电缆盘应有可靠的制 动措施。select a proper set-up place as per convenient to pave. gene

35、rally place it near the start or end point of cable. be aware of rolling direction of cable axle, and keep pay-off-rack steady. cable rack should be placed securely, and the steel shaft intensity and length should match the cable tray weight and width. check and debug the cable laying and have relia

36、ble brake devices 5.2.2 卷扬机与滑轮的布置卷扬机与滑轮的布置 winch and pulley arrangement 在线路的另一端布置好卷扬机,并准备好滑轮,约 1.52m 布置一个平面滑轮,每个转角布置一 个转角滑轮,并每隔 2030m 安排一个工人看护。卷扬机用地锚固定,转角滑轮用钢管固定,平 面滑轮无需固定。arrange a winch and pulleys at the end of the line. arrange one planar pulley every 1.52m, a quarter block at each corner and a

37、watch- out worker every20 30m .windlass is fixed with ground anchor corner and pulley with steel pipes; flat pulleys do not need fixing. 电缆架与卷扬机布置见下图: cable rack and winch arrangement see below: 35kv: 10kv: 5.3 电缆展放电缆展放 lay-off cable 1) 电缆展放可用人力拉引或机械牵引。当采用机械牵引时,用机械的最大牵引强度宜满足下表的 规定,其速度不宜超过 15m/min,且应

38、在牵引头或钢丝网套与牵引钢缆之间装设防捻器。 use manual or mechanical traction. when using mechanical traction, the maximum mechanical strength should meet the requirements in table, its speed should not exceed 15m/min, and should install fortified twister between traction head or steel mesh sleeve and pulling steel cabl

39、e. cable maximum traction strength (n/mm2) 电缆最大牵引强度(n/mm2) 牵引方式 traction牵引头 traction head 钢丝网套 steel mesh sleeve 受力部位 force area 铜芯 lead core 铝芯 alumin um core 铅套 lead sheath 铝套 aluminum sheath 塑料护套 plastic sheath 允许牵引强度 allowable traction strength 704010407 本次采用机械牵引,采用钢丝网套直接塑料护套方式,按表计算允许最大牵引强度: the

40、 mechanical traction uses aluminum and plastic sheath. calculate allowable maximum traction strength: 35kv 电缆:300mm2的单芯电缆,其允许最大牵引强度: 35kv cable: 300mm2 single cable, the allowable maximum traction strength: f1=7*300=2100n 10kv 电缆:95mm2的三芯铠装电缆,铅套,其允许最大牵引强度: 10kv cable: 95mm2 three-core armored cable,

41、 lead sheath, the allowable maximum traction strength: f2=10*95*3=2850n 185mm2的三芯铠装电缆,铅套,其允许最大牵引强度: 185mm2 three-core armored cable, lead sheath, the allowable maximum traction strength: f3=10*185*3=5550n 2)牵引力和侧压力计算:traction and lateral pressure calculation: 侧压力计算公式为:the calculating formula lateral

42、 pressure: p=t/r 式中:p 为侧压力(n/m) ;t 为牵引力(n) ;r 为弯曲半径(m) where: p for lateral pressure (n / m); t for traction (n); r for the bend radius (m) 水平直线牵引时:horizontal straight line traction t=9.8wl 式中: 为摩擦系数,在滚轮上牵引时取 0.10.2; where: is friction coefficient, wheel traction is 0.1 0.2 w 为电缆每米重量(kg/m) ;l 为电缆长度(

43、m) w is cable per meter weight (kg / m); l is cable length (m) 实际施工中,考虑实际情况, 取 0.12,r1取 0.5m ,r2取 1.3m, r3取 1.5m the actual construction should consider actual circumstances, takes 0.12, r1 takes 0.5m, r2 takes 1.3m, r3 takes 1.5m 35kv w1=8900kg/m3*300*10-6m2*1m+1.5kg=4.17kg 10kv w2=8900kg/m3*95*3*1

44、0-6m2*1m+1.5kg=4.04kg w3=8900kg/m3*185*3*10-6m2*1m+1.5kg=6.44kg 令 t1=f1=2100n,则 l1=2100/(9.8*0.12*4.17)=428m t2=f2=2850n,则 l2=2850/(9.8*0.12*4.04)=600m t3=f3=5550n,则 l3=5550/(9.8*0.12*6.44)=733m p1=2100/0.5=4200n p2=2850/1.3=2192n p3=5550/1.5=3700n 所以,采用塑料护套直接拉动电缆时,35kv 电缆每次允许拉 428m 电缆,其侧压力为 4200n;1

45、0kv 95mm2的电缆每次允许拉 600m,其侧压力为 2192n;10kv 185mm2的电缆每次允 许拉 733m,其侧压力为 3700n。therefore, pull the cable with plastic sheath. each time the allowable length of 35kv cable is 428m and its lateral pressure is 4200n; 10kv 95mm2 cable is 600m and 2192n and 10kv 185mm2 cable is 733m and 3700n. 3)电缆展放时,电缆应从盘的上端

46、引出,不应使电缆在地面摩擦拖拉。电缆上不得有铠装压扁、电 缆绞拧、护层折裂等未消除的机械损伤。pull cable from the upper plate to avoid friction on the ground. armored cable may not be crushed. do not have cable twisted, retaining layer fracture and other not eliminated mechanical damage. 4)人员合理配备。每隔 2030m 有一个人来注意电缆拉动情况;在每过路管前后应安排人员看护, 同一过路管中第二根电

47、缆开始穿管时,钢丝绳与电缆连接处套上热缩管;电缆转角处有人看护, 跟随电缆头行走人员通过对讲机来指挥操作卷扬机工作人员。reasonably arrange personnel. at intervals of 20 30m have persons to note cable pulling; around each crossing pipe arrange workers to watch and sheathe heat-shrinkable tube at the joint between the steel line and cable when the second cable

48、 threads in the same crossing tube. watch the cable corner, and worker along the head part of cable uses interphone to command the pulley operators. 5) 每根电缆敷设好后,在电缆两端做好临时标示,以分清电缆回路及黄、绿、红三相。make temporary signs at both ends of cables. identify cable loop and yellow, green, red phases. 5.4 电缆敷设、固定电缆敷设

49、、固定 cable laying and fixing 1)电缆弯曲半径应符合规范要求,在沟内敷设应有适当的蛇形弯,电缆的两端、中间接头、穿管 处、垂直位差处均应留有适当的余变。cable bend radius should meet specifications, and pull cable in the trench should have appropriate snake-like bend. leave appropriate laying surplus at ends, middle joints, threading, vertical potentiometer etc.

50、 2)电缆之间,电缆与其它管道、道路、建筑物等之间平行和交叉时的最小净距,应满足规范的要求。 the minimum parallel and cross spacing between cables or between cables and other pipeline ,roads, buildings, etc. should meet the specification requirements. 3)电缆与现有电缆交叉时,满足规范要求,保持足够间距。crossovering the existing cables to meet the regulatory requirement

51、s and maintain adequate spacing. 4)同一回路的三根单芯电缆用尼龙扎带品字型捆扎,捆扎间距不大于 1.5m。同一电缆沟内敷设的 不同回路的电缆中心间距为 20cm。three single-core cables of the same loop should be bundled a triangle type with nylon belts with bundling spacing not more than 1.5m. the center spacing of different circuits in the same cable trench i

52、s 20cm. 5)冬季敷设电缆,温度达不到规范要求时,应将电缆提前加温。in winter, when the temperature can not meet regulatory requirements, the cable should be heated in advance. 6)电缆敷设应设置联络指挥系统,宜以无线电对讲机联络,手持扩音喇叭指挥。the cable laying should set command contact system, contact with radio walkie-talkie and hand-held loud-speakers. 六六.

53、覆砂盖砖覆砂盖砖 spread sand and cover bricks 1) 电缆敷设完毕,应请建设单位、监理及质量监督部门作隐蔽工程验收,作好记录、签字。ask construction unit, supervision and quality supervision departments accept concealed project, make records and do the signature. 2) 电缆上面与电缆下面一样,覆盖 10cm 砂土或软土,然后用砖或电缆盖板将电缆盖好,覆盖宽度 应超过电缆两侧 5cm。spread 10cm sand or soft so

54、il above or below cable and cover with bricks or boards with width more than 5cm of both sides. 七七. 回填土回填土 backfill earth 1) 直埋电缆回填土前,应经隐蔽工程验收合格。prior to buried cable backfill shall be accepted. 2) 回填土应及时并分层夯实。the backfill should be timely layered and compacted. 八八. 埋标桩埋标桩 burying stake 电缆在拐弯、接头、交叉,

55、进出建筑物等地段应设明显的方位标桩。电缆直线段每隔 50-100m 处应加设间距适当的路径标桩。标桩应牢固,标志应清晰,标桩露出地面以 15cm 为宜。set clear direction stake on cable turning, joints, cross, access to buildings and other sites. set appropriate path stake at intervals of 50-100m. stake should be fixed with 15cm above the ground and signs should be clear.

56、九九. 挂标志牌挂标志牌 hanging signs 1) 标志牌规格应一致,并有防腐性能,挂装应牢固。the signs shall be the same size, have antiseptic properties, and mounted hanging shall be firmly. 2) 标志牌上应注明电缆编号、规格、型号及电压等级。the signs should indicate cable numbers, specifications, models and voltage level. 3) 直埋电缆进出建筑物及电缆终端头应挂标志牌。buried cable acc

57、ess to buildings and cable termination heads should hang signs. 4)电缆标志牌同时应遵循业主标准。cable signs follow owner standard. 十十. 质量控制质量控制 quality control 10.1 主控项目主控项目 master items 1) 电缆的耐压试验结果,泄漏电流和绝缘电阻必须符合施工规范规定。the cable voltage test results, leakage current and insulation resistance must comply with the

58、provisions of the construction specifications. 检验方法:检查试验记录。test method: check test records. 2)电缆敷设必须符合以下规定:电缆严禁有绞拧、铠装压扁、护层断裂和表面严重划伤等缺损, 直埋敷设时,严禁在管道上面或下面平行敷设。the cable laying must meet the following requirements: strictly prohibit twist, armored squash, sheath fracture and severe lacerations and othe

59、r surface defects. forbid parallel pipeline laying. 检验方法:观察检查和检查隐蔽工程记录。testing method: observe examination and check concealed work records 10.2 一般项目一般项目 general items 1) 坐标和标高正确,排列整齐,标志桩和标志牌设置准确;防燃、隔热和防腐要求的电缆保护措 施完整。coordinate and elevation should be correct and arrange neatly. set up sign stake an

60、d signboard accurately; take protection flame proof, heat insulation and corrosion matures. 2) 电缆的埋置深度应符合下列要求:电缆表面距地面的距离不应小于 0.8m,且电缆应埋在冻土 层以下。在电缆引入建筑物、与地下建筑物交叉及绕过地下建筑物处等受条件限制时,可浅 埋,但应采取保护措施。the depth of buried cables should meet the following requirements: the distance from cable surface to ground

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论