1、5.1 现场布置5.1 Site Layout 5.1.1项目组织机构图5.1.1 Project Organization Chart 5.1.2组织机构说明5.1.2 Introduction of Organization根据本工程的特点,本着“精干、高效”的原则组建南苏丹Magwi-Lobone公路项目部,项目经理为项目的第一责任人。In accordance with features of the project and under the principle of “high capability and efficiency”, establish the Southern S
2、udan Magwi-Lobone Highway Project Department, and the project manager is the primary person in charge of the project. 项目部下设:The Project department comprises: 决策层:项目经理、项目副经理、总工程师;Decision-making level: Project Manager, Deputy Project Manager, General Project Engineer; 管理层:施工部、技术部、合同部、财务部、QHSE部、机物部、行政
3、部;Management level: Construction Dept., Technology Dept., Contract Dept., Financial Dept., QHSE Dept., Mechanical Materials Dept., Administration Dept.; 工区作业层:根据本工程特点,按照工区管理作业队及班组的形式。设置4个工区,即土方一工区、土方二工区、路面工区、综合工区。 Work area operation level: in accordance with features of the project and as per work
4、areas form to manage operation teams and groups, set up 4 work areas, namely Earthwork area I, Earthwork area II, Road pavement area, Complex processing area. 5.1.3主要管理层的主要工作内容及职责5.1.3 Main Work Content and Duties of Main Management Levelu 施工部:负责施工现场的调度及生产组织等。负责测量队的归口管理及协调工作。u Construction Dept.: be
5、 responsible for scheduling of construction site and organization of production, etc. In charge of the centralized management and coordination work of Survey Team. 测量队:负责本项目测量控制网建立、地形地貌测绘,施工现场测控、结算测量以及竣工测量等工作。Survey Team: be responsible for the establishment of surveying control network and geograph
6、ic and geomorphic surveying and mapping of the project, construction site survey and control, settlement survey and final survey, etc. u 技术部:负责工程的施工方案和施工技术措施的编写,施工图纸的设计,进度的编制及进度更新等工作。u Technology Dept.: be responsible for the compilation of construction scheme and construction technical measure of t
7、he project, design of construction drawings, compilation of schedule and schedule update, etc.u QHSE部:负责工程质量控制管理,各工序施工终检、验收,竣工资料整编等。负责施工安全管理、爆破安全、交通安全管理、施工人员健康、消防、保卫、施工区环境保护等。负责实验室的归口管理及协调工作。u QHSE Dept.: be responsible for the projects quality control management, final inspection and acceptance of
8、construction of all processes, reorganize completion data, etc. In charge of construction safety management, blasting safety, traffic safety management, health of construction personnel, fire control, security, construction area environmental protection, etc. In charge of the centralized management
9、and coordination work of Laboratory. u 实验室:负责本项目原材料检测、土工试验、混凝土现场实验、沥青混凝土实验任务以及外送委托实验任务等内容等。u Laboratory: be responsible for material test, soil test, concrete field experiment, asphalt concrete experiment task and outside entrusted experiment task and other content of the project, etc. u 合同部:负责合同管理、
10、工程结算、资金流控制、预算编制等。u Contract Dept.: be responsible for contract management, project settlement, fund flow control, budgeting, etc. u 财务部:负责成本管理、成本控制、内部经营及负责项目部的内、外财务运作及管理等。u Financial Dept.: be responsible for cost management, cost control, internal operation and in charge of internal and external fi
11、nancial operation and management of the Project Department, etc. u 机物部:负责设备、物资、施工材料、设备配件供应及物供合同的管理,项目部仓储系统的管理,施工设备运行及修理的管理。u Mechanical Materials Dept.: be responsible for supply of equipment, material, construction material, equipment accessories and management of material supply contract, manageme
12、nt of the Project Departments storage system, and management of the operation and repair of construction equipment. u 行政部:负责文件收发、档案管理,内部行政事务,对外协调;负责后勤服务;负责项目的人力资源招聘及管理等。u Administration Dept.: be responsible for receiving and sending files, archives management, internal administrative affairs and ex
13、ternal coordination; in charge of logistics service; in charge of the human resource recruitment and management of the project, etc. u 一工区:包括2个路基作业队,1个结构物作业队和1个排水作业队。负责0+000-40+000段的清表、土石方开挖回填、排水沟、涵洞、桥梁的施工管理。u Work area I: includes 2 subgrade construction teams, 1 structure construction team and 1 d
14、rains construction team. Be responsible for surface cleaning, earth-rock excavation and backfill, and construction management of drain, culvert and bridge from 0+000 to 40+000 section. u 二工区:包括2个路基作业队,1个结构物作业队和1个排水作业队。负责40+000-811+000段的清表、土石方开挖回填、排水沟、涵洞和桥梁的施工管理。u Work area II: includes 2 subgrade co
15、nstruction teams, 1 structure construction team and 1 drains construction team. Be responsible for surface cleaning, earth-rock excavation and backfill, and construction management of drain, culvert and bridge from 40+000 to 811+000 section.u 路面工区:包括2个路面作业队。负责本标段的选定层、底基层和面层的生产等管理工作。u Road pavement a
16、rea: includes 2 pavement construction teams. Be responsible for production and other management work of selected layer, subbase layer and surface layer of this section. u 综合工区:负责所有机械设备的维修、保养以及本项目的辅助工程施工等管理工作。u Complex processing area: be responsible for repair and maintenance of all mechanical equip
17、ment, construction of the projects ancillary works and other management work.5.1.4主要作业层的主要工作内容及职责5.1.4 Main Work Content and Duties of Main Operation Levelu 路基作业队:负责本标段的清表、土石方开挖回填等施工任务。u Subgrade construction team: be responsible for surface cleaning, earth-rock excavation and backfill and other con
18、struction tasks of this section. u 排水作业队:负责本标段的排水设施和浆砌片石护坡修建等施工任务。u Drains construction team: be responsible for construction of drainage facilities and mortar rubble masonry pavement and other construction tasks of this section. u 结构物作业队:负责本标段的管涵、箱涵和桥梁修建等施工任务。u Structure construction team: be respo
19、nsible for construction of pipe culvert, box culvert and bridge and other construction tasks of this section.u 路面作业队:负责本标段选定层、底基层和面层等施工任务。u Pavement construction team: be responsible for construction tasks of selected layer, subbase layer and surface layer of this section. u 机械修理厂:负责本标段所有车辆和设备的维修保养等
20、工作。u Machine repair plant: be responsible for repair and maintenance of all vehicles and equipment and other tasks of this section. u 综合加工厂:负责混凝土骨料、路面碎石料等块石材料的开采、运输及加工;以及钢筋加工、模板维修等。u Complex processing plant: be responsible for exploitation, transportation and processing of concrete aggregate, pavem
21、ent metalling and other stone materials; and processing of reinforced steel, template repair, etc. 5.1.5营地布置5.1.5 Camp Layout 为方便施工管理,计划在线路起点Magwi处设置项目主营地,主营地旁边设置工程师营地,在K30+600处设置一处副营地。主营地包括办公室、宿舍和医务室,副营地包括部分办公室和宿舍。在营地附近打井取水,并检测是否适合饮用。营地设置位置详见5.1-2。To facilitate the construction management, plan to
22、set up the projects main camp on Magwi which is the starting point of the route, set up the engineer camp beside the main camp, and set up a sub-camp on K30+600 position. The main camp includes office, dormitory and dispensary and the sub-camp includes some offices and dormitories. Dig a well beside
23、 camps to get water, and test whether the water is drinkable. Camps set location can be seen in 5.1-2. 5.1.6临时设施设置5.1.6 Setup of Temporary Facilities5.1.6.1施工用电、用水5.1.6.1 Power and Water Supply for Construction 项目办公驻地和施工现场均配备柴油发电机。Both the project site office and construction site are equipped with
24、diesel generator. 道路沿线有部分地表水源(小溪),可打井取用地下水,但均需进行检验以满足施工或饮用水要求。There are some surface water sources (brooks) along the road, it is practicable to dig a well to take use of groundwater, but the groundwater shall be tested to meet the requirements of construction or drinking water. 5.1.6.2施工通讯5.1.6.2 Construction Communication 施工通讯主要以Magwi移动通讯电话为主;无信号的施工区内用对讲机联络,距离较远时设对讲机中转基站。网络通讯安装卫星接收装置,以保证施工指挥协调及对外联络需要。Construction communication mainly relies on Magwi mobile
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 秘书每日工作安排建议计划
- 文学竞赛社团组织策略计划
- 秋季网络教学组织与管理计划
- 信念责任面试题目及答案
- 音乐演奏技巧理论测试与答案解析
- 生物与人文素养的融合教育计划
- 消防安全教育预案
- 2025现代企业合同风险管理与控制策略
- 先天性血管瘤的健康宣教
- 2025供应商合同的核心要素
- 机器学习(完整版课件)
- AEO贸易安全培训
- 《简历制作培训》课件
- 食品安全案例-课件-案例十二-苏丹红事件
- 肝硬化失代偿期
- 2023年非车险核保考试真题模拟汇编(共396题)
- 2024年中国分析仪器市场调查研究报告
- “龙岗青年”微信公众号代运营方案
- DB11-T 478-2022 古树名木评价规范
- 施工现场扬尘控制专项方案
- 年度固定污染源排污许可证质量审核、执行报告审核技术支持服务 投标方案(技术标 )
评论
0/150
提交评论