版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、PM 005 Project Execution PlanTemplate & GuideThis Guide is intended to be read in conjunction with the following template for the development of a Project Execution Plan. As such the Guide should be removed from the front of your final document.Version 1.0 (14 December 2000)What is a Project Executi
2、on Plan?The Project Execution Plan is the road map used by the Project Team to deliver the agreed project outputs. It outlines the responsibilities of the Project Team and key stakeholders.Why would you develop a Project Execution Plan?A Project Execution Plan is developed to expand on the Project B
3、usiness Plan by specifying the day-to-day (operational) management procedures and control plans including: detailed project plans; resource schedules; quality procedures; reporting procedures; product purchasing and development plans; risk management planning; and project budgets.The document enable
4、s those completing the tasks/activities in the project to deliver the expected results, as per the agreed Project Business Plan.When would you develop a Project Execution Plan?Approval to proceed to develop a Project Execution Plan is usually obtained from the acceptance or approval of a preceding s
5、tage such as a Project Proposal/Brief For a definition of these underlined terms, refer to the Project Management Glossary. or Project Business Plan. The Project Execution Plan expands the proposals developed in these documents in order to: document the day-to-day (operational) management and contro
6、l activities to be undertaken by the Project Team; and gain acceptance by the Project Sponsor or Proposer to the suitability of these activities.What you need before you start: Agreement to proceed with the development of the Project Execution Plan from the Project Sponsor or Proposer. Knowledge and
7、 understanding of developing detailed project plans, quality plans, implementation and delivery plans, resource scheduling, risk management planning and financial planning. Knowledge and understanding of the Key Elements, as outlined in the Tasmanian Government Project Management Guidelines.Optional
8、: Any of the following documents - Strategic Information Systems Plan, Project Proposal/Brief, Process Review Report or Feasibility Study. Departmental Project Management Guidelines.What you will have when you are finished:A completed Project Execution Plan that is ready for acceptance by the Projec
9、t Sponsor or Proposer.How to use this template?The template contains sections which are either optional or can be developed at a number of levels of detail depending upon individual need. Sections that are not completed can be indicated in a number of alternative methods depending on the reason for
10、non-completion, for example by referring to another document, by deleting the heading, or by indicating that the section is not applicable.All documents developed based on this template should include an appropriate acknowledgement.A number of different text styles have been used within the template
11、, as follows: Text in italics is intended to provide a guide as to the kind of information that can be included in a section and to what types of projects it might be applicable. Text in normal font is intended as examples. Text enclosed in is intended to be replaced by whatever it is describing.23
12、/ 34文档可自由编辑打印Project Execution PlanOrganisational UnitDEPARTMENT OF Version 0.A (dd mmm yyyy)DOCUMENT ACCEPTANCE and RELEASE NOTICEThis is of the Project Execution Plan.The Project Execution Plan is a managed document. For identification of amendments each page contains a release number and a page n
13、umber. Changes will only be issued as complete replacement. Recipients should remove superseded versions from circulation. This document is authorised for release once all signatures have been obtained.PREPARED:DATE:_/_/_(for acceptance) (, Project Manager)ACCEPTED:DATE:_/_/_(for release) (Project S
14、ponsor, )1.BUILD STATUS:The most recent amendment first.VersionDateAuthorReasonSections2.AMENDMENTS IN THIS RELEASE:Section TitleSection NumberAmendment Summary3.DISTRIBUTION:Copy NoVersionIssue DateIssued To12ElectronicTable of Contents1Introduction11.1Document Purpose11.2Intended Audience11.3Proje
15、ct Outputs11.4Scope of Work22Management Plan22.1Management22.2Status Reporting32.3Risk Management42.4Provision of Facilities and Equipment52.5Skills and Resource Requirements52.6Configuration Management62.7Confidentiality72.8Output Review and Acceptance72.9Updating this Plan73Quality Plan93.1Introdu
16、ction93.2Methodologies and Standards93.3Development Environment103.4Inspection, Measuring and Test Equipment103.5Development Cycle103.6Outputs to be Developed103.7Project Evaluation113.8Records114Purchasing Plan124.1Purchasing Specification124.2Selection of Suppliers134.3Subcontractor Management134.
17、4Inspection and Testing of Purchased Goods & Services134.5Records Required145Development Plan145.1Design and Development Activities145.2Organisation and Staffing155.3Design Methodology155.4Design Input155.5Design Output155.6Inspection and Review155.7Approval and Acceptance165.8Authorisation and Dist
18、ribution165.9Updating and Changing166Test Plan176.1Introduction176.2Unit Testing176.3System and Integration Testing176.4Acceptance Testing186.5Certification of Test Results187Implementation and Delivery Plan197.1Implementation197.2Handling, Packing, Marking and Delivery198Output Management Plan208.1
19、Output Register208.2Output Identification and Traceability218.3Version Control218.4Maintenance of Libraries218.5Non-conforming Output229Maintenance Plan2210Project Evaluation Review(s)2211Project Plan2311.1Overall Project Plan2312Appendices241 Introduction1.1 Document PurposeDepending on the size an
20、d complexity of the project, the need for multiple Project Execution Plans (PEPs) for the Project may arise. Examples include where separate Project Teams are developing specific outputs for different business areas (i.e. as sub-projects).The Project Execution Plan (PEP) is the operational document
21、for the project. It is owned, maintained and utilised by the Project Manager and Project Team to support the delivery of the agreed project outputs.The PEP is the responsibility of the Project Manager and is the road map enabling the effective day-to-day (operational) management and control of the p
22、roject.The PEP expands on the Project Business Plan which is the approved plan describing what will happen in the project. The PEP details how the Project Team will carry out their tasks/activities to ensure that the what will occur. The document provides new Project Team members, or a new Project M
23、anager with the ability to start during a project, and continue to perform the projects activities in a consistent manner.The document should be reviewed and amended to meet changed conditions during the projects life span.1.2 Intended AudienceClearly identify the intended audience of this document,
24、 as it may include key representatives from the business area(s), and other stakeholders who will be impacted by the planned outputs.State any assumptions regarding the document up front that may assist the reader, for example: Knowledge of the project and a basic understanding of project management
25、 principles and practices is assumed; As the document proceeds through a series of iterations during the life of the project (e.g. after each phase), its structure, emphasis and intended audience may change.1.3 Project OutputsDescribe specifically the projects outputs.Table : OutputsOutputDescriptio
26、nA.B.1.4 Scope of WorkBriefly summarise the scope of the work involved in the project as defined in the Project Business Plan.Table : Scope of WorkWithin ScopeOutside ScopeA.B.2 Management Plan2.1 ManagementThis section may be covered by a reference to the Projects governance structure, i.e. managem
27、ent roles, functions and responsibilities that are defined within Section and Appendix of the Project Business Plan.The project will be managed by who is the Project Manager. The Project Manager is responsible to the for the delivery of the agreed project outputs.The sub-headings under section 2.1 (
28、2.1.1 2.1.5) may not be required if the above content is adequately covered in the Project Business Plan.2.1.1 IntroductionThis section expands the operational management of the Project, as defined within the Project Business Plan.2.1.2 Sub-Project ManagementDefine the operational management of the
29、sub- projects if this has not already been defined within the Project Business Plan.2.1.3 Reference GroupsDetail any specific reference groups (i.e. function, objectives, membership etc) that are required and have not been defined in the Project Business Plan.2.1.4 ConsultantsDetail any consultancie
30、s (i.e. function, time frame, objectives, management, reporting etc) that are required and have not been defined in the Project Business Plan.2.1.5 Working PartiesDetail any specific working parties (i.e. function, responsibilities, time frame, objectives, membership etc) that are required and have
31、not been defined in the Project Business Plan.2.2 Status ReportingDescribe the provision of project reporting requirements (e.g. content, frequency, audience etc) for the following: Project Manager Reference Groups Consultants Working Parties Quality ConsultantsCross reference the above reporting re
32、quirements with status reporting in the Project Business Plan so as not to duplicate.Clearly define the purpose, content and frequency of project status reports. The following is a generic guide to minimum requirements: the status of the project, which includes monitoring of milestones and budget:o
33、for the last reporting period;o for the next reporting period;o for the remaining period of the project. an issues report (including areas of concern, specific problems, and any action that needs to be taken); and a risk management report (which will specify any changes to the risks identified and t
34、he strategies put in place to manage them).2.3 Risk ManagementAll projects require on-going risk analysis to be undertaken regularly throughout the life of the project. Analysis should be undertaken with the critical stakeholders.If appropriate, describe how risk management will be conducted. Refer
35、to the Tasmanian Government Project Management Guidelines that contain a section on risk management.Risk assessment and management strategy working documents may be attached as an appendix.2.3.1 Risk AssessmentThe Project Manager is responsible for: Scheduling and performing risk assessment and deve
36、loping strategies to manage those risks for each phase of the project as identified within the Project Plan. Providing a risk review within status reports to the Steering Committee, which will specify any changes to the risks identified during each phase of the project and the strategies adopted to
37、manage them.Provide details of the following: where the results of each risk assessment will be retained; the frequency of risk assessment; who will be involved in the risk assessment; how the risk assessments will be conducted; what will trigger the implementation of the risk mitigation strategies;
38、 how the effectiveness of risk mitigations strategies will be monitored; and the approval mechanism for risk mitigation strategies e.g. Steering Committee approval.2.3.2 Failure to DeliverIn the event of the project suffering slippage of greater that then the project schedule and outputs to be deliv
39、ered shall be reviewed by the Business Owner/Project Sponsor and the Project Manager. The Project Manager shall inform the Steering Committee of the situation and recommend the course of action to be followed. Agreement on how to proceed shall be negotiated by the Project Manager and Steering Commit
40、tee.2.3.3 Acceptance and Review PeriodsAll review and acceptances shall be completed within of the output being handed to .Should any agreed review period not be met and, in the opinion of the Project Manager, the project is unable to proceed the schedule shall be revisited. Any adjustments for the
41、time lost should be negotiated by the Project Manager with all affected parties.2.3.4 IssuesWhen issues arise which must be resolved between the Business Owner and the Project Manager then the issue shall be advised in writing between the Project Manager and the Business Owner. The recipient of the
42、issue shall be responsible for ensuring it is resolved and the resolution communicated in writing to the initiator.2.3.5 Non-availability of ResourcesShould any agreed resource not be made available as scheduled in the Project Plan (Refer Section X) and, in the opinion of the Project Manager, the Pr
43、oject cannot proceed the schedule shall be revisited. Any adjustments for the time lost should be negotiated by the Project Manager with all affected parties.2.4 Provision of Facilities and EquipmentDescribe what facilities are required by the Project Team (e.g. accommodation, office support, equipm
44、ent etc) and any specific maintenance requirements.Document the projects environment baseline.2.5 Skills and Resource Requirements2.5.1 Skills and ResourcesThe project resource requirements (for entire period or specific phases): Project Manager; Independent Quality Officer and/or Quality Review Con
45、sultant; Representatives of the Business Owners; and An external project auditor.Address whether resources are full or part time, as required etc.Describe any specific knowledge and skills required to undertake processes designed to achieve the project outputs (examples): managerial skills and knowl
46、edge; strategic and conceptual skills; sound communication, negotiation and consulting skills; capacity to develop innovative solutions; understanding of project and quality management principles and practices; etcThe following things need to be addressed: the impact of resources being off-line on p
47、rojects; how these resources will be released to the project; and from the project when no longer required.Formal agreements may be required to confirm the availability and timeliness of resources.2.5.2 TrainingWhat training requirements are there based upon the required skills and resources listed
48、in 2.5.1? How is the training to be provided and conducted?2.6 Configuration ManagementThis section may be expanded or condensed depending on the appropriateness to the project.Configuration management is a term often applied to change control procedures (e.g. change requests, problem reporting, iss
49、ues management etc) undertaken at the project/implementation team level to control change and reduce its impact on the overall project.2.6.1 Change ControlChange control shall be used by the Project Manager in accordance with . This process provides the means for: facilitating the introduction of sp
50、ecific project change; allowing the impact of the change to be assessed; providing a method of authorising change; and providing an audit trail of change.Approval of changes is by .Describe the process that will be used to raise, record, review and resolve change requests.2.6.2 Problem Reporting and
51、 ResolutionProblem reporting is used to record a problem that has been identified in a project.Describe the process that will be used to raise, record, review and resolve problem reports.2.6.3 Incident Reporting2.6.4 Issues ManagementAn issue is a point that requires noting, but is not considered a
52、problem or change.It is anticipated that most of the issues raised within the development phase will be solved by the . However, issues arising which must be resolved between the Business Owner and the Project Manager are referred to the Project Sponsor for resolution (refer to 2.3.4).Describe the p
53、rocess that will be used to raise, record, review and resolve issues.2.7 ConfidentialityAll project members, agents, contractors and subcontractors shall respect the confidentiality of each others business and technology and shall not reveal any information concerning the other party without the wri
54、tten permission of the other party.All agreements and contracts entered into require inclusion of a confidentiality clause.2.8 Output Review and AcceptanceDescribe the process that will be used for the review and acceptance of each output and documentation product, including who is responsible for scheduling the reviews, who will be involved, what will be generated for each accepted output or documentation product.2.9 Updating this PlanThis plan shall be updated at least at the end of each phase or phase
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2025青城鉴山售楼部合同
- 二零二五年度企业食堂承包管理服务合同3篇
- 二零二五年度公益项目合同资金使用与效益评估协议3篇
- 清廉金融视频拍摄方案
- 2024版多人借款合同书
- 2025版教育机构兼职教师工作责任与义务协议3篇
- 2024年特征鲜明离婚合同书参考文本版B版
- 二零二五年个人智能家居设备贷款担保三方合同3篇
- 2024年度环保项目施工人员用工合同范本3篇
- 二零二五年度劳动合同安全检查与整改执行合同3篇
- 2022年10月自考00850广告设计基础试题及答案含解析
- 工会委员会会议纪要
- 《水电工程水文设计规范》(NB-T 10233-2019)
- 2024年1月电大国家开放大学期末考试试题及答案:法理学
- (高清版)DZT 0284-2015 地质灾害排查规范
- 驾驶员劳务派遣车辆管理方案
- 电缆大和小修危险源辨识和控制措施
- CSCO胃癌诊疗指南转移性胃癌更新解读
- 微电子器件课后答案(第三版)
- 机关餐饮项目服务方案(完整版)
- 《网络安全等级保护条例》
评论
0/150
提交评论