5.1施工前准备工作

5.1Preparations

BeforeConstruction主讲老师:班志鹏

Lecturer:BanZhipeng5.1施工前准备工作PreparationsBeforeConstruction现场施工人员准备Preparationofon-siteconstructionpersonnel装配式混凝土施工现场常规作业人员大幅度减少,但新增了吊装作业人员、灌浆工等,测量放线人员的作业内容也有所变化。所配备的人员应具备装配式建筑施工岗位的基本知识和技能。Fortheprefabricatedconcreteconstruction,thenumberofregularoperatorsaregreatlyreduced,buthoistingoperatorsandgroutingworkersarerequired,andtheworkcontentsofsurveyingandsetting-outpersonnelarechanged.Allpersonnelprovidedshallhavebasicknowledgeandskillsrequiredforprefabricatedbuildingconstructionposts.图5-1装配式建筑现场施工人员

Figure5-1On-sitePersonnelforPrefabricatedBuildingConstructionSitesupervisorDedicatedinspectorGroutingworkerGroutingworkerGroutingworkerPhotographer现场施工道路和场地布置Siteconstructionroadsandsitelayout施工现场现场道路应路面平整,满足大型车辆的转弯半径的要求和荷载要求;有条件的施工现场应设一出一进两个门。Thesiteconstructionroadsshallbeflatandmeettherequirementsforturningradiusandloadsoflargevehicles.Ifconditionspermit,twogatesshallbeprovidedfortheconstructionsite,oneastheentranceandtheotheroneastheexit.现场临时堆放场地,应在起重机作业半径覆盖范围内,地面平整、坚实,有良好的排水措施。场地布置应考虑构件之间的人行通道,方便现场人员作业,道路宽度不宜小于600mm。Thetemporarystorageyardonsiteshallbelocatedwithinthecoverageofthecraneoperatingradius,withflatandsolidgroundandgooddrainagemeasures.Forsitelayout,pedestrianpassagewaysbetweencomponentsshallbereservedfortheoperationconvenienceofon-sitepersonnel,andthewidthshouldnotbelessthan600mm.图5-2装配式建筑现场布置

Figure5-2LayoutofPrefabricatedBuildingConstructionSite图5-3构件堆场

Figure5-3ComponentStorageYard5.1施工前准备工作PreparationsBeforeConstruction起重机械设备和吊具准备Preparationofcranesandhoistingtools选择吊装主体结构预制构件的起重机械时,应注意以下事项:Pleasepayattentiontothefollowingswhenselectingcranesforhoistingprefabricatedcomponentsofthemainstructure:(1)起重量;

(1)Hoistingcapacity;(2)作业半径;(2)Operatingradius;(3)力矩应满足最大预制构件组装作业要求;(3)Themomentshallmeettherequirementsfortheassemblyofthemaximumprefabricatedcomponent;(4)最大起重量不宜低于10t;

(4)Themaximumhoistingcapacityshouldnotbelessthan10t;(5)提升或下降速度应满足预制构件安装和调整的要求;(5)Thelifting/loweringspeedshallmeettherequirementsfortheinstallationandadjustmentofprefabricatedcomponents;(6)塔吊应具有安装和拆卸空间。(6)Thereshallbespacefortheinstallationanddisassemblyofthetowercrane.5.1施工前准备工作PreparationsBeforeConstruction起重机械设备和吊具准备Preparationofcranesandhoistingtools根据预制构件的运输路径和起重机施工空间等要素,决定采用移动式起重机还是固定式的塔式起重机。Theselectionofcranetype(mobilecraneorfixedtowercrane)shoulddependonthetransportationpathofprefabricatedcomponentsandtheconstructionspaceofthecrane.图5-4履带吊

Figure5-4CrawlerCrane图5-5汽车吊

Figure5-5TruckCrane图5-6塔吊

Figure5-6TowerCrane5.1施工前准备工作PreparationsBeforeConstruction预制混凝土构件常用到的吊具主要有起吊扁担、专用吊件等,吊具的选择必须保证构件不变形,不损坏,起吊后不转动、不倾斜、不翻倒。Hoistingtoolsgenerallyusedforhoistingtheprefabricatedconcretecomponentsmainlyincludecarryingpoles,specialhangers,etc.Hoistingtoolsshallbeproperlyselectedtoensurethatthecomponentwillnotdeformorgetdamaged,andwillnotrotate,tiltorturnoverafterbeinghoisted.图5-7起吊扁担

Figure5-7CarryingPole图5-8吊装框架

Figure5-8HoistingFrame图5-9吊具

Figure5-9HoistingTools5.1施工前准备工作PreparationsBeforeConstruction起重机械设备和吊具准备Preparationofcranesandhoistingtools施工组织准备Preparationforconstructionorganization施工组织设计除了普通现浇混凝土该有的内容外,应根据工程总工期,确定装配式建筑的施工进度、质量、安全及成本目标;需要明确的结构吊装施工和支撑体系施工方案,确定预制构件的施工衔接原则和顺序;在编制施工方案时,应考虑与传统现浇混凝土施工之间的作业交叉,尽可能做到两种施工工艺之间的相互协调与匹配。Inadditiontothenecessarycontentsofordinarycast-in-situconcrete,theconstructionorganizationdesignshalldeterminetheprogress,quality,safetyandcostobjectivesofprefabricatedbuildingconstructionaccordingtothetotalconstructionperiodoftheproject;clarifytheconstructionschemesofstructurehoistingandsupportsystems;anddeterminetheconstructionlinkingprincipleandsequenceofprefabricatedcomponents.Whenpreparingtheconstructionscheme,thecrossoperationwithtraditionalcast-in-situconcreteconstructionshallbeconsidered,andthecoordinationandmatchingbetweenthetwoconstructionprocessesshallbeensuredasfaraspossible.图5-10施工进度图

Figure5-10ConstructionSchedule图5-11施工工艺模拟

Figure5-11ConstructionProcessSimulation5.1施工前准备工作PreparationsBeforeConstructionMasterScheduleforSteelStructureHousingGroupProject

inJiuliResettlementArea(EastZone2)inFuyangCity施工安全技术交底Disclosureofconstructionsafetytechnologies装配式混凝土建筑施工安全风险源有:吊装构件大、重;高空作业频繁;临时构件固定、校正;吊装技术要求高等。参与作业的所有人员应进行系统、全面的安全培训。作业各个环节都应编制安全操作规程,在施工前应进行书面安全技术交底。Safetyrisksofprefabricatedconcretebuildingconstructionmainlycomefrom:hoistingoflargeandheavycomponents;frequentlyworkingatheights;fixingandcorrectionoftemporarycomponents;highrequirementsforhoistingskills.Alloperationpersonnelshallreceivethesystematicandcomprehensivesafetytraining.Safetyoperationproceduresshallbepreparedfor

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论