1、.1号机组首次点火至PAC时间表及详细的调试项1GE重型燃机的典型启动过程11并机调试步骤和方法(OEM版)21启动锅炉燃烧器改造后的点火步骤23燃机启动过程气体燃料泄漏试验过程分析231号机组首次点火至PAC时间表及详细的调试项Day/Date天/日期Test试验Purpose of Test试验目的Test activities试验活动Remarks备注Day 1第1天11/08/2006Rotor run-in:转子试转:Crank test摇转试验Listen for rubs or unusual noises听是否有摩擦和异常噪音Functional test of emergen

2、cy trip button紧急跳闸按钮的功能试验Purge speed cranking for rotor vibration check以吹扫速度摇转,检查转子振动情况Monitor LCI starting temperatures and operation监视器LCI起动温度和运行Air blowing the purge piping of D5 and PM4 gas fuel during crank摇转期间给D5和PM4吹扫管鼓风Check operation of lift oil and turning gear 检查顶轴油和盘车的运行Roll up to 50 rpm

3、 trip by DCS emergency push button and 200 rpm and trip by GT MK 6 control emergency stop通过DCS紧急按钮逐渐增加到50rpm,通过GT MK6控制紧急停机跳闸Restart, accelerate to go to Purge speed for 5min and select normal stop重起,加速到吹扫速度5分钟,选择正常停止Restart, hold at purge speed and air blowing the piping of D5 and PM4, trip by DCS

4、customer trip (L4CT) after 30 Min crank test重起,保持在吹扫速度,给D5和PM4管道鼓风,在30分钟摇转试验后通过DCS客户跳闸(L4CT)跳闸Verify coast down to turning gear核实惰行至盘车Monitor vibration levels through out the test period监视整个试验期间的振动级Use auto start-up sequences to prepare the unit for a “Ready-to-Start”采用自动走动顺序将机组准备好“准备起动”Rub checks a

5、re performed 检查摩擦ADRE vibration monitor to be connected连接ADRE振动监视器After Shut-down停机后Reinstate the piping spool of D5 and PM4 pipe work after shutdown停机后重新恢复D5和PM5管子的导管Day 1第1天11/08/2006Rotor run-in:转子试转:False firing, actual first firing and FSNL假点火,实际第一次点火和FSNLFalse fire假点火Actual First Fire to FSNL实

6、际第一次点火至FSNLSelect fire for false fire and check unit for gas leaks, and P2 pr. Check选择假点火的火,检查机组是否漏气,和P2。检查Verify unit trip and coast down to turning gear核实机组跳闸,惰行至盘车Actual first firing and check for gas leaks at firing speed实际第一次点火,检查点火速度时是否漏气Acceleration unit up to FSNL and stabilized min 4 hours

7、thermal soakStart up heater commissioning将机组加速到FSNL,至少稳定4小时热浸泡Normal down unit and keep turning gear on for natural cooldown.机组正常停机,保持盘车,自然冷却Monitor vibration levels through out the test period监视整个试验期间的振动级After Shut-down停机后1. Install balance shots if required如果需要,安装平衡粒2. Repair any leaks / defects i

8、dentified 修复发现的泄漏/缺陷3. Replace or clean the strainers of LP Hood spray, CEP, BFP and drains spray and perform any other maintenance items as required更换或清洁低压罩喷嘴、EDP、BFP和疏水喷嘴的滤网,根据需要执行其它维护项4. Inspect and clean start up temporary gas strainers and sealing/cooling air if required to clean检查和清洁起动临时气体滤网和密

9、封/冷却空气(如果需要清洁的话)Day/Date天/日期Test试验Purpose of Test试验目的Test activities试验活动Remarks备注Day 2第2天11/09/2006Rotor run-in:转子试转;Start up and FSNL起动和FSNLFSNL and heat soak for 4 hoursFSNL和热浸泡4小时Start normally, go to FSNL and stay there if vibration levels acceptable正常起动,至FSNL,如果振动级可以接受,保持2. Electrical test电气试验

10、1) Shaft voltage test 轴电压试验 2) AC impedance test 交流阻抗试验 3) Main transformer Short circuit test with the connection of Generator by EX2100 power通过EX2100电力连接发电机做主变压器短路试验 4) Open circuit test by EX2100, The test voltage will be variable from 0V to 20.52KV(1.08PU of 19KV)通过EX2100做开路试验,试验电压从0V至20.52KV(19

11、KV的1.08PU/)5) Megger check for seal casing and bearing (T8) at collector end side用迈格表检查收集器端侧密封缸和轴承 (T8)3. Check HRSG expansion.检查HRSG的膨胀4. Shutdown unit and keep turning gear on for natural cool down.让机组停机,保持盘车,自然冷却5. Monitor vibration levels through out the test period监视整个试验期间的振动级6. By pass valve c

12、ommissioning旁路阀门调试After Shut-down停机后1. Install balance shots if required如果需要,安装平衡粒2. Repair any leaks / defects identified 修复发现的泄漏/缺陷3. Replace or clean the strainer of LP Hood spray, and drains spray and perform any other maintenance items as required更换或清洁低压罩喷嘴和疏水喷嘴,根据需要执行其它维护项4. Inspect and clean

13、start up temporary gas strainers and sealing/cooling air if required to clean检查和清洁起动临时气体滤网和密封/冷却空气(如果需要清洁的话)Day/Date天/日期Test试验Purpose of Test试验目的Unit activities机组活动Remarks备注Day 3第3天11/10/2006Rotor Run-in: ;转子试转;FSNLRun up to FSNL 运行至FSNLPerform off line electrical tests执行脱机电气试验Dummy synchronization

14、test伪同步试验Protection test保护试验Synch check同步检查EX2100 on-line test EX2100联机试验1. Unit restart to FSNL机组重新起动至FSNL2. EX2100 Offline test EX2100脱机试验 1) Manual high and low limit,手动高低极限 2) Offline OEL limit test脱机OEL极限试验 3) Offline OEL trip test.脱机OEL跳闸试验 4) Voltage high trip test.电压高跳闸试验 5) V/HZ straight ti

15、me/ Reverse time trip.V/HZ正向/反向时间跳闸 6) Auto High and low limit test.自动高低极限试验 7) PT failure Test. PT故障试验 8) Auto/Manual transfer test.自动/手动传输试验 9) M1/M2 transfer test.M1/M2传输试验3. Dummy Synch test伪同步试验4. Perform synchronize to grid and reverse power 52G trip test if vibration levels Acceptable如果振动级可以接

16、受,与电网并网,倒送电52G跳闸试验 5. EX2100 on-line test (25% load)EX2100 联机试验(25%负荷)6. Monitor vibration levels through out the test period.监视整个试验期间的振动级7. By pass valve commissioning旁路阀门调试After Shut-down停机后1. Install balance shots if required如果需要,安装平衡粒2. Repair any leaks / defects identified 修复发现的泄漏/缺陷3. Replace

17、or clean the strainers of LP Hood spray, CEP, BFP and drains spray and perform any other maintenance items as required更换或清洁低压罩喷嘴、EDP、BFP和疏水喷嘴的滤网,根据需要执行其它维护项4. Inspect and clean start up temporary gas strainers and sealing/cooling air if required to clean检查和清洁起动临时气体滤网和密封/冷却空气(如果需要清洁的话)Day 4第4天11/11/2

18、006Load test负荷试验Combined cycle联合循环Start up and Synch to grid起动和并网Steam cleaning蒸汽清洗Line up of chemical sampling, dosing and CPP调整化学取样、加药和CPPSteam to turbine if steam quality acceptable如果蒸汽质量可以接受,给汽机送蒸汽Over speed trip test超速跳闸试验Restart unit to FSNL and synch to grid 重新起动机组至FSNL,并网Steam cleaning and s

19、team to turbine if steam quality acceptable如果蒸汽质量可以接受,蒸汽清洗,给汽机送蒸汽Steam temperature matching test蒸汽温度匹配试验ST 25% load and min 4 hours soak蒸汽轮机25%负荷,至少浸泡4小时52G breaker off and over speed trip test 52G断路器断开,超速跳闸试验Monitor vibration levels through out the test period监视整个试验期间的振动级After Shut-down停机后1. Instal

20、l balance shots if required如果需要,安装平衡粒2. Repair any leaks / defects identified 修复发现的泄漏/缺陷3. Replace or clean the strainer of LP Hood spray, and drains spray and perform any other maintenance items as required更换或清洁低压罩喷嘴和疏水喷嘴,根据需要执行其它维护项4. Inspect and clean start up temporary gas strainers and sealing/

21、cooling air if required to clean检查和清洁起动临时气体滤网和密封/冷却空气(如果需要清洁的话)Day/Date天/日期Test试验Purpose of Test试验目的Unit activities机组活动Remarks备注Day 5第5天11/12/2006DLN tuning PPM mode to base Load DLN调整PPM模式至基本负荷Combined cycle base load (PPM) operation联合循环基本负荷(PPM)运行Preliminary DLN tuning up base load with strainer (

22、PPM)带滤网初步DLN调整基本负荷Restart unit and load to combined cycle base load with PPM重新起动机组,加载至联合循环基本负荷PPMPerform DLN tuning 执行DLN调整Performance heater commissioning执行加热器调试 3. EX2100 step response test (25%, 50%, 75% and 100%).EX2100阶跃响应试验(25%, 50%, 75% 和100%)4. PT failure test at on-line condition (25% only)

23、联机状态下PT故障试验(仅25%)5. HRSG safety valve test if any HRSG安全阀门试验(如果有的话)6. Perform normal shutdown afterwards and monitor flame out at correct speed during unit coast down执行正常停机,监视机组惰行期间正确速度时的熄火情况7. Monitor vibration levels through out the test period监视整个试验期间的振动级8. Check HRSG expansion.检查HRSG的膨胀After Shu

24、t-down停机后1. Install balance shots if required如果需要,安装平衡粒2. Repair any leaks / defects identified 修复发现的泄漏/缺陷3. Replace or clean the strainer of LP Hood spray, and drains spray and perform any other maintenance items as required更换或清洁低压罩喷嘴和疏水喷嘴,根据需要执行其它维护项4. Inspect and clean start up temporary gas stra

25、iners and sealing/cooling air if required to clean检查和清洁起动临时气体滤网和密封/冷却空气(如果需要清洁的话)Day 6第6天11/13/2006PPM base load for 30 hours PPM负荷30小时Combined Cycle Base Load联合循环基本负荷Combined cycle base load (PPM) operation联合循环基本负荷(PPM)运行Continue to run 30 hours at PPM base load继续以PPM基本负荷运行30小时Restart unit and load

26、 to combined cycle base load (PPM)重新起动机组,加载到联合循环基本负荷(PPM)Monitor vibration levels 监视振动级 Inspect and clean start up temporary gas strainers and sealing/cooling air if required to clean检查和清洁起动临时气体滤网和密封/冷却空气(如果需要清洁的话)Day 7第7天11/14/2006PPM base load for 30 hoursPPM基本负荷30小时Combined Cycle Base Load联合循环基本负

27、荷1. Combined cycle base load (PPM) Operation联合循环基本负荷(PPM)运行2. Continue to run 30 hours at PPM base load继续以PPM基本负荷运行30小时1. Continue to run combined cycle base load (PPM)继续运行联合循环基本负荷(PPM)2. Monitor vibration levels 监视振动级3. Perform normal shutdown afterwards and monitor flame out at correct speed durin

28、g unit coast down执行正常停机,监视机组惰行期间正常速度时的熄火Inspect and clean start up temporary gas strainers and sealing/cooling air if required to clean检查和清洁起动临时气体滤网和密封/冷却空气(如果需要清洁的话)Day/Date天/日期Test试验Purpose of Test试验目的Unit activities机组活动Remarks备注Day 8第8天11/15/2006Cooling down冷却Cooling down to remove all of straine

29、rs冷却后拆除所有滤网Cooling down to remove all of strainers冷却后拆除所有滤网Remove all of strainers for gas fuel, sealing and cooling air, steam strainers after completion of 30 hours operation运行30小时结束后拆除气体燃料、密封空气和冷却空气的所有滤网及蒸汽滤网Day 09第9天11/16/2006Cooling down冷却Cooling down to remove all of strainers冷却后拆除所有滤网Cooling

30、down to remove all of strainers冷却后拆除所有滤网Inspect inlet air and exhaust area检查进气和排气区域Remove all of strainers for gas fuel, sealing and cooling air, steam strainer after completion of 30 hours operation运行30小时结束后拆除气体燃料、密封空气和冷却空气的所有滤网及蒸汽滤网Day 10第10天11/17/2006Cooling down冷却Cooling down to remove all of st

31、rainers冷却后拆除所有滤网Cooling down to remove all of strainers冷却后拆除所有滤网Inspect inlet air and exhaust area检查进气和排气区域Remove all of strainers for gas fuel, sealing and cooling air, steam strainer after completion of 30 hours operation运行30小时结束后拆除气体燃料、密封空气和冷却空气的所有滤网及蒸汽滤网Day 11第11天11/18/2006DLN tuning Premixed mo

32、de to base Load DLN调整预混合模式至基本负荷DLN1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行2. DLN tuning without strainer for Premixed mode预混合模式无滤网DLN调整3. Load reject test for 50% and 100%50%和100%的甩负荷试验1. Restart unit and load to combined cycle base load with PM重新起动机组,加载到联合循环基本负荷PM2. Perform DLN tuni

33、ng 执行DLN调整3. Load reject test for 50% and 100% 50%和100%的甩负荷试验4. Re-Synch to gird and base load重新并网和基本负荷5. Prepare 168 hours reliability test run准备168小时可靠性试运CEMS ready to DLN tuning CEMS准备DLN调整Day 12第12天11/19/2006Reliability run 168hrs, 1 day可靠性运行168小时,第1天1. Combined cycle base load (PM) operation联合循

34、环基本负荷(PM)运行1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行CEMS ready to PM base load CEMS准备PM基本负荷Day 13第13天11/20/2006Reliability run 168hrs,2 day可靠性运行168小时,第2天1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行CEMS ready to PM bas

35、e load CEMS准备PM基本负荷Day/Date天/日期Test试验Purpose of Test试验目的Unit activities机组活动Remarks备注Day 14第14天11/21/2006Reliability run 168hrs, 3 day可靠性运行168小时,第3天1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行CEMS ready to PM base load CEMS准备PM基本负荷Da

36、y 15第15天11/22/2006Reliability run 168hrs, 4 day可靠性运行168小时,第4天1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行CEMS ready to PM base load CEMS准备PM基本负荷Day 16第16天11/23/2006Reliability run 168hrs, 5 day可靠性运行168小时,第5天1. Combined cycle base lo

37、ad (PM) operation联合循环基本负荷(PM)运行1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行CEMS ready to PM base load CEMS准备PM基本负荷Day 17第17天11/24/2006Reliability run 168hrs, 6 day可靠性运行168小时,第6天1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运

38、行CEMS ready to PM base loadCEMS准备PM基本负荷 Day 18第18天11/25/2006Reliability run 168hrs, 7 day可靠性运行168小时,第7天1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行1. Combined cycle base load (PM) operation联合循环基本负荷(PM)运行2. Normal shut down after completion of 168 hours reliability run test168小时可靠性运行试验完成后

39、正常停机CEMS ready to PM base loadCEMS准备PM基本负荷 Day 19第19天 11/26/20068 days start up and shut down daily, 1 day每天起动和停机,共8天,第1天8 days start up and shut down daily每天起动和停机,共8天 8 days start up and shut down daily每天起动和停机,共8天 8 days start up and shut down daily 每天起动和停机,共8天Day/Date天/日期Test试验Purpose of Test试验目的U

40、nit activities机组活动Remarks备注Day 20第20天11/27/20068 days start up and shut down daily, 2 day1 day每天起动和停机,共8天,第2天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天Day 21第21天11/28/20068 days start up and shut down

41、daily, 3 day1 day每天起动和停机,共8天,第3天8 days start up and shut down daily每天起动和停机,共8天 8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天Day 22第22天11/29/20068 days start up and shut down daily, 4 day1 day每天起动和停机,共8天,第4天8 days start up and shut down daily 每天起动和停机,共

42、8天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天Day 23第23天11/30/20068 days start up and shut down daily, 5 day1 day每天起动和停机,共8天,第5天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut dow

43、n daily 每天起动和停机,共8天Day/Date天/日期Test试验Purpose of Test试验目的Unit activities机组活动Remarks备注Day 24第24天12/01/20068 days start up and shut down daily, 6 day1 day每天起动和停机,共8天,第6天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动

44、和停机,共8天Day 25第25天12/02/20068 days start up and shut down daily, 7 day1 day每天起动和停机,共8天,第7天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天Day 26第26天12/03/20068 days start up and shut down daily, 8day1 day每天起动

45、和停机,共8天,第8天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天8 days start up and shut down daily 每天起动和停机,共8天Day 27第27天12/04/2006No Test没有试验Cooling冷却Cooling for water wash冷却准备水洗Install performance test equipments安装性能试验设备Day 28第28天12/05/2006No Test没有试验Coolin

46、g冷却Cooling for water wash冷却准备水洗Install performance test equipments安装性能试验设备Day/Date天/日期Test试验Purpose of Test试验目的Unit activities机组活动Remarks备注Day 29第29天12/06/2006Off line water wash脱机水洗Off line water wash脱机水洗Off line water wash脱机水洗Off line water wash脱机水洗Day 30第30天12/07/2006Integrated DLN Tuning整体DLN调整I

47、ntegrated DLN Tuning for part load部分负荷整体DLN调整Integrated DLN Tuning for part load部分负荷整体DLN调整Collect data收集数据Day 31第31天12/08/2006No Test没有试验Cooling冷却Cooling for water wash冷却准备水洗Day 32第32天12/09/2006No Test没有试验Cooling冷却Cooling for water wash冷却准备水洗Day 33第33天12/10/2006Off line water wash脱机水洗Off line water

48、 wash脱机水洗Off line water wash脱机水洗Off line water wash脱机水洗Day 34第34天12/11/2006Integrated DLN Tuning整体DLN调整Integrated DLN Tuning for base load基本负荷整体DLN调整Integrated DLN Tuning for base load基本负荷整体DLN调整On line water washing test if any required如果需要,做联机水洗试验Collect data收集数据Day/DateTest天/日期Purpose of Test试验目的

49、Unit activities机组活动Remarks备注Day 35第35天12/12/2006No Test没有试验Cooling冷却Cooling for water wash冷却准备水洗Day 36第36天12/13/2006No Test没有试验Cooling冷却Cooling for water wash冷却准备水洗Day 37第37天12/14/2006Off line water wash脱机水洗Off line water wash for performance test脱机水洗准备做性能试验Off line water wash脱机水洗Off line water wash

50、脱机水洗Day 38第38天12/15/2006Performance Test性能试验Baseload & Part load performance test基本负荷和部分负荷性能试验Emission level check排气污染程度检查Operational noise levels check运行噪音级检查Baseload performance test on gas气体基本负荷性能试验Part load performance tests on gas气体基本负荷性能试验 Emission tests排放试验Operational Noise levels measure

51、ment测量运行噪音级Test to be done within 25 hours after GT compressor water wash.在燃机压缩机水洗后25小时做试验Ensure unit operated at baseload for at least 2 hours prior to test.确保试验前机组至少以基本负荷运行2小时Day 39第39天12/16/2006No Test没有试验Cooling冷却Remove performance test equipment拆除性能试验设备Remove performance test equipment拆除性能试验设备D

52、ay 40第40天12/17/2006Load test负荷试验Power System Stability (PSS) Tests电力系统稳定性(PSS)试验Restart unit and load to combine cycle base load重新起动机组,加载至联合循环基本负荷Perform PSS tests执行PSS试验This test can be done any time during commissioning period depend on customers decision此项试验在调试期间随时可做,由客户决定GE重型燃机的典型启动过程以下的操作指南是适用于

53、7001FA、9001E或9001FA系列燃机驱动的发电机机组。操作指南以Mark V SPEEDTRONIC透平控制盘为例启动1总则。操作一台单循环的透平/发电机组即可以在就地进行,也可以通过远方遥控操作。下面的描述列举了运行人员、控制系统和机组在燃机启动时的操作或事件。请参考描述透平控制盘设备的文件控制盘和术语透平控制盘。以下内容是假定机组在盘车状态,可以随时启动。2启动程序a 用在DEMAND DISPLAY菜单中选择“MAIN”画页然后点击进入。(1)此画页显示速度、温度及机组的各种状况等参数。在<I>显示器上显示下面三条状态:SHUTDOWN STATUS(停机状态)OF

54、F COOLDOWN(盘车停止)OFF(闭锁状态)b用光标点击“AUTO(自动)”靶标后再点击“EXECUTE(执行)”靶标。(1) <I>显示器将出现下面三条显示:STARTUP STATUS(启动状态)READY TO START(准备启动)AUTO(自动)c用光标点击“START”靶标后点击“EXECUTE”靶标(1)机组辅机例如滑油泵将被启动以建立滑油压力。在<I>显示器上显示SEQ IN PROGRESS(程序在进行中)信息。(2)当条件满足后,主保护信号(L4)被满足,显示器上显示将变成:STARTUP STATUS(启动状态)STARTING(正在启动)A

55、UTO(自动)START(启动)(3)盘车装置将开始盘动透平转子,零转速继电器信号“14HR”将出现。当机组转速达到大约6rpm时,启动装置带电,机组开始加速。<I>显示器出现STARTUP STATUS/CRANKING(启动状态/高盘)信号。(4)当机组达到15转速时,最小点火转速信号(14HM)在<I>显示屏上出现。(发电机励磁系统开始启励建立发电机电压并通过UCAT变压器给机组冷却水风扇提供电源。否则发电机将在运行转速时才进行启励建压。(5)如果机组的构造要求在点火前进行热通道的清吹,启动装置将以清吹转速按照清吹计时器的设定时间进行高盘。清吹计时器的设定参见控制规范参数设定图(6)FSR将被设定成点火值(FSR燃油流量冲程基准是决定进入透平燃烧系统的燃油流量的电信号。)点火程序被触发,<I>显示屏上将显示START UP STATUS/FIRING(启动状态/正在点火)信号。(7)当火焰出现,<I>显示屏上显示那些装有火焰探头的燃烧室的火焰状况。(8)FSR将设定为暖机值,<I>显示屏将显示STARTU

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论