ProjectManagementwithSAPR/3
TeachingMaterialfortheDepartmentof
ProductionManagement
WIRTSCHAFTS
UNIVERSITAT
ViennaUniversityofEconomicsand
BusinessAdministration
AndreasMild
AlfredTaudes
v.1.0
1Introduction..............................................................4
2Basics&Keywords........................................................5
3Gettingreadyfortheworkshop...........................................8
4CaseStudy...............................................................15
4.1Casedescription........................................................15
4.2DataforProjectRealization.............................................16
5Planningtheprojectstructure..........................................18
5.1General..................................................................18
5.2ImplementationinSAP..................................................20
6Scheduling...............................................................31
6.1General.................................................................31
6.2Basiccalculations......................................................35
6.3Implementation..........................................................37
6.4Theprojectplanningboard..............................................47
7Costplanning&Controlling............................................53
7.1General.................................................................53
7.2Implementation..........................................................54
8Lookingupthecosts.....................................................67
9CapacityPlanning........................................................71
9.1General.................................................................71
9.2ImplementationinSAP..................................................72
10EarnedValueAnalysis...................................................76
10.1General................................................................76
10.1.1Measurementtechniques....................................................76
10.1.2CalculationofEarned-ValueandDeviationAnalysis..........................81
10.1.3Aggregation...............................................................82
10.2Implementation.......................................................83
11Execution................................................................85
11.1Implementation........................................................85
11.1.1Confirmingnetworkactivities..............................................85
11.1.2Invoices..................................................................87
11.1.3Material..................................................................90
12InformationSystem......................................................94
12.1Implementation.........................................................94
12.1.1Costreports..................................................................95
12.1.2Earned-ValueAnalysis.......................................................100
13Literature.................................................................................................................107
1INTRODUCTION
Thisscriptservesasabasisfortheworkshop"ProjectManagementwithSAPR/3〃.
ThisworkshopispartofaseriesofSAP-relatedworkshopswhichareheldbythe
DepartmentofProductionManagementoftheViennaUniversityofEconomicsand
BusinessAdministration,headedbyProf.Dr.AlfredTaudes.Theworkshopwas
developedbyAndreasMild.
ThegoalofthisProjectManagementWorkshopisthat,afterhavingattendedit,each
studentshouldbefamiliarwiththetheoreticalbackgroundsandbeabletoplanand
controlaproject.Theprojectmanagerhasthetaskofensuringthattheproject
isexecutedefficiently,ontime,andwithinthebudget-whichhe/sheachievesby
makingcertainthattherequiredresourcesandfundsareavailablewhenneeded.Every
studentshouldthenbeabletoputhis/herSAPknowledgeintoaction.
Tomakethecontinuousimprovementofthisscriptpossible,pleasereportmistakes
foundorideasforfurtherdevelopmenttoandreas.mild@wu-wien.ac.at.
2BASICS&KEYWORDS
SAPR/3isanintegratedandindustry-independentstandardsoftwarewhichcovers,
integratesandconnectsallfunctionalareasinabusiness.SAPAGdefines
integrationas“definedcommunication",.1AlthoughR/3isdesignedforcomplete
integration,itcanalsobeusedforacoupleofbusinessareas.2
SAPistheabbreviationforaSysterne,Anwendungen,Produkte,theGermanwords
foruSystems,Applications,Products”.’
Informationaboutthecompanycanbefoundat:http:〃www.sap,com.
Projectsaretaskswithspecialcharacteristics.Attributesofaprojectarethe
followingissues:
•complexity,non-repetitivity,highrisk
•detailedgoalstobeachieved
•timerestrictions
•highcostandcapitalexpenditure
•qualityrequirements
•oftenstrategicsignificance
Tobeabletoplan,monitor,control,andcarryoutaprojectasawhole,theproject
goalsmustbepreciselydescribedandtheactivitiestobeperformedhavetobe
structured.
Aprojectcanbedescribedasfollows:
•accordingtohowitisorganized,i.e.byexplainingtheprojectstructure,
•accordingtotheprocessesinvolved.
Aprojectstartsoutasastatementofworkwhichiseitherawrittendescription
oftheobjectivestobeachievedandthedesiredroughschedulelikestartandend
dates.Inthedescriptiononecouldincludealsoperformancemetricsandbudget
constraints.
Aprojectisfurthersubdividedintomeaningfulpieces,referredtoastasks.Tasks
takeusuallylessthanafewmonths.Thetaskcanbefurthersubdividedintosubtasks.
Aworkpackagecanbedefinedas“agroupofactivitiescombinedtobeassignable
1AFOS(Hrsg.)SAPArbeit,Management.Braunschweig/Wiesbaden1996p.59
2ComputerweltNo.13of13.3.1998,p.20
3AFOS(Hrsg.)SAPArbeit,Management.Braunschweig/Wiesbaden1996p.59
toasingleorganizationalunit.”
Theprojecttasks,subtasks,andworkpackagesarebroughtintoa
hierarchybydefiningaworkbreakdownstructure.
Theindividualelementsrepresentactivitieswithintheworkbreakdown
structureandarecalledworkbreakdownstructureelements(WBS
elements).
WBSelementscanbe:
•tasks
•partialtaskswhicharesubdividedfurther
•workpackages
WBScanbestructuredaccordingto
•object
•function
•phase
Whichkindofstructuringisuseddependsonthefocusoftheproject.
Objectsorientationisoftenused,ifthemainpartoftheprojectisa
physicalobjectlikeapowerplant.Functionalorganisationispreferred,
ifmanydifferentpartsofanorganisationormanyorganisationsare
involved.
Inpractice,allthreekindsofstructuringareusedwithinoneWBS.
“ProjectManagementcanbedefinedasplanning,directing,andcontrolling
resources(people,equipment,material)tomeetthetechnical,costandtime
constraintsoftheproject.wTheprimaryreasonwhyprojectsfailisinsufficient
effortintheplanningphase.ProjectManagementthusisconsideredasvery
important.
TheSAPProjectSystemenablescloseandconstantmonitoringofallaspectsofa
projectbyhavingconstantaccesstodatainallthedepartmentsinvolved.
Projectmanagementcanbesubdividedintoprojectplanning,i.e.thetask
whichwillbeundertakenbeforetheprojectstarts,andproject
4ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:
ManufacturingandServices,p.48
5ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:
ManufacturingandServices,p.48
6ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:
ManufacturingandServicesp.69
controllingduringtheimplementationoftheproject.Planningmust
include:
•organization-service
•process-dates
•costs
•capacity
Therearemanypossibleprojectgoalssuchas,forexample,torealizeapositive
netpresentvalue,toachieveahighimputedinterest,tominimizecosts,tocover
costs,tomaximizegrossprofit,orsimplytofinishasearlyaspossible.However,
itisimportant,thatgoalsaredefinedoperationally,thaitiswhenitispossible
tomeasuretowhichextentthegoalhasbeenachieved.
Theprojectmanagerbreakstheprojectdownintoasetofactivities.Thenhealso
definestherelationshipsamongtheseactivities.Theoutcomeisaguideline
regardingtheactivitiesthatcanbeperformedinparallelandthosethathaveto
bedoneinasequentialorder.Thistaskisdoneviaplanningbynetwork.
Now,thereareactivitiesthatrequirecapacitiesandresourceslikepersonneland
material.Suchresourcesarelimitedandtheserequirementshavetobeconsidered
inordertobeabletodevelopafeasible,soundplan.Informationfromothermodules
ase.g.thematerialplanningmoduleisrequired.
Thesystemcalculatesthematerialrequirementsforeachstepoftheprojectand
organizesthatmaterialsareboughtintimetoavoiddelays.Whenpurchasingmaterial,
thesystemtakesintoaccountordersizes,inventorypoliciesaswellasother
information.
Topreparethefinancialstatements,thevalueofworkinprogress(including
projectwork)hastobecalculated.ThisalsorequiresinteractionofsomeR/3
modules.
Thus,thesystemneedsinformationfromallbusinessareassimultaneously.Andthis
isexactlywhatintegrationdoes.
TheprojectmoduleispartoftheintegratedconceptofSAPR/3providinginterfaces
toothermoduleslikeAccounting,Distribution,MaterialManagementandProduction
PlanningandControl.Eachareawithintheorganizationhasitsownstructureand
itsownviewoftheproject,butdatahastobeenteredonlyonce.
3GETTINGREADYFORTHEWORKSHOP
Thischapterprovidesinformationonthefirstuseofthesystem.
LoggingonR/3
Loggingoff
SAPR/3isaclient/serverapplication.Therefore,youhavetocancelthe
connectionwiththeserverbytellingitthatyouwanttologoff.
CreateSession
Oftenitisusefultoopenmorescreens.Youcandothisbycreatinga
newsession,likeanewdocumentinawordprocessor.
SAPHelp
Ifyouwanttogetsomebasicinformationaboutaspecificfield,focusthisfield
withyourmouseandpress<F1>.Thedialogboxindicateswhatthefieldisfor.
Sometimesevendependenciesareexplained.
Matchcodes
Matchcodesareusefulforfindingdata,becauseitisdifficulttoknow/remember
theidentificationnumberofalinepositionsuchasamaterial.
Example:
Youwanttoeditthematerialmasterofamaterial.Youdon'tknowthenumber,but
youknowthatthematerialdescriptionstartswithsomethinglike"PM_"
IfyoupressF4yougetasearch-maskwhereyouareabletosearchwithwildcards
AfterhavingpressedEnteryougetalistwiththesearchresults.
Thenyoucanselectonematerial,youcansortorcancel.
TransactionCodes
Thefollowingscreenwillbeoftenusedduringtheworkshop.Thus,wecanuse
TransactionCodesforfasteraccess.
ThenselectStructureplanning-ChangeProject,
Now,wewantto“bookmark”thisscreen.
So,welookupthetransactioncode.
Thestatusdialogboxopens:
Hereweseealotofinformationconcerningimportantrelevanttechnicaldetails.
Whereveryoufindyourselfinthesystem,youcangettothisscreenbyentering
CJ20intheTransactionscreen.
Letusrefinethisalittlebit.Ifyouhaveseveraltransactioncodes,youmayget
confused.Keyintheappropriatetransactioncodeandthecommenteditproject
structure.
Then,ifyouopenthecomboboxofthetransactioncodesafterhaving
enteredmorecodes,youwillfindtheappropriateone.
TheStandardToolbar
Inmanyscreensyouwillfindthestandardtoolbar.
Savebutton
Whenyoupressthesavebutton,thesystemalsovalidatesyourinput.Iftherewas
anerror,youhavetocorrecttheerrorfirst,beforeyoucanproceed.
Backbutton
Ifyouclickthebackbuttonyoureturntothepreviousscreenwithoutsavingyour
data.
Help
3
Enterbutton
Whenyouhavefinishedenteringinformationonascreen,youpresstheEnterbutton
whichperformsthesamefunctionaspressingtheEnterkey.
Exitbutton
Pressit,ifyouwanttoleavethecurrentapplicationtogobacktothe
previousmenue.
Cancelbutton
X
Clickonthisbuttontoexitthecurrenttaskwithoutsaving.TheCancelbutton
performsthesamefunctionasCancelintheEditmenu.
Printbutton
Pagingkeys
Find/Findnextbutton
用倒
Clickonthisbutton,ifyouwanttoperformasearchfordatarequiredinthescreen
youarecurrentlyworkingin.
4CASESTUDY
4.1Casedescription
ThiscasewasdevelopedinordertodemonstratetheprojectsystemofSAPR/3.All
pricesanddataarepurefictionandheldverysimple.
Theobjectoftheprojectisthespecificationandinstallationofanelevator.
Physically,theElevatorconsistsof
•acabine
•anengine
•mechanicalparts
•acontrolunit
Inthecourseoftheproject,thesepartsmustbeconstructed,procuredand
assembled.
Attheend,anexternalinspectionoftheentiresystemisprescribed.
Theprojectmustbefinishedby30.6.2000.
Thecompanyconsistsoftwoworkcenters:
•Development(PROJ-RD)
•Installation(PROJ-INS)
SpecificationactivitiesareperformedbytheDevelopmentdepartment.Procurement
activitieswillbedoneoutsidetheprojectorganisation,andneithercostnor
capacityconsiderationsareplannedwithinaprojectforprocurement.Installation
isdonebytheInstallationdepartment.
Inparticular,theactivitiesareasfollows:
ActivityDurationWorkWork-center
Specificationofthecabine1020Development
Specificationoftheengine1010Development
Specificationofmechanical2010Development
parts
Specificationofthecontrolunit210Development
Procurementofthecabine20
Procurementoftheengine50
Procurementofmechanicalparts10
Procurementofthecontrolunit10
InstallationI15100Installation
InstallationII20100Installation
ExternalInspection1external,80.000
Specificationactivitiescanbeperformedinaconsecutiveorderonly.Specification
startswiththecabine.Aftercompletion,thespecificationoftheenginecanbe
done.Then,themechanicalpartscanbedesigned.Thelastactivityisthedesign
ofthecontrolunit.
Afterthecompletionofeachspecificationactivity,theprocurementofthespecific
itemcanbeeffected.
AftertheprocurementofallpartstheInstallationcanstartandmustbedonein
twoconsecutivesteps(1+II).
Thefinalactivityoftheprojectisexternalinspection.
A10%planningreserveonthebaisisofplannedcostisrequired.Noactualcost
shouldbepostedtothisWBSelement.
Correspondingmaterialsassignedtothepurchasingactivities
Structure
ParametersfurEarned-ValueAnalysis
AllspecificationactivitiesandInstallationIIusethe20-80Methodfor
performancemeasurement.Procurementactivitiesuse0-100method.
InstallationIhas3milestones,viz.Preparationfinished(20%),Installation
finished(80%),Qualitychecked(100%).
4.2DataforProjectRealization
ActivityStartEndWork
Specificationofthecabine24.1.200004.2.200020
Specificationoftheengine07.2.200005.3.200030
Specificationofmechanical06.3.200022.3.200020
parts
Specificationofthecontrolunit
Procurementofthecabine06.3.200006.3.2000
Procurementoftheengine07.3.200007.3.2000
Procurementofmechanicalparts08.3.200008.3.2000
Procurementofthecontrolunit09.3.200009.3.2000
InstallationI
InstallationII
ExternalInspection
Externalinspectionhadtobepaidinadvanceat3.2.2000(100000ATS).
Allmaterialwastakenfromstockatgiventime.
5PLANNINGTHEPROJECTSTRUCTURE
5.1General
Eachprojectstartswiththedefinitionandclassificationofthestructures
requiredforprocessingandtheincorporationoftheseintotheexistingenterprise
structure.
TheProjectSystemhasnoorganizationalstructuresofitsown;ithastobe
incorporatedintotheexistingstructurebymakingassignmentstothe
organizationalunitsinAccountingandLogistics.
Afterthat,theprojectisbrokendownintomeaningfulpiecesinahierarchyreaching
fromtaskstothelowestlevel,theworkpackages.
DatastructureinSAP
Asmentionedabove,theprojectmustbeincorporatedintotheexistingstructure
byassigningorganizationalunitsinAccountingandLogistics.
7SAPOnlineDocumentationIDESRelease4.0B
Source:SAPOnlineDocumentationIDESRelease4.OB
Thischartprovidesanoverviewofwhatcanbeassignedtoaprojectandits
components.WewilldefinetheSAPvocabularylateron.
Thework-breakdown-structure(WBS)definesthehierarchyofthetaskswithina
projectanddividestheprojectintousefulsteps.
TocontrolcostsassignedtoWBSelements,operativeindicatorsareused.
ThefollowingoperativeindicatorscanbeassignedtoaWBSelement:
PlanningWBSelementsforwhichcostscanbeplanned
AccountWBSelementstowhichcostscanbeassigned
assignment
BillingWBSelementstowhichrevenuescanbeposted
5.2ImplementationinSAP
Inthissectionwecreateanewproject.Wethenwillhavealookatthe
controlparameters.Afterthatweentertheworkbreakdownstructure.
Finally,thestatusconceptofSAPR/3willbeexplained.
Createnewproject
Thus,wegettotheinitialscreen:
Weenterourprojectdefinition,adescriptionofourprojectandselectthestandard
profileforprojects.
Inourcase,weonlysetafinishdate.WhenpressingEnter,awarningmessagethat
thisdateisnotaworkingdaymightoccur.Onecanpassthewarningbypressing
Enter
Wethensaveourworkandgettheconfirmationthattheprojecthasbeencreated.
Note:Itiswisetosaveyourworkfromtimetotime.Wewillnotmentionthesave
procedureintherestofthemanuscript!
Tocontinue,wehavetochoosetochangeourproject.
SUucturePlanning:Change
ProjectEditfiotoDetailsSettingsEybasSystemHglp
yI3Wg&X[「M疏社''r句犀111
Projeddef.|MILDELEV10
WBSelement
Selection
Makesurethatthecheckboxwithactivitiesisalwayschecked.Clickexecuteto
proceed.
Nowhehavecreatedanewproject.Althoughwehavenotkeyedinanydataexcept
theProjectProfileNumber,manyparametershavealreadybeenassignedtoournew
project.
Generalcontrolparameters
Clickheretoviewtheglobalparameters.Thissectionshouldprovideyou
withabasicinsightintowhichparametersareset.Ifyoufeelthatthe
resultscalculatedbyR/3arenotlogical,youshouldhaveanideawhere
tostartsearchingtherelevantcustomizingdetails.
TheprojectprofilespecifiesThenetworkprofilespecifiesIntheWBSschedulingprofile
generaldatalikeControllinggeneraldatalikesettingsitemslikethescheduling
area,Plant,Factoryforthegraphicaltype(forward,backward)are
calendar,Planningmethodrepresentation,activityspecifieti.
etc.Whencreatingtheparameteri,likethecurrency
project,theprofileisdefault\ofexternally
choosen.processedActivities.
ChangeProject:Projectdefinition_______________________________■国画
ProjectEditfioto^BSelementRetailsEjjlrasSystemHglpV7
I,II二馆加后妇到电上窗:
津居品ASbuctueSettlementiule\
Projectdef.|jlILD_ELEV_1O国|El”atorProject
■
BasicdataControldata|Admtmstfation
Projectprofiler,Transfertomoi.def
AccountingTimescheduling
BudgetprofileNetwcxkprofile|。0。00。2
PlanningprofileWBSschedulingpd]O(3BOOeOOGCIB1
Paymentplanprofile
lnl.c*.p(dile■C^lc.withact.
InvestmentprofilePlanrT>U^ba$icOpenpiarwiing
1
ResultsanalysiskeyPfenmeth/fAOpenplanning
SimulationptoiileNetwakasstFaptojeddefinition
Thebudgetprofilespecifiesitemslikebudgeting',Theplanningprofilespecifies,
currency,thevalidtimehorizonforbudgetingbacke.g.,costingvariantandtime
in-tothepastorintothefuturehorizon.
Planningparameters
Inthegeneralparametersection,manyparametersaresetasdiscussed
above.Naturally,onecanoverrideapartoftheminthecurrentproject.
However,wearenotchanginganyparameters.
Hereyoucanspecifyifyouwanttousetop-Down,bottomup,oropenplanning.
HerewespecifywhatthesystemshoulddoAnimportantparameteristhescheduling
ifschedulingdeterminesdateswhicharetype.Hereyouspecify,ifyouwanttouse
notwithinthebasicdates.Incase,theforward,backwardorotherscheduling
scheduleddatesshouldbetakenoverasnewtypes.
dates.
Startenteringthedatagiveninthescreenshotbelow.Ifyouarefinished,press
Enter.
Then,yourscreenshouldlooklikethis:
ChangeSUuctuiePlanning:BasicdatesHQBl
ErojectEditGotoRetailsSettingsEjjbasSystemHfilpK
旷I;30中畲xaa画翁t3心灯百团曾
局13回身DQ"包母国置盹三品必困咚由AComponentoverview图Displayassignment人PStexts
Rrc^eddef.DesoiplionStartFinishDotationTimCal
|MILD_ELEV_1Q|ElevatorProject||3006.001O[DAY|AU
WBSbasicdataBasicdates|Forecastdates|Activitydata|
SAcLevWBSelementActIEtemDesaiptionStrtdatFin.datInE>Se:G(AZD
■f1MILD_ELEV_1OElevatorProject
听2MILD_ELEV_10-10QConstruction
0101Constructionofthecabinerrc
0102Constructionoftheengine(SCcc
0163Constructionofthemechanicalparts(Sc「r
0104Constructionofthecontrolunit9rcc
听2MILD_ELEV_10-200Procurement
0201Procurementoftheengine(9rrr
0202Procurementcabineccc
■1MILD_ELEV_1G-300Installation
0301InstallationI④crjr
0302InstallationIIrC£
1arrr
acc-c
Levelingup/downWBSElements
Thereisamistake.WBSElementELV_000-300shouldhavelevel2.
SelecttheWBSElementtoleveling
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 小升初数学压轴题天天练-判断题100道附参考答案【完整版】
- 部编版六年级下册道德与法治-选择题50道及答案(网校专用)
- 2022年五年级上册数学期末测试卷及完整答案1套
- 部编版六年级下册道德与法治-填空题50道及完整答案(必刷)
- 冀教版小学六年级下册数学期末测试卷附参考答案【基础题】
- 小学数学六年级上册期末测试卷附参考答案(完整版)
- 人教版八年级音乐上册(五线谱)第2单元《西班牙斗牛舞曲》教学设计
- 人教版八年级下册音乐 5.3.2《长恨歌》选段 教案
- 教科版科学一年级上册第二单元《比较与测量》测试卷带答案【典型题】
- 平行四边形面积(教案)-2023-2024学年五年级上册数学人教版
- 新12123交管学法减分考试题库及答案
- 恋爱心理与幸福人生智慧树知到期末考试答案章节答案2024年青岛职业技术学院
- 2024年湖北省武汉市江岸区九年级下学期五月调研考试英语试卷
- 2022-2023学年山东省济南市高一(下)期末数学试卷(含解析)
- 2024年浙江省温州市瑞安市中考二模语文试题
- 常州市 2022-2023学年七年级下学期英语期末模拟试卷(含答案解析)
- 2023年云南省投资控股集团有限公司招聘笔试题库及答案解析
- 后勤校长述职报告合集6篇
- 浅析陶行知生活教育理论
- 农村集体土地承包经营权调查项目自查(自检)报告
- 十二经脉PPT课件完整版
评论
0/150
提交评论