绿地博城DX-1地块小学项目
高支模安全专项方案
编制单位:中建八局第一建设有限公司绿地国博城项目部
H期:_________2020年8月6日___________________
目录
第一章编制依据.................................................................201
第二章工程概况.................................................................202
2.1总体概况..................................................................202
2.2设计概况..................................................................203
2.2.1工程建筑概况...........................................................203
2.2.2高大模板工程概况......................................................203
2.3工程施工条件..............................................................206
第三章施工安排.................................................................207
3.1项目管理机构...............................................2U/3.2项目管理目标
..........................................................................................................................................................................................................................208
3.3各项资源供应计划..........................................................208
3.3.1劳务资源安排...........................................................208
3.3.2工程大宗物资供应安排..................................................209
3.4施工流水段划分及工艺流程..................................................209
3.5工程重难点分析及应对措施..................................................210
3.6新技术应用................................................................210
第四章工期计划.................................................................210
第五章施工准备与资源配置计划...................................................211
5.1技术准备..................................................................211
5.2资源配置计划..............................................................211
5.2.1劳动力配置计划........................................................211
5.2.2工程施工主要周转材料配置计划..........................................211
5.2.3施工设备配置计划......................................................212
5.2.4测量仪器配置计划......................................................212
第六章模板施工设计与施工.......................................................213
6.1楼板模板方案选择及工艺...............................2136.1.1楼板模板设计
......................................................................................................................................................................................................................213
6.1.2楼板模板安装.........................................................213
6.2梁模板方案选择及工艺......................................................214
6.2.1梁模板设计.............................................................214
6.2.2梁模板安装.............................................................214
6.3墙柱模板方案选择及工艺....................................................215
6.3.1墙柱模板设计..........................................................215
6.3.2墙柱模板安装..........................................................215
6.4满堂支撑架方案选择及工艺..................................................215
6.4.1构造要求..............................................................215
6.4.2架体搭设顺序..........................................................215
643剪刀撑的搭设要求216644架体拉结点的设置
..................................................................................................................................................217
6.5方案要点阐述..............................................................219
6.6架体验收..................................................................224
6.6.1检查验收标准和要求....................................................224
6.6.2验收程序..............................................................224
6.6.3验收内容..............................................................224
6.6.4验收人员..............................................................225
6.6.5验收表.................................................................225
6.7施工注意事项..............................................................227
6.8模板拆除..................................................................227
6.8.1拆除制度..............................................................227
6.8.2模板拆除的原则........................................................227
6.8.3拆模时碎强度条件......................................................228
6.8.4拆模顺序..............................................................229
6.8.5楼板、梁模板拆除工艺..................................................229
6.8.6拆除工艺施工要点......................................................229
第七章进度管理计划.....................................2297.1确定施工进度控制点
...............................229
7.2施工进度管理组织机构和职责分工............................................229
第八章质量管理计划.............................................................230
8.1质量控制目标分解..........................................................230
8.2质量管理的组织机构和职责分工..............................................230
8.3质量保证措施..............................................................231
8.4质量验收措施..............................................................232
8.4.1原材进场验收...........................................................232
8.4.2架体搭设验收..........................................................232
8.4.3模板安装验收..........................................................234
第九章安全文明施工措施..........................................................235
9.1职业健康安全管理分解目标....................2359.2安全管理组织机构和职责分工
......................................................................................................................................................................236
9.2.1安全管理组织机构......................................................236
9.3职业健康安全重大危险源....................................................238
9.4安全生产管理制度..........................................................239
9.5安全生产措施..............................................................239
9.6高支模监测计划............................................................240
9.6.1高支模检查和监测要点..................................................240
9.6.2混凝土浇筑过程监测....................................................241
9.6.3详细监测方法及方案....................................................241
第十章绿色施工措施.............................................................242
10.1绿色施工管理粗织及职责...................................................242
1U.2绿色施工管理贡任分配表....................................................243
10.3境保护...................................................................244
10.3.1扬尘控制..............................................................244
10.3.2噪音与振动控制.......................................................244
10.4绿色施工特色措旅推行.................................244第十一章成品保护计划
..........................................................................................................................................................................245
11.1成品保护管理组织和职责分工...............................................245
11.1.1成品保护管理组织......................................................245
11.1.2成品保护职责分工......................................................246
11.2成品保护计划及保证措施...................................................246
第十二章应急预案...............................................................246
12.1应急领导小组..............................................................246
12.2危险源辨识...............................................................247
12.3危险源应急处理措施.......................................................247
12.4应急准备与应急响应.......................................................250
12.4.1应急准备..............................................................250
12.4.2应急响应..............................................................252
第十二章疫情防控措施................................25313.1项目疫情防控组织保障
.................................................................................................................................................................253
13.2疫情应急救援组织体系图...................................................254
13.3项目疫情工作职责.........................................................254
13.4项目疫情防控分工表.......................................................255
13.5储备防疫物资情况.........................................................256
13.6疫情防控应急预案.........................................................256
13.6.1疫情防控措施..........................................................256
13.6.2项目日常工作..........................................................258
13.7关闭疫情防控程序.........................................................260
第十四章附图....................................................................260
第十五章计算书.................................................................261
15.1满堂楼板模板支架计算(9.85M高120MM厚).................................261
15.2梁模板扣件钢管支撑架计算(300x700)..........................................................................270
15.3梁木模板与支撑计算(300x700).......................................................................................280
15.4梁模板扣件钢管支撑架计算(400x1300).•…28315.5梁木模板与支撑计算<400x1300)
.................................................................................................................................................................293
第一章编制依据
序号类别文件名称编号
1《中华人民共和国安全生产法》2018修订版
国家行政
2《中华人民共和国环境保护法》2018修订版
文件
3《建设工程安全生产管理条例》国务院令第393号
8《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2011
9《建筑结构荷载规范》GB5OOO9-2O12
10《建筑施工模板安全技术规范》JGJ162-2008
11《钢管脚手架扣件》GB15831-2006
12《建筑施工高处作业安全技术规范》JGJ80-20I6
13国家行业《建筑施工安全检查标准》JGJ59-2011
14规范《建筑施工临时支撑结构技术规范》JGJ300-2013
15《建筑施工安全技术统一规范》GB5O87O-2O13
16《混凝土结构工程施工质量验收规范》GB5O2O4-2OI5
17《混凝土结构设计规范》(2015年版)GB50010-2010(2015版)
18《建筑工程绿色施工规范》GB/T50905-20I4
19《建筑工程绿色施工评价标准》GB/T50640-2010
20《建筑机械使用安全技术规程》JGJ33-2012
21《施工现场临时用电安全技术规范》JGJ46-20D5
22《建设工程施工现场消防安全技术规范》GB50720-2011
23《绿色工业建筑评价标准》GB/T50878-2013
24《建筑工程施工质量验收统一标准》GB5O3OO-2O13
25《建筑施工脚手架安全技术统一标准》GB51210-2016
住房城乡建设部令第37
26《危险性较大的分部分项工程安全管理规定》
号/31号文
《山东省建筑工程安全专项施工方案编制审查与专家鲁建质安字(2018)15
27
论证办法》号
《山东省建筑工程安全专项施工方案编制审查与专家
28鲁建管发【2010】4号
论证办法》
地方法规《济南市房屋建筑及轨道交通工程安全专项施工方案
29济建发(2016)18号
编制审查与专家论证实施细则》
《济南市建筑工程安全专项施工方案编制审查与专家济建质安站字[2008]23
30
论证实施细则》号
31《模板支架安全管理十条》济建发[2019]43号
32合同绿地国博城DX-I地块小学项目(EPC)总承包合同/
33设计文件绿地国博城DX-1地块小学项目设计图纸/
34企业标准《建筑施工脚手架安全技术标淮》ZJQ08-SGJB003-2017
35其他PKPM施工软件/
第二章工程概况
2.1总体概况
工程名称绿地国博城DX-1地块小学项目工程性质公建
山东济南市济阳区崔寨镇蔡马村,220
承包方式建筑施工总承包工程地址
国道东侧
总占地面积36551m1总建筑面积15794.92m*
建设单位绿地北展济南置业有限公司支护承包方甲指分包
成都基准方中建筑设计有限公基坑支护设
设计单位山东正元勘察测绘有限公司
司计单位
合格,符合国家及地方相关的验收标
勘察单位山东建勘集团有限公司质且
准;
山东众成建设项目管理
监理单位工期120天
有限公司合同要
求零伤亡、确保济南市级安全文明示范
总承包单位中建八局第一建设有限公司安全
工地、山东省安全文明标准化工地
质量监督单绿色
//
位施二
2.2设计概况
2.2.1工程建筑概况
单体性质层数建筑面积(户)建筑高度(m)
1#(综合教学楼一)公建32692.8412.75
2#(综合教学楼一)公建47026.1820.15
3#(行政办公楼)公建21581.48.85
4#(多功能厅)公建21000.9610.95
5#(风雨操场及餐厅)公建23133.4315.15
6#(换热站)公建1227.246.15
7#(变电站)公建1111.786.15
大门及门卫公建121.095.10
水泥砂浆地面、细石混凝土地面、大理石楼面、防滑地砖防水地面、静
楼地面
电活动地板、静电塑胶地板
顶棚涂料顶棚、铝合金扣板吊顶、矿棉吸声板吊顶、装饰石膏板吊顶
内墙面前防水内墙、水泥砂浆内墙面、矿棉吸声板内墙、防水涂料内墙
装饰装修
外墙涂料外墙面、真石漆外墙面
踢脚面砖踢脚
窗铝合金窗
防水等3+3厚SBS改性沥青
屋面一级防水材料
级防水卷材
防水材1.5厚JSn型防
厕浴间面层材料防滑地砖
料水涂料
100厚挤塑聚苯蒸压加气混凝土砌块
屋面墙体
板蒸压加气混凝土墙板
保温节能
80厚岩棉保温30厚玻化微洙保温砂
外墙门窗框与墙体间隙
板浆
2.2.2高大模板工程概况
根据建办质(2018)31号,搭设高度8nl及以上,或搭设跨度18m及以上,或施
工总荷载(设计值)15kN/m2及以上,或集中线荷载(设计值)20kN/m及以上的混凝
土模板支撑工程超过一定规模的危险性较大的分剖分项工程。
经识别,本工程高支模只分布在5#楼57轴~5-6轴乂5-13轴~5-£轴面层区域;
各梁截面及板厚见后附表,高支模区域板面浇注梁板混凝土浇筑前,下部支撑板面的
模板体系不允许拆除。
高支模(5#楼屋面层板)基本概况
5-1轴~5・6轴X板厚
轴线面积960m2120
5个轴~5正轴(mm)
区
区域梁截面300X700,3(X)X1300,
域搭设高度9.85m面积较大
特点(mm)300X1500,400X1300
说
明基础形式高支模落在2层板上(首层板按高支模要求搭设且高支模完工前不拆除)
周边环境高支模区域周边环境为西面、北面为外脚手架,东面、南面为普通支模架
平
面
位
置
示
意
图
41600
高支模区域图
5-1轴~5-6轴X5-B板厚
区轴线面积960m*120
域轴~54轴(mm)
说
搭设高区域梁截面300X700,300X1300,
明9.85m面积较大
度特点(mm)300X1500,400X1300
平
面
位
置
示
意
图
立
杆
布
置
图
剪
刀
撑
布
置
图
支
模
剖
面
图
2.3工程施工条件
极端最高高气温月最大降水量为504.5mm,一年之
最大雨晟及雨
温度及期42.5°C,约中降水主要集中在六、七、八月份,三
季时间
气限持续1个月个月的降水量占年降水量的65%0
温极端最低极低气温济南地区主要以SSW风向为主,多
建设最大风力、风
温度及期-19.7℃,约年平均风速3.2m/s(1951年7月21日,
地点向及发生时间
限持续10天风向W)
状况
最大雪量及发冬季土的冻结
12月0.44m
生时间深度
周围道路及可现场西侧为220过道,为项目各类材料设备运输的主要路线,北
利用情况侧为已经完工的展厅。东、南侧均为未开发区域。
电力供应情况现场设置4个箱变,满足施工要求。
水资源供应情况现场用水环网已完成。
第三章施工安排
3.1项目管理机构
序管理
姓名职责和权限
号职务
1、履行与业主签订的工程总承包合同与书面承诺。
2、协调好业主、监理、设计、分包等与项目相关各方面的关系。
3、负责高大模板施工所需人、财、物的组织管理与控制。
1项目经理王德才4、负责高大模板分包进度、质量、安全、文明等综合协调。
5、针对高大模板工程实施过程中的重大问题组织专题讨论和方
案论证.处理高大模板分包重大的管理和协调问题.保证高大模板丁
程的有效实施。
1、全面负责项目的技术管理工作,负责高大模板施工方案的编
制和方案的交底。
2项目总工赵海峰2、全面负责高大模板的技术、质量管理、验收。
3、主持项目部例会并根据现场实际工程进度及时调整施工计划,
并进行资源再分配。
1、协助项目经理工作,具体负责物资采购和商务合约管理工作。
2、在项目经理的领导下,对高大模板施工管理的重要或重大决
3商务经理王明
策进行研究,形成决议,并分别予以落实。
3、负责高大模板分包商工作的协调。
1、高大模板施工不出现因项目原因导致的工期一般及以上延误。
2、对高大模板施工总、月、周计划完成情况进行过程记录。
专业3、组织、监督劳务分包进行高大模板施工前技术交底。
4赵纯孟
工程师4、进场安全教育,组织、监督劳务班组,高大模板施工前进行
安全交底,安全隐患整。
5、掌握高大模板工人人员组成及动态,及时协调劳务分包配合
及组织施工。
1、负责工程质量的现场监督检查和高大模板工程的质量验收。
2、负责一般质量隐患的处置,发现严重不合格部位及时报告技
5质量总监相文泽术负责人,并负责处置后的质量验收与评定。
3、对劳务分包和高大模板施工班组提出质量奖罚.
4、质量验收文件的记录与整理。
1、参与高大模板危险源辨识、风险评价与控制策划,参与环境
因素的识别与评价。
2、参与高大模板职业健康安全与环境管理规划、管理方案及技
术措施方案的制定,落实相关责任。
6安全总监罗英琳3、巡回进行高大模板职业健康安全/环境管理检查,对关健特性
参数定期进行监测,发现问题下达整改通知单,并对整改情况进行验
证。
4、负贡高大模板职业健康安全/环境应急准备检查,按应急预案
进行响应
1、负责高大模板工程的物资控制,包括经上级授权对物资供应
商进行评价、实施招标采购、做好进场物资的验证和记录、物资保管、
物资
7张建平标识等。
工程师
2、监督检查桩基分包商自夕亍采购物资的控制。负责不合格物资
的处置和记录。
测量
8樊悦军1、负责高大模板的定位放线。
工程师
3.2项目管理目标
项目管理目标名称目标值
工期120天
质量目标合格
安全目标零存亡、确保济南市级安全文明示范工地、山东省安全文明标准化工地
绿色施工满足6个100%的要求
3.3各项资源供应计划
3.3.1劳务资源安排
施工项目资质开始施工时分包分包商
专业施工队名称建设工期
名称要求间方式选择方式
山东璜淞建筑工程劳务分
模板工程无2020.9.20120天公司选定
有限公司包
3.3.2工程大宗物资供应安排
物资名称采购地点要求进场时间责任人
木模板(2440XI220X12mm)山东分批进场董兴方
木方(50*70*4000mm)山东分批进场茶兴方
钢管(由48.3mmX3.0mm)山东分批进场董兴方
钢管扣件(十字卡、接头卡、转卡)山东分批进场董兴方
U型托(直径38mm,托板厚5mm)山东分批进场董兴方
通长对拉螺杆(614mm)山东分批进场董兴方
3.4施工流水段划分及工艺流程
结构施工阶段分为幼儿园、小学两个区,投入一家施工队伍,因工程工期紧张,、
分别作为单独段组织施工。
3.5工程重难点分析及应对措施
序号重难点分析解决方案资任人
I张建平
高支模面积
模板及钢管等材料进场时加大验收力
约1400m',支模
高支度,确保进场材料的质量,验收由项目部物
高度最高处9.85
模区域施资、质量、工程、技术一同验收,通过后方赵纯孟
米,高支模区域混
工质量可进场,同时加大施工过程中的检查力度,
凝土浇筑质量是
确保施工质量
控制重点
加强安全旁站监督,高支模区域设置专
高支模施工职安全员进行旁站监督。
安全防护是重点,重点检查工人安全防护措施佩戴及使用
作业赵纯孟
2项目处于赶工期情况。
安全防护罗英琳
间,夜间施工时需成立安全检查小组,对高支模区域加强
加强安全防护。巡查与教育。
现场提供足够照明;夜间加班监督旁站。
3.6新技术应用
序号新技术名称应用部位应用要点责任人应用时间
通过网络无线实时
1架体无线监测仪高架支模区域樊悦军2020.10.30
监测架体稳定性
第四章工期计划
工期安排如卜.:
控制点部位控制点项目名称施工时间完成时间
1施工放线2D20.9.202020.9.20
2竖向钢筋绑扎2D20.9.262020.9.29
3外架搭设2020.9.292020930
4支模架体搭设2020.9.312020.10.4
55#楼屋面第一段墙柱模板加固2D20.10.42020.10.6
6岛支模第一段墙柱浇筑2020.10.72020.10.8
7模板支设2020.10.92020.10.11
8梁板钢筋绑扎2020.10.22020.10.13
9高支模验收2020.10.142020.10.14
10混凝土浇筑2020.10.152020.10.16
第五章施工准备与资源配置计划
5.1技术准备
1.根据结构施工图、施工现场条件编制模板工程施工方案。
2.绘制模板加工图和各部位模板安装图。
3.组织有关技术人员精读图纸,对设计图纸中的疑难点进行汇总,并对劳务分包
主要管理人员、班组长进行交底。对施工班组下达书面技术交底、安全交底书。技术
复核和隐蔽验收计划表
序号技术复核复核和隐蔽内容责任人
1测量、定位放线楼层放线(轴线、标高)樊悦军
模板几何尺寸、轴线、标高、预埋件和预留孔位置.、
清扫口留置、施工缝留置、模板消理、脱模剂涂刷、
2模板工程赵纯孟
止水要求;模板支架的材质、构造;后浇带模板的
支设。
钢筋放样、品种、规格、是否带E,连接方式、接
3钢筋工程头位置、搭接长度、锚固方式及长度;构造柱插筋;赵纯孟
后浇带钢筋保护;
混凝土的强度等级、配合比、塌落度、砂石质量、
赵纯孟
4混凝土工程水泥品种和强度等级、外加剂的品种和掺量;高强
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 年终工作总结个人报告(10篇)
- 中专自我鉴定合集15篇
- 标准设备购买合同
- 西安迈科商业中心连体超高层结构设计-龙辉元张晓宇王福安
- 师德师风个人学习心得范文
- 班级建设目标
- 2023六年级语文上册 第八单元 28 有的人-纪念鲁迅有感教学实录新人教版
- 简爱读后感10篇【100-1000字】
- 教师的辞职报告15篇
- 餐厅服务员辞职申请书集锦6篇
- 生产与运作管理第三版课后习题含答案版
- 高频考点之评价与文本互证考题专练-2024年高考语文二轮复习三点突破讲解专练
- 《高铁酸钾的制备》课件
- 上海财经大学《801经济学》历年考研真题及详解
- XX医院临床医疗质量考核通用记录表
- 城市交通枢纽运营故障应急预案
- 料场加工施工方案
- 【浅析人工智能在石油行业中的应用3400字(论文)】
- 专题06课内阅读(解析版)-2021-2022年(两年真题)全国三年级上学期语文期末试卷分类汇编
- 矫治器与矫治技术-常用活动矫治器(口腔正畸学课件)
- (全)外研版丨九年级下册英语各模块作文范文(名校版)
评论
0/150
提交评论