1、船坞(台)大合拢搭载工艺Final Erection Craft 文件号:QB/JMS-01H1313-09船坞(台)大合拢搭载工艺 版改号:A / 0页次:15 /15一、适用范围 Range of application本工艺主要适用于在倾斜船台进行大合拢建造的钢质全焊接船舶;This craft is applied to all-welding steel ships in inclined building berth本工艺主要包含了合拢前分段技术要求以及分段吊装程序工艺。This craft includes block technical requirement before a
2、ssembly and block lifting procedure.二、工艺内容Content:1、大合拢前的场地准备:Site preparation before final erection:1.1船体分段大合拢通常在船台或船坞上进行,对船台场地应进行必要的打扫和清理。Block erection usually is conducted on berth or dock, the ground should be clean. 1.2船台中心线处勘划船体中心线的船台地面扁钢条应除锈,涂防锈漆,所勘划船中心线肋位站号应明显、永久、精确。Ship berth flat steel ba
3、r of hull center line need rust removal, painting antirust paint. Frame number on ship center line should be obvious, permanent and accurate.1.3在船台一侧设置永久性标杆并涂上油漆,在标杆上设置分段水平检验标志,该标志要求醒目,在船台合拢区域内不得有妨碍激光寻标的任何物件。Set a permanent benchmark on one side of berth and being painted. Set block level testing ma
4、rk on benchmark, this testing mark should be striking. Anything in berth erection area obstruct laser marking is not permitted. 1.4船台定位肋骨线,根据排楞图中滑落机的位置,定出船体在船台上的布置位置,用 40mm×40mm肋位样条在船体基线一定高度位置,定出船台面中心线肋位号标志,该标志应明显、永久、精确。Locate frame line. According location of slide machine, find arrangement lo
5、cation of hull on berth, and mark the berth center frame number, and this mark should be obvious, permanent and accurate.2、大合拢前分段技术要求:Block technical requirement before final erection;2.1进行大合拢的分段作为中间产品,必须是经中合拢检验合格的分段产品,其分段的建造精度符合CSQS。进行船台大合拢预装的预埋件,必须根据生产计划及托盘表的要求按时送到大合拢指定地点。As semi-finished product,
6、 final erection blocks must be qualified after middle erection, of which building accuracy must accord to CSQS. The embedded part for berth erection preassembly must be sent to erection place in time according to production plan and requirement of tray table.3大合拢分段合拢要点:Key point of final erection bl
7、ocks3.1分段合拢时以定位分段为基准,然后向艏、艉方向发展的舯塔式建造方案。为此定位分段上船台前两端余量割净,按焊接型式要求两端开出坡口。In block erection, with the base block as reference, building fore and aft, which is middle tower building scheme, is adopted. Clean margin of both ends of base blocks before they are carried to berth. Open groove at both base bl
8、ock ends according to welding types.3.2主船体其它各分段其拼接端的余量上船台套割,其另一端自由端在上船台前割去余量,开出焊接坡口。艏楼、甲板室分段下端余量上船台合拢时套割。The joint side margin of each other blocks should be cut off before erection. And margin of the other free end should cut off before erection and open the welding groove. The margin of lower part
9、 of forecastle and deck house should be cut during the erection. 3.3船体双层底企口上侧余量50mm,用企口接缝线10mm作为上口线激光划线,然后割去余量。For double bottom, the margin of upper side is 50mm, use groove seam line 10mm as upper edge line laser mark, then cut off the margin.3.4分段两端构件尽可能一刀切,为保证分段的强度和构件的完整性,纵向构件碰到横舱壁时,构件应延伸到舱壁,环形大
10、接缝尽量在同一平面内。To ensure the block strength and integrity of components, cut the components of both block ends with one cut as possible. When longitudinal component encounter the transverse bulkhead, component should be extended to bulkhead, and big ring joint should be at same level as possible. 3.5为保证
11、底部双层底分段长度和减少舷侧分段与双层底分段的肋位的错位现象,在双层底分段的大合拢接口处的肋位,船台定位考虑环缝焊接收缩量后,装配误差应控制在+3-0mm之内。To ensure block length of double bottom and reduce the frame number dislocation of double bottom, error of assembly on erection joint frame number of double bottom should be within +3-0mm, considering the shrinkage of ci
12、rcular seam welding.3.6为使上层建筑吊装时,肋位误差尽可能小,主船体大合拢接口肋位误差控制在±5mm之内。To reduce frame number error as possible when lifting the superstructure, control the frame joint error of hull erection within ±5mm3.7舷侧分段下口外板50mm 纵舱壁20mm余量按标杆修正定位水线10mm,再放公差12mm,划线后再割去下端余量。3.8 对于双壳体的船舶,考虑内壳的精度,纵向舱口围板焊在舷侧分段甲板
13、上,该甲板不伸出纵舱壁和纵向舱口围板,左右相应舷侧分段应在平台上事先在分段艏艉上端用方形横撑过桥固定,同时亦可在船台上分别定位后,加固方形横撑过桥。As for double shell ship, considering accuracy of inner shell, longitudinal hatch coaming should be welded to decks of shipside block. The deck could not extend out of longitudinal bulkhead and longitudinal hatch coaming. Rele
14、vant shipside blocks P/S should be fixed on platform with square gap bridge in advance. Also,locate3.9根据图纸要求加放大合拢分段反变形值,本厂惯例艉部0、-10、-15mm,艏部-5、-5、-10mm。Add deformation value of erection block as drawings requirement, usually deformation value of stern is 0、-10、-15mm,and that of bow is -5、-5、-10mm.3.
15、10对箱型结构双层底分段环缝的焊接,一定要在前后或后方已拼23只分段,并在其中分段上加固体重物压载后才可进行。For circular seam welding of box structure double bottom block, it is necessary that there have been 2 or 3 jointed block fore or aft and solid heavy things to be ballasted on blocks.3.11所有分段大合拢环缝附近的横向构件角焊缝在分段建造中均应焊妥。为使大合拢环缝接口光顺,减少凹凸不平现象,在大合拢环缝附
16、近,最好在强构件处,用火工进行反变形加工,一般将板边向外烘烤1020mm左右,并在双层底横向环缝离实肋板若大于等于400mm自由端,则在舭部离环缝50mm处,做假舭肘板,用一8×300,余料拼成,直至分段大合拢定位前拆去。Transverse component angle welding seam near erection circular seam should be welded well for all blocks. To make joint of erection circular seam fair and reduce uneven part, near erec
17、tion circular seam, take deformation process with hot work. Generally bake the plate edge about1020mm,and if distance between double bottom transverse circular seam and solid floor is equal or greater than 400mm free end, then make a virtual bilge bracket 50mm away from bilge. The virtual bilge brac
18、ket is made of 8×300 margin. Remove the virtual bilge bracket before positioned erection.3.12分段在大接缝处的纵桁及纵向构件不包括舱壁250500 mm内不焊接,应待大合拢拼接后再焊接。Longitudinal girder and longitudinal component except 250-500mm of bulkhead are not welded until erection assembly.3.13艉轴管一般在艉立分段上预装,因而艉立分段上船台安装应以轴系粗拉线与主机座相
19、对位置为基准,船台定位。在船台大合拢时应及时测量轴系中心线的变形偏移并及时控制。Stern tubes usually preassemble on stern vertical block, so installation of berth should be on base of relative location of shaft rough line and ER foundation, then position the berth. When erect the berth, excursion of shaft center line should be measured in
20、time and taken under control. 3.14大合拢环缝的十字焊缝分段装配定位时先矫直,内侧焊缝焊接结束后,外侧焊缝应采用先将纵向焊缝进行碳刨,使纵向焊缝保持光顺后进行焊接,然后碳刨环缝,焊接横向大合拢环缝。When block is being assembled, cross welding seam of erection circular seam should be adjusted. After finishing welding inner side seam, carbon gouging should be taken to longitudinal w
21、elding seam in order that longitudinal welding seam keeps fair, then carbon gouge the circular seam and weld the transverse erection circular welding seam.3.15若舷侧分段上端舱口围板顶板处有高强度钢构件的,一般考虑舱口围板顶板的面板在大合拢时焊接,并严格按照高强度钢的焊接工艺进行。If there is high strength steel component on top plate of hatch coaming on ships
22、ide block, generally the face plate of hatch coaming is welded in erection and it takes in accordance with welding procedure of high strength steel.3.16凡二次除锈分段,在大接缝处端接缝及构件端部、船台散装件处的焊缝区域不油漆,并用胶带保护。For all secondary rust removal block, welding zones of end seam, end of component, berth stuff are not p
23、ainted and protected with adhesive tape.3.17各分段装配定位后,分段间的船台散装构件按托盘表应装妥。After each block assembly positioning, berth bulk between blocks should installed well according to tray table.3.18根据建造进度,凡已构成密闭区域处可以进行密性试验,密性试验技术要求详见相关船舶全船密性试验图。According to building schedule, tightness test can be taken to encl
24、osed area. Technical requirement of tightness test see in tightness test drawing of relative ship.4、拉轴线条件:Condition of pulling axis:4.1机舱前端横舱壁向艉主船体焊接、火工、密性试验结束。Welding from transverse bulkhead in front of engine to stern part of hull, hot work,then finish the tightness test.4.2带缆桩、导缆器等系泊设备定位焊接火工结束。P
25、ositioning welding of mooring equipment, such as bollard and fairlead completed.5、勘划水尺、水线、载重线条件: Condition of water depth mark, water line and load line.5.1全船主体焊接结束,上建分段定位安装结束。Welding of main hull completed, positioning assembly of superstructure block completed.5.2 船体基线挠度连续三次测量值趋向稳定Three times cont
26、inuous measuring value of hull base deflection tend to be stable.6、船舶下水前船台最少工作量:Reduce workload of berth before launching.6.1下水前,主要船体结构、水下工作及预制预装工作结束。Before launching, preassembly of main hull structure, underwater work, prefabrication and preassembly completed.7、船体建造误差及验收项目 Shipbuilding error and c
27、heck project: 船 长 ship length ±L/1000 mm 船 宽ship width ±B/1000mm 型 深 moulded depth 2D/1000mm船底基线龙骨挠曲度 keel deflection of bottom base line ±25 mm 船底中心线偏移 shift to bottom center line ± 5 mm上 翘 raise 艏bow ±30 mm 艉 stern ±20 mm 大接头肋距framespace of big joint ±10 mm8、各类型分
28、段合拢时吊装程序:Lifting procedure of various blocks in erection8.1底部分段的吊装程序 Lifting procedure of bottom block8.1.1将分段吊上船台(同时包括定位分段在内),分段上船台前,应按工艺要求切割余量,无余量上船台,减少大合拢修割工作量.Lift the block onto berth(including position block),To reduce erection modified cutting, the block should cut off margin according to cra
29、ft requirement and block should be lifted to berth without any margin. 8.1.2吊线锤使分段定位肋骨线对准船台上相应肋骨线 Align the positioning frame line on block to relevant frame line on berth with plumb bob.8.1.3吊线锤使分段中心线对准船台中心线Align the center line on block to center line on berth with plumb bob.8.1.4用水平管(或激光经纬仪)校验船底基
30、线高度,使之与相应的船底基线高度相符合,并使分段纵倾度与龙骨斜度相一致,注意由船台坡度而产生的读数差.Use leveling pipe (or laser theodolite) to check height of bottom base line to make it coincide with height of relevant bottom base line, and coincide block trim to keel inclination. Pay attention to differential reading caused by berth gradien
31、t.8.1.5用水平管校验分段横向状态,使之左右保持水平.Use leveling pipe to check transverse condition of block to keep it horizontal left and right.8.1.6划出并切除余量,并与相邻分段对接.Mark and cut off margin, and jointed neighbouring blocks.8.1.7固定分段位置,以待焊接.Fix block position to wait for welding.8.1.8底部分段合拢精度要求:Erection accuracy requirem
32、ent of bottom block. 中心线偏差<2mm Center line offset is less than 2mm左右水平偏差±4mm Left-and-right level 船底中心线艏艉高度与基线偏差±2mm Fore and aft height of bottom center line and base line ±2mm 肋骨检验线前后位置偏差<±4mm.Back and forth of frame inspection line <±4mm8.2舷侧平面分段的吊装:Hoisting of s
33、ide level block8.2.1将分段吊上船台,根据具体船舶分段划分图要求,需要割除的余量,应当切割完毕,但舷顶列板上缘应于分段两端300400mm不割,以便相邻分段对接后,修齐上口线。Lift the block on the slipway and cut the allowance which need to be cut according to the block division plan, but top of sheer strake should not be cut on the both ends of the block 300400mm so as to to
34、uch up the edge line after the block connection.8.2.2使分段定位肋骨线对准底部分段相应的定位肋骨线.Make the block locating frame line aim at the opposite locating frame line at bottom8.2.3用水平管(或激光经纬仪)使分段纵倾度与基线相一致,并使水线高度符合标杆上的相应高度。Use the horizontal pipe(or laser theodolite)to make the block trim reconcile with the base li
35、ne and make the water line height fit the height of pole.8.2.4在分段两端的肋骨线和甲板边线相交处吊线锤检验其型宽。Hang a plumb bob at the connection of frame line and deck edge line to test its molded breadth.8.2.5划出并割除分段下缘的余量Line out and cut the allowance at block underneath. 8.2.6固定分段,以待焊接。Fix the block for welding 8.2.7舷侧
36、平面分段合拢精度控制:Side level block folding accuracy control前后水平<=3mm Back and forth <=3mm水线高度±4mm Water line height ±4mm8.3甲板平面分段的吊装:Deck level block hoisting8.3.1将分段吊上船台,根据具体船舶分段划分图要求,需要割除的余量,应当切割完毕。Lift the block on the slipway and cut the allowance which need to be cut according to the b
37、lock division plan.8.3.2使分段上横梁定位线对准舷侧分段同号肋骨定位线。Make the upper beam locating line aim at the ship side same number block frame locating line.8.3.3吊线锤 (或激光经纬仪)使分段中心线对准内底上的船体中心线。Plumb bob (or laser theodolite)make the block center line aim at the hull center line of inner bottom.8.3.4根据舷侧对准甲板边线。Accordi
38、ng to the side, aim at the deck edge line.8.3.5利用水平软管检验梁拱。Use level hose to test the camber.8.3.6固定分段,以等焊接。Fix the block for welding8.3.7甲板平面分段合拢精度控制:Deck level block folding accuracy control甲板中心线与船底中心偏差<3mm Deck center line and bottom center line 甲板宽度B±0.05%B Deck breadth B±0.05%B肋骨检验线
39、前后位置偏差±5mm Back and forth of frame testing line ±5mm8.4艏立体分段的安装:Fore tridimensional block installation8.4.1将分段吊上船台,根据具体船舶分段划分图要求,需要割除的余量,应当切割完毕。Lift the block on the slipway and cut the allowance which need to be cut according to the block division plan8.4.2吊线锤使分段中间定位肋骨线、首端点分别对准船台上的相应肋骨线及首
40、端点位置,两者相矛盾时,一般以首端点作为定位依据。Plumb bob(or laser theodolite)make the block center locating frame line and head point respectively aim at frame and the head point on the slipway. If conflict, generally use head point as locating poisition.8.4.3吊线锤 (或激光经纬仪)使分段中心线对准内底上的船体中心线。Plumb bob (or laser theodolite)m
41、ake the block center line aim at the hull center line of inner bottom.8.4.4吊线锤 (或激光经纬仪)校验基线,并使之与高度标杆上相应的高度符合,并使分段的纵向倾斜度与基线坡度相一致Plumb bob(or laser theodolite)tests the base line and make it as same as the height pole and make the block trim as same as the base line gradient. 8.4.5用水平软管(或激光经纬仪)校验艏端点高度
42、,使之与高度标杆上的首端点高相符合;也可以用钢卷尺根据线型图上首端点距基线的垂直距离直接量取,但读数要考虑因基线坡度而修正的数值。高度定位时,还需考虑基线的反变形值。Use level hose (or laser theodolite)to test the height of fore head point and make it as same as the height pole. We can also use the steel tap to measure the vertical distance between fore head point and the base lin
43、e in the body line plan directly. But the revised number due to the base line gradient should be considered. The deformation value of base line should also be considered when locating the height. 8.4.6用水平软管在甲板面上校验分段的横向状态,使之左右保持水平。Use the level hose on the deck level to test block's transverse co
44、ndition and keep it in balance.8.4.7割除余量,并与相邻分段对接。Cut off the allowance and connect it with adjacent block.8.4.8固定分段,以等焊接。Fix the block for welding8.4.9艏立体分段的安装精度要求: Fore tridimensional block installation accuracy demands中心线偏差(上下) <3mm Center line deviation (up and down) <3mm甲板左右水平±5mm De
45、ck right and left level deviation ±5mm船底中心处艏艉端高度与基线偏差±5mm Fore and aft height at bottom center and base line deviation ±5mm肋骨检验线与船台中心线偏差±5mm Frame test line and slipway center line deviation ±5mm艏柱中心线与船台中心线偏差<5mm Stem center line and slipway center line deviation <5mm8
46、.5艉立体分段的安装:Aft tridimensional block installation8.5.1将分段吊上船台,根据具体船舶分段划分图要求,需要割除的余量,应当切割完毕。Lift the block on the slipway and cut the allowance which need to be cut according to the block division plan8.5.2吊线锤使分段中间定位肋骨线、尾端点、舵杆中心分别对准船台上的相应标记,分段前后位置,定位肋骨线、舵杆中心线与尾端点的位置相矛盾时,一般以舵杆中心线为定位依据。Plumb bob make th
47、e frame line in the middle of block 、the end point and rudderstock center aim at the mark on the slipway separately. When front and back position of block、locating frame line and rudderstock conflict with the end point ,generally use the rudderstock center line as the locating basis. 8.5.3吊线锤 (或激光经纬
48、仪)使分段中心线对准内底上的船体中心线。Plumb bob (or laser theodolite)make the block center line aim at the hull center line of inner bottom.8.5.4用水平软管(或激光经纬仪)校验基线,轴中心线高度,使之与高度标杆上相应的高度相符合,分段的纵倾度与基线坡度相一致。Plumb bob(or laser theodolite)tests the base line and make it as same as the height pole and make the block trim as
49、same as the base line gradient.8.5.5用水平软管(或激光经纬仪)校验艉端点高度,使之与高度标杆上的尾端点高相符合;也可以用钢卷尺根据线型图上尾端点距基线的垂直距离直接量取,但读数要考虑因基线坡度而修正的数值。高度定位时,当尾端点、轴中心线与基线高度相矛盾时,一般以轴中心线高度为定位依据,其余作参考。Use level hose (or laser theodolite)to test the height of fore head point and make it as same as the height pole. We can also use the
50、 steel tap to measure the vertical distance between end point and the base line in the body line plan directly. But the revised number due to the base line gradient should be considered. When locating the height, if the end point and axis center line conflict with the base line height ,usually use t
51、he axis center line as locating basis and the others are used as reference.8.5.6用水平软管在甲板面上校验分段的横向状态,使之左右保持水平。Use the level hose on the deck level to test block's transverse condition and keep it in balance.8.5.7割除余量,并与相邻分段对接,但要放焊接收缩余量35mm。Cut off the allowance and connect it with adjacent block,
52、 but it need to leave welding shrinkage allowance 35mm.8.5.8固定分段,以等焊接。Fix the block for welding8.5.9艉立体分段的安装精度要求: Aft tridimensional block installation demands中心线偏差(上下) <3mm center line deviation (up and down) <3mm甲板左右水平±5mm deck right and left level ±5mm船底中心处艏艉端高度与基线偏差±5mm Fore
53、 and aft height at bottom center and base line deviation ±5mm肋骨检验线与船台中心线偏差±5mm Frame test line and slipway center line deviation ±5mm艉柱中心线与船台中心线偏差<5mm Stem center line and slipway center line deviation <5mm8.6舱壁平面分段的安装:bulkhead level block installation8.6.1将分段吊上船台。Lift the block
54、 to the slipway8.6.2使舱壁下缘对准底部(或甲板、平台)分段上的中心线。Make the bulkhead lower aim at the center line on the bottom(or deck、plate)8.6.3吊线锤使舱壁中心线对准底部(或甲板、平台)分段上的中心线。The plumb bob makes the bulkhead center line aim at the center line on the bottom(or deck、plate)8.6.4使舱壁与基线面垂直,并用线锤或斜度样板检验。Make bulkhead and base
55、line level be vertical and test with plumb bob or slope model.8.6.5用水平管校验舱壁上的水线,使之保持水平。Use horizontal pipe to test water line on the bulkhead and keep it in balance. 8.6.6用水平管确定舱壁上的水线位置,使之与标杆上要求的水线高度相一致。Use horizontal pipe to determine the water line position on the bulkhead ,m make the water line h
56、eight fit the height of pole. 8.6.7上述位置的高度差即为余量,在舱壁上划出并割除。Above mentioned position's height differences are allowance; line out and cut off them on the bulkhead.8.6.8固定舱壁,以等焊接。Fix the bulkhead for welding.8.6.9舱壁平面分段的安装精度:Bulkhead horizontal block installation accuracy control中心线偏差<2mm Center
57、 line deviation <2mm左右水平偏差±3mm Right and left horizontal deviation ±3mm垂直度±4mm vertical value ±4mm8.7上层建筑分段的安装:Superstructure block installation 8.7.1将分段吊上船台。Lift the block to the slipway8.7.2将分段两舷外围壁定位肋骨线与甲板面上所划的肋骨线相对准。Make locating frame line of double side bulkhead aim at t
58、he frame line lined out on the deck. 8.7.3吊线锤 (或激光经纬仪)使分段上甲板中心线及两端外围壁中心与甲板面上所划的中心线相对准。Plumb bob (or laser theodolite)make the deck center line of block and double ends bulkhead center aim at the frame line lined out on the deck.8.7.4用水平软管(或激光经纬仪)校验分段的纵倾度与基线坡度相一致基线(也可用甲板中高检查,)分段前后、左右端壁水线检查线在同一平面上。Use
59、 horizontal hose(or laser theodolite) to test that the base line of the block's trim and base line slope (also can be used in deck height testing) and all around water line test line are on the same level.8.7.5根据图纸尺寸垂直量取检查水线到甲板面上的距离,大于定值者减去分段与甲板面上的距离,大于定值者减去分段与甲板间的空隙和定值之和即为余量,划后割除。Vertically measure the distance between testing water line and deck level according to the drawing size.8.7.6固定分段,以等焊接。Fix the block for welding 8.7.7上层建筑分段的安装精度: Superstructure block installation accuracy船中心线与甲板
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2024年大型仓储屋顶防水分包合同
- 2024年个人车辆租赁给企业合同
- 2024年城市公共服务合同
- 2024年厨房设备租赁及运营合同
- 物联网服务合同
- 2024年农副产品采购销售合同
- 2024年专用版:住宅购买合同
- 2024年合同担保金协议
- 2024年个人住房按揭合同
- 2024年公共卫生事件监控预警工程合同
- (新版)糖尿病知识竞赛考试题库300题(含答案)
- 《创意改善生活》课件 2024-2025学年湘美版(2024)初中美术七年级上册
- CHT 1027-2012 数字正射影像图质量检验技术规程(正式版)
- 《扣件式钢管脚手架安全技术规范》JGJ130-2023
- 教学成果奖培育思考
- 河北省廊坊市药品零售药店企业药房名单目录
- 毕业设计(论文)叉车液压系统设计
- 研发项目立项管理流程总体思路.doc
- 室内装饰装修工程施工组织设计方案(完整版)
- 榆林市第十二中学第二个五年发展规划
- 日本城市生活垃圾处理现状及发展趋势
评论
0/150
提交评论