CSPCNANHAIPETROCHEMICALSPROJECTCSPC南海石化项目WorkingInstruction

OfCoolingWaterPipelinesInstallation循环水管道安装作业指导书ProjectProcedure:WI-8710-8100-2005项目程序:WI-8710-8100-2005SEPCOElectricalPowerConstructionCorporation山东电力基本建设总公司版次日期出版原因编写校核审查批准A17July03IssueForReviewAndApprovalDiaoyanhuaLiHongJuChenHuiYouDingPeiSheng0031August03IssueforimplementationDiaoyanhuaLiHongJuChenHuiYouDingPeiSheng0127October03ReissueforimplementationLiudongxianTiandexunZhaoxieShideping0215November03ReissueforapprovalLiudongxianTiandexunZhaoxieShideping0328November03ReissueforapprovalLiudongxianTiandexunZhaoxieShideping目录contents1.0范围scope32.0目的purpose33.0职责responsibility34.0概述general35.0编制依据reference46.0施工工艺及要求constructionprocessandrequirement47.0程序升版说明updatedescription178.0附图attacheddrawing179.0工作安全分析(JSA)17范围scope本程序适用于南海石化项目汽电联产部分,四台蒸汽轮机循环冷却水管道(CW)安装、检验和试验。ThisprocedureisapplicabletotheCWpipes’erection、inspectionandacceptance.2.0目的purpose本程序规范循环水管道的安装、检验和试验,规定了管道的安装工艺、顺序以及施工中应注意的事项。Thisproceduredefinesthepipes’erectionprocess、flowandattenteditemstoensuringpipes’erection、inspectionandacceptance.3.0职责responsibility3.1山东电建二公司负责循环冷却水(CW)玻璃钢管道的安装、检验和试验。SEP2isresponsiblefortheerection,inspectionandacceptanceoftheGRPCWpipe.3.2山东电建一公司负责循环水管道的管沟开挖。SEP1isresponsibleforthepipechannel’sexcavation.3.3基建总公司负责接口协调和质量验收。SEPCOisresponsiblefortheinterfacecoordinationandqualityinspection.4.0概述general4.1厂区位于大亚湾北海岸附近,地下水位在地表1.5米,循环水母管管中心标高为3.35mHHD。TheS&PprojectlocatesattheroundofnorthcoastofDayabay.Theundergroundwaterlevelisat1.5moftheearth’ssurface.Thecentralelevationofcentralcoolingwatermainpipeis3.335mHHD.4.2循环冷却水管道(CW)采用玻璃钢夹砂管,刚度为SN5000,设计压力为0.8MPa,介质为淡水,设计温度为80℃;工作压力为0.464Mpa;输送介质为河水,水温为34℃~42℃。ThecoolingwaterpipesareGRPpipe,whichstiffnessisSN5000,andthedesignpressureis0.8Mpa.Thepipesusefreshwater,thedesigntemperatureis80℃,theworkingpressureis0.464Mpa;thetransfermediumisriverwater,andtheworkingtemperatureis34℃~42℃.4.3循环水管道埋设在地下,主管为变截面设计,规格有DN2000、DN1500、DN1000,支管为DN800、DN600、DN200。另有少许DN100、DN40、DN15放水排气管道。进口主管长度约200米,出口主管长度约250米。ThemainpipesofCWpipeswhichareundergroundarevariablecross-sectionpipes.Themainpipes’sizesareDN2000,DN1500andDN1000andthebranchareDN800,DN600andDN200.TherearealsosomedrainagepipeswhichsizesareDN100,DN40,andDN15.Thelengthoftheinletpipeisabout200mandtheoutletisabout250m.4.4DN>200mm的管道间采用双”O”型带锁紧承插接头连接,短接管、支管和主管的连接采用现场开孔、粘结的方法;DN≤200mm的管道采用套管对接并粘结的连接方法。 Thepipeswhichdiameterismorethan200mmarejoinedbydoubleOtightsocket,Thenipple、mainandbranchpipesarejoinedthroughtappingorbonding.Thepipeswhichdiameterislessthan200mmarejoinedbysleevejointorbuttfelt.4.4汽机房两侧的循环水管道上侧路面为混凝土铺设的路面。Theupsideroad’ssurfaceofCWpipeonbothsidesofturbinehallisconcrete.5.0编制依据reference5.1DEP31.40.10.19《GRPpipelinesandpipingsystems》5.2GB50268-97《给排水管道工程施工及验收技术规范》GB50268-97Supplyanddrainagepipeconstructionandacceptancetechnicalspecification.5.3QC-8420-8300-0002《循环水管道安装质量检验计划》QC-8420-8300-0002Coolingwaterpipelineerectionqualityinspectionplan5.4施工图纸constructiondrawing51-8230-8100-300051-8230-8100-3002~300551-8230-8100-3006(1/2)51-8230-8100-3006(2/2)51-8230-8100-3007~301044-8320-8100-0559~056144-8320-8100-0600~06105.5CECS129:01《埋地给水排水玻璃纤维增强热固性树脂夹砂管管道工程施工及验收》Embeddedsupplyanddrainglassfiberreinforcedheathardeningresinsandpipeconstructionandacceptance5.6厂家资料《纤维缠绕玻璃钢管安装埋地手册》Manufacturerdocument:《GRPpipelayingmanual》6.0施工工艺和要求constructionprocessandrequirement6.1循环水管道安装的施工工艺流程图:flowchartforCWpipeerection运输管子、管件到现场transportpipeandfittingtosite沟槽开挖、验收trenchexcavationandacceptance施工准备constructionpreparation运输管子、管件到现场transportpipeandfittingtosite沟槽开挖、验收trenchexcavationandacceptance施工准备constructionpreparation管沟回填trenchbackfill管道安装pipeerection承插口打压试验hydraulictestforbellandsocket管沟回填trenchbackfill管道安装pipeerection承插口打压试验hydraulictestforbellandsocket管道整体打压试验overallhydraulictestforpipe路面铺砌roadpavement全部回填overallbackfill管道整体打压试验overallhydraulictestforpipe路面铺砌roadpavement全部回填overallbackfill6.2主要机具tools6.2.1主要机具:16t汽车吊、50t汽车吊、潜水泵、手动试压泵、电动试压泵。Maintools:16ttruckcrane、50ttruckcrane,submergedpump,manualpump,motorpump6.3施工准备Installationpreparation6.3.1施工前仔细审阅图纸,熟悉系统。Reviewdrawingscarefullybeforeconstruction.6.3.2了解规范和标准的要求,掌握质量要求和验收标准,签质量检验计划。Understandtherequirementofspecificationandstandard,andmasterqualityrequirementandacceptancecodeandissueI&TPlan.6.3.3对施工人员进行安全、技术交底。Makesafetyandtechnologyclarificationtotheconstructionpersonnel.6.3.4沟槽验收channelacceptance管沟截面尺寸符合图纸51-8230-810-3002。Thesectionsizeofpipechannelapplieswithdrawing51-8230-810-3002.垫层厚度符合设计要求(150mm),并夯实(夯实程度为95%SPD);垫层应平整,用水准仪每12米检测一次垫层的标高。Thepipesandbeddingmeetdesignrequirements(150mm)andramdown.(Theramextentis95%SPD).Smooththecushionandchecktheelevationofcushionatevery12metersbyusingoflevel.管沟无滑坡、积水、淤泥。由于开挖深度超过地下水位,应设置临时排水沟或集水坑。Thereisnoslipslope,seeperandsiltofthetrench.Astheexcavationdepthisoverundergroundwaterlevel,setuptemporarydrainditchandsumppit.承插口安装处的凹槽开挖完毕,凹槽尺寸符合设计要求,以便于整个管身底部放在砂垫层上,均匀受力。Theexcavationofthejointgrooveiscompletedandthegroovesizemeetsdesignrequirements.Thus,placethebottomofpipeonthesandcushiontobearforceevenly.弯头、三通、变径管、盲端、阀门等处的固定支墩充分凝固并安装完毕,符合设计要求。Thefixedpiersattheelbow,tee,reducingpipe,pipeendsideandvalveshouldbehardenedfullyandcompletederectingtomeetingdesignrequirement.6.3.5管道的运输及现场布管pipetransportationandlayingatsite装卸时须使用专用的吊装索具(纤维绳),防止碰损。运输时应垫稳、绑牢,不得相互撞击,在运输到现场过程中要有技术管理人员监护。Whenloadingandunloading,specialslingsshouldbeusedtopreventdamage.Thepipeshouldbesteadyandboundfirm.Itisnotallowedtofouleachother.Atechnicalmanagementpersonmustmonitorthetransportation.由于管道安装为逆水流方向安装,因此将管子、管道连接附件等依次沿一侧管沟摆放。特别注意应将每根管的承口朝向设计水流相反的方向。管道安装的详细顺序见附图1Asthepipeerectiondirectionisthereversecurrentdirection,thepipe,fitting,etc.shouldbeputalongonesideofthechannel.Payspecialattentiontothebelldirection.Itshouldbeexposedtotheoppositedirectionofthecurrent.Thedetailsequenceofpipeerectionseesattacheddrawing1.检查管材、管件的合格证,对管材的规格、配合尺寸、外观等进行全面检查。Checkthecertificateoftubesandpipemeterials.Finalcheckthespecification,matchingsizeandappearance.管道存放时应均匀支撑,防止管材变形、碰损。Thepipeshouldbesupportedevenlywhenplacingtopreventdeformationanddamageofthetubes.6.4管道安装pipeerection6.4.1根据施工顺序及现场情况,吊车的摆放及行走路线见附图1。Accordingtotheconstructionsequenceandsitecondition,thearrangementofthecraneandtravelingrouteseeattacheddrawing1.6.4.2根据管道布置图和管道的安装方向,将第一根要安装的管道用起重机缓慢吊入到管沟内,开始安装。Accordingtothepipearrangementdrawinganderectiondirectionofthepipe,liftthefirstpipetobeerectedslowlybycranetothetrench,thenbegintoerect.安装前应对管道进行复查,无标志、无编号或有缺陷者须查清修补后方可使用;承插口、橡胶圈应进行清理,不得有泥沙等杂物黏连。Reviewthepipebeforeerection.Thepipewithoutdesignation,numberandwithdefectcouldbeusedafterrepair.Cleanthebellandsocketandrubberring.Nosilt,etc.shouldadhere.用水准仪检查管子的标高,标高偏差值值应在+30mm与-30mm之间。Checktheelevationofthepipebywaterlevel.Thetoleranceshallbewithin+30mm/-30mm.用线坠检查管子的坐标,坐标偏差值应在+30mm与-30mm之间。Checkthecoordinateofthepipebywiregauge.Thetoleranceshallbewithin+30mm/-30mm.6.4.3然后,安装下一节管道。连接前检查承口和插口,在承口上安装打压嘴。Then,erectnextpipe.Checkthebellandsocketbeforeconnectinganderectnozzleonthebell.复查承口内是否光滑,有无纵向的沟槽或直径超过1.5mm的气泡,如发现有沟槽或直径超过1.5mm的气泡,应在厂家技术人员指导下修复。。Reviewwhetherthesurfacewithinthebellissmoothandwhetherthereisanylongitudinalditchorairbubblewithdiameterover1.5mm.Anylongitudinalditchorairbubblefoundshallberepairedunderthedirectionoftechnicianfrommanufacturer.复查插口,其外表应光滑,无突出处。“O”型圈槽的台阶及端面应无分层现象。如有则应在厂家技术人员指导下修复。Reviewwhetherthesurfaceofthesocketissmoothandwhetherthereisanyprotrusion.ThestepandendfaceofOrubberringmustnothaveanydelaminationphenomenon.Thedelaminationifanyshallberepairedunderthedirectionoftechnicianfrommanufacturer.复查“O”型橡胶圈,橡胶圈应无裂纹、气泡、疙瘩、杂质等。如有则应更换“O”型橡胶圈。Reviewwhetherthereisanycrack,airbubble,knobandforeignmatterontheOrubberring.Replacetheringifanyoftheaboveisfound.6.4.4将要连接的管段插口和承口调平、对中,清理连接区、环槽,并均匀涂上一层润滑油,然后将“O”型圈套在插口环槽内,在“O”型圈套上也均匀涂上一层润滑油。Adjustandalignthesocketandbelltobeconnected.Cleanjointingareaandringchannel.Coatalayeroflubricationevenly.PutOringtotheringchannelofthesocket.CoatalayeroflubricationonthesurfaceofOringevenly.6.4.5管道吊入管沟内后,用龙门架(龙门架制造图见附图2)和手拉葫芦等工具进行管口对接。管沟内设专人指挥将插口对准前一管的承口,调整两管在同一直线上,用两只倒链对称拉紧,将待安装的管道拽进已安装的管道承口内。Afterthepipeislifttotheditch,joinbygantryframe(seeattachmentdrawing2)andchainblock.Aspecialpersonshouldbeassignedtodirectthejoin.Adjusttwopipesonthesameline.Tightensymmetricallywithtwochainblocks.Dragthepipetobeerectedintotheerectedbell.通常在插口上画出深度限位线。安装时,只需将插口拉进到限位线即可。Generally,drawthedepthlimitinglineonthebell.Itisonlyneedtopullthesockettothelimitinglinewhenerection.检查管道的标高、坐标。Checktheelevationandcoordinateofthepipe.检查承插口接头的转角,不得大于下表中的规定:Checktheturningontheconnectionofthebellandsocket.Thevalueoftheturningshouldbenomorethanthebelow.管道直径Pipediameter(mm)许用转角Allowableturning(°)管道偏移量(mm)Pipedeviation管道曲率半径(m)Pipecurvatureradius3m6m12m3m6m12m<500315731462857115229500—900210520941986172344900--1800152105209172344688>18000.526527834468813766.4.6承插口打压试验,检查双"O"型密封圈的密封效果。Whenmakingbulgetestonthebellandsocket,checkthesealonthedoubleOsealingring.如承口上的打压嘴在管道正上方,按照下列图示连好装置,加水打压至管道设计压力的1.5倍(12bar)。Ifthebulgemoutherectedonthebellandsocketisdirectlyaboveonthepipe,erectequipmentsaccordingtotheabovedrawing.Wateringuntilthepressurereach1.5timesofthepipedesignpressure(12bar).如承口上的打压嘴不在管道正上方,按照下列图示连好装置,加水打压至管道设计压力的1.5倍(12bar)。Ifthebulgemoutherectedonthebellandsocketisnotdirectlyabovethepipe,erectequipmentsaccordingtothedrawingbelow.Wateringuntilthepressurereach1.5timesofthepipedesignpressure(12bar).试验介质采用洁净的水。Thetestmediumusecleanwater.保压10分钟,根据压降情况和泄漏情况检查承插口的压密性。Keepthepressurefor10minutes.Checkthetightnessofthebellandsocketaccordingtothepressuredropandleakage.如果承插口水压试验时不合格,须将不合格管段退出,重新进行安装、试验。退管应在厂家技术人员的指导下进行,防止退管时损坏管道承插口。Ifthebellandsocketisnotqualifiedwhenhydraulictest,dropouttheunqualifiedpipesection.Erectandtestagain.Pipewithdrawingshouldbedoneunderthemanufacturer’stechnicianinstruction.Bellandsocketofthepipeispreventedtobedamagedwhenpipewithdrawing.试验完毕进行泄压,因水量很少,直接排出少量水即可。Relievepressureaftertest.Dischargesomewaterdirectlyfortheamountofwaterisnotmuch.6.4.7试验合格后,通过承口端的锁紧棒的穿孔插入尼龙棒,通过尼龙棒的抗剪切能力来抗管道产生的轴向应力,插入前要在尼龙棒上均匀涂上润滑油,不得有泄露,通过承口上的插入孔,向内挤压尼龙棒,注意应保证尼龙棒始终沿插口的切线方向推进,在推进的过程中要均匀用力,防止尼龙棒折断。直到规定的长度完全插入。Afterthetestisqualified,insertthenylonbarthroughtheholeofthelockingrodonthebell.Usetheshearresistantabilitytoresisttheaxialstressarousedbythepipe.Thenylonbarshouldbecoatedlubricationoilevenlybeforeinsertion.Noleakageisallowed.Squeezethenylonbarthroughtheinsertholeonthebell.Payattentiontoensurethenylonbarshallbepushedalongtangentdirectionofthebell.Forceevenlywhenpushingtopreventthenylonbarbreakingtillthespecifiedlengthinsertcomplete.6.4.8上述工作完成后立即回填,承插口处应预留。管区采用分层回填,回填要求应符合GB50268-97《给排水管道工程施工及验收技术规范》及图纸51-8230-8100-3002上的要求。Backfillimmediatelyafterthecompletionoftheabovework,thesocketlshallbeobligated.Layeringbackfillshallbeadopted.BackfillrequirementsshallapplywithGB50268-97Supplyanddrainagepipeconstructionandacceptancetechnicalspecificationanddrawing51-8230-8100-3002.6.5部分主管和支管的连接采取现场开孔、粘结的连接方法,黏结处整体水压试验前不可回填,黏结工作由厂家技术人员完成,黏结时应考虑天气对黏结工作的影响,并要有防尘保护措施。胶结过程应在2小时内完成。由厂家检测黏结质量。黏结部位待整体水压试验合格后进行回填,。Theconnectionofthemainpipeandbranchusesitetappingandbonding.Nobackfillisallowedbeforeoverallhydraulictestofthebonding.Bondingworkshallbedonebytechnicianfrommanufacurer.Considertheinfluenceoftheweathertothebondinganddustprotectionmeasuresshouldbetaken.Cementingshouldbefinishedwithin2hours.Backfillaftertheoverallhydraulictestisqualified.6.6阀门的安装Erectionofvalves6.6.1阀门到货后应对阀门进行全面检查,厂家资料应齐全,表面无沙眼,操作机构灵活,水压试验合格。Carryoutanoverallinspectionafterthearrivalofvalves.Manufacturer’sdocumentshallbecomplete.Thereisn’tanyairpocketonthevalvesurfaceandtheoperationalpartshallbeflexible.6.6.2阀门搬运时不得损坏阀门,应按厂家要求储存阀门。Donothurtvalvesduringtransportation.Storethemaccordingtomanufacturerrequirements.6.6.3阀门安装根据介质流向确定其安装方向。Determinetheerectiondirectionaccordingtothemediumflowdirection.6.6.4检验阀门安装的支撑,确定牢固后进行阀门的安装,阀门的安装位置应准确无误。Inspectthesupportofvalveerectionandmakesureitisfirm.Theerectionpositionofthevalveshouldbecorrect.6.6.5阀门的垫片应平整,表面光滑,如表面有气泡、沟槽,应更换合格垫片。Thevalvegasketshallbeflatandsmooth.Anygasketwithairbubbleorditchchannelonthesurfaceshallbereplaced.6.6.6阀门安装前应清理干净,自然连接,无强力连接。Beforeerection,valvesshallbecleanedupandtheconnectionshallbenaturely,withoutanyforcedconnection.6.6.7将安装上的阀门进行调整,调整合适后将底角螺栓进行浇灌,固定阀门。Adjusttheerectedvalvesandthenpourthebaseboltstoanchorvalves.6.6.8检查阀门的操作机构,操作机构应灵活准确,无卡涩现象。Inspecttheoperationalpartofvalve.Makesureitisflexiblyandprecise.Noblockandunsmoothexist.6.6.9转矩限制机构的保护动作准确、可靠。开度指示机构指示位置应正确。Protectionactionoftorquelimitmechanismshallbecorrectandreliable.Thedenotingpositionoftheopeningdenotingmechnismshallbecorrect.6.7过路管的安装erectionofthepipecrossingroad6.7.1管道过路采用C20混凝土包层对玻璃钢管道进行保护。GRPpipeshouldbeprotectedbyC20concretecladwhenthepipeiscrossingtheroad.6.7.2安装过路管时,须在玻璃钢管外表面缠上橡胶板或垫板作保护材料,同时在路的另一侧设置一固定钢支架,将倒链或紧绳器将玻璃钢管从混凝土包层内拉出,然后按正常连接方法将管道连接。Whenerectingthepipecrossingtheroad,twistrubberplateorbackplateontheoutsidesurfaceoftheGRPpipeasprotectionmaterial.Atthesametime,setafixedsteelsupportontheothersideoftheroad.DrawtheGRPpipefromtheconcretecladusingchainblockoreuphroe.Thenconnectthepipeusingthenormalconnectingmethod.6.7.3管道和混凝土包层间应采用水泥砂浆进行填充,填充时的最大灌浆压力不得大于0.54bar。Fillthespacebetweenthepipeandtheconcretecladusingcementmortar.Themaximumgroutingpressureshouldbenomorethan0.54barwhenfilling.6.8 管道法兰安装erectionofpipeflange6.8.1法兰安装前,应检查法兰的压力等级、规格、尺寸等参数是否符合设计要求,厂家资料应齐全。Checkwhetherthepressureclass,specificationandsizeoftheflangemeetthedesignrequirementbeforeerection.Manufacturer’sdocumentshallbeallcomplete.6.8.2 对检查法兰的密封面及密封垫片进行外观检验,不得有影响密封性能的缺陷存在。Checkthesealingsurfaceandsealinggasketoftheflangevisually.Nodefectaffectingsealingperformanceexists.6.8.3检查法兰端面的垂直度,偏差不大于1mm。Checktheverticalityoftheflangeend.Thedeviationshouldbenomorethan1mm.6.8.4搬运法兰不得碰坏法兰的接触面,应按生产厂家的要求进行存放。Theflangeinterfacemustnotbecollidedduringtransportation.Flangestorageshallmeetthemanufacturer’srequirements.6.8.5法兰连接应保持同轴,并使用同一规格螺栓、螺母,安装方向应一致,紧力均匀,并应露出2~3扣,螺纹处涂二硫化钼。Theflangeconnectionshouldkeeponthesameaxleandusetheboltwithsamespecificationandsameerectiondirection.Tightensymmetricallyandevenly.Theextrusionlengthofthescrewshouldbe2-3timesofthepitch.Supramolyshallbecoatedonthescrewthread. 现场水压试验hydraulictestonsite管道在试验前应具备下列条件:Thefollowingconditionsshouldbeavailablebeforetest:管道的坐标、标高、坡度检查合格,除黏结处及承插口处露外,回填完毕。Thecoordinate,elevationandslopeofthepipeshouldbecheckedqualified.Backfillcompleteexceptthebondingconnectionandtheexposurepartofsocket.所有支管设置好堵板。Closureplateshallbeequippedforallbranchpipes.管道内部杂物清理干净。Cleantheinnersundriesinsidethepipe.管道系统上不参与试压的设备、仪表、阀门等隔开,不得有安全阀、水锤消除器等附件。Blockofftheequipment,instrumentandvalvewhicharenotinvolvedinthetest.Noattachment,suchassafetyvalve,waterhammerandsilencerexist.试验用临时管道、阀门及压力表等安装完成,试验用压力表采用Y-150型,精度不低于1.5级,使用前应校正。Theerectionoftemporarypipe,valveandmanometerfortestarecomplete.UsethepressureguageofY-150.Theprecisionofthemanometerisnolessthan1.5degree.Adjustitbeforeuse.试验段两端封闭完成,不得采用闸阀作为堵板。临时排水管道完成。Afterthebothendsofthetestsectionarefinished,itisnotallowedtousewedgevalveasplug.Temporarydrainagepipeiscomplete.管件的支墩、锚固设计已经达到设计强度,未设支墩及锚固设施的管件,应采取加固措施。Thepierandanchorofthepipeisuptothedesignstrength.Reinforcementmeasuresshouldbetakenforthepipewithoutpierandanchor.注入试验用水:waterfortestfilling试验用水用Ф100的软管从距试验点最近的水源取水。ThewaterfortestisgotfromthenearestwatersourcefromthetestpointbyФ100hose.充水时为防止水锤冲击,应缓慢充水,充水速度约为0.6m/s,最大不超过1.8m/s。此时,应打开管道高处的排气阀1,待水灌满后,关闭排气阀和进水阀。Fillslowlytopreventwaterhammerstrikingduringwaterfilling.Thefillingspeedisabout0.6m/sandnotover1.8m/s.Atthistime,openeachhighventvalveonthepipe,Closetheventvalveandinletvalvewhenthewaterisfilledfull.将管道进行充分浸泡,浸润时间为24小时。Soakthepipecompletelyfor24hours.用电动试压泵试压,压力逐渐升高,加压到一定数值时,停下来对管道进行检查,无问题时继续加压,升至试验压力的时间不得小于1小时,以减少冲击力。水压试验用于检验管道的强度,试验压力为1.5倍的设计压力(12bar)。Testthepressurebymanualhydraulictestpumpormotortestpump.Thepressurewillbeincreasedgradually.Whenthepressurereachesacertainvalue,stopandcheckthepipe.Ifthereisnoproblem,increasethepressurecontinually.Thetimeforpressureincreasingtothetestpressureisnolessthan1hourthustodecreasetheimpactforce.Thehydraulictestisusedtotestthestrengthofthepipe.Thetestpressureis1.5timesofthedesignpressure(12bar).用泵加压至工作压力(4.64bar)时,暂停打压,检查管道有无泄漏。如无泄漏,继续升压到试验压力,保压30分钟,检查接口、管身及压力表等部件无破损及漏水现象时,如在试验温度下观察10分钟,下降压力值不超过0.05Mpa,可认为合格。特别是三通、四通等现场粘结的附件,应检查位置是否偏移、有无超过验收标准规定的可见缺陷。Whenthepressureisincreasedtotheworkingpressurebypump(4.64bar),stopandchecktheleakageofthepipe.Ifthereisnoleakage,increasethepressurecontinuallytothetestpressure.Keepthepressurefor30minutes.Checktheconnection,pipebodyandmanometer.Ifitisobservedfor10minundertesttemperatureandthepressurereduceiswithin0.05Mpa,thenitisconsideredeligible.Whencheckingtheteeandcross,checktheobviousdefects,suchasdeviationandoverthestatementoftheacceptancestandard.水压试验合格后,可进行管道严密性试验,用于检验管道的严密性。Afterthehydraulictestisqualified,makeleakagetestofthepipetochecktheleakage.严密性试验压力为1.1倍的设计压力Thepressureforleakagetestis1.1timesofthedesignpressure.保压时间不少于24小时,符合渗水量的标准可认为合格。渗水量标准见下表:Thetimeforkeepingthepressureshouldbenolessthan24hours.Itcannotbeconsideredeligibleuntiltheseepagestandardreaches.Theseepagestandardseethebelow:渗水量试验管径(mm)pipediameterforseepagequantitytest管道水压试验允许渗水量(L/min•Km)Allowableseepageforpipehydraulictest检验方法和器具Checkmethodandinstrument1001.40按GB50268进行。Accordingtothearticle64inGB502682001.986003.448003.9610004.4215005.0020006.26试验过程中,每30分钟记录一次管道压力。Recordthepipepressureevery30minutesduringtest.6.9.5水压试验完毕后,将进水管上阀门关闭,打压用水不再排出。Afterthehydraulictestiscomplete,closethevalveontheinletpipe.Thewaterforthehydraulictestwillnotbedrained.6.9.6水压试验时,用专用堵头封住试压段的两端,并和支撑贴紧,以防止打压时管道沿轴向位移。Closethebothendsofthehydraulicsectionwithspecialplugwhenhydraulictestingandkeepclosetothesupporttopreventthepipedisplacingalongtheaxialdirection.6.9.7如果进行严密性试验时,试验压力下降,那么可以采用下列方法决定管道是否严密:Ifthetestpressuredropswhenmakealeakagetest,determinewhetherthepipeistightusingthefollowingmethod:试验段打压至试验压力(1.1倍的设计压力)后,每个小时记录试验压力。如果压力下降,采用补充水后重新加压至试验压力。这样通过补水重新打压的方法保持24小时。Afterthepressureofthetestsectionreachesthetestpressure(1.1timesofthedesignpressure),recordthetestpressureeachhour.Ifthepressuredrops,increasethepressureagaintothetestpressurebyrefillingwater.Thismethodshouldbeusedwithin24hours.如果发现的每小时补水数量逐渐减少,应观察补水量是否符合以上规定,如符合,那么就可以认为管道严密;如果不符合,那么可以认定管道不严密。Ifitisfoundthatthequantityofrefillingwaterisdecreasinggradually,observewhetherthequantityofrefillingwatermeettheabovestatement.Ifso,thepipeisconsideredtight.Ifnot,thepipeisconsiderednottight.6.9.8水压试验合格后进行整体回填并夯实,发现问题应及时处理,处理完毕重新进行试验,只到水压试验合格为止。Afterthehydraulictestisqualified,makeanoverallbackfillandramdown.Treatwiththeproblemfoundintime.Thenmakeahydraulictestagaintillthetestisqualified.7.0附图。Attacheddrawing8.0工作安全分析(JSA)附后。JSAisattachedbelow.DrawingDrawing:1附图:1UNIT:mm单位:mm15000InstallOrderFromWestToEast安装顺序由东向西15000150001500015000InstallOrderFromWestToEast安装顺序由西向东15000CraneTravelAndPutLine吊车行走及摆放路线CraneTravelAndPutLine吊车行走及摆放路线constructioninceptdrop施工起始点CraneTravelAndPutLine吊车行走及摆放路线InstallOrderFromNorthToSouth安装顺序由北向南InstallOrderFromSouthtoNorth安装顺序由南向北UNIT:mm单位:mm15000InstallOrderFromWestToEast安装顺序由东向西15000150001500015000InstallOrderFromWestToEast安装顺序由西向东15000CraneTravelAndPutLine吊车行走及摆放路线CraneTravelAndPutLine吊车行走及摆放路线constructioninceptdrop施工起始点CraneTravelAndPutLine吊车行走及摆放路线InstallOrderFromNorthToSouth安装顺序由北向南InstallOrderFromSouthtoNorth安装顺序由南向北200030002500200030002500AJOBSAFETYANALYSIS工作安全分析Date(日期):JobTitle工作名称:PipeTransportation管道运输Location地点:Jobsite施工现场JSANoJSA编号:DEPARTMENT部门:汽机工程处SUPERVISOR主管人:TITLEOFPERSONWHODOESJOB工作执行人职务:PREPAREDBY编制:REVIEWEDBY审查:APPROVEDBY批准:EnvironmentalConditions:环境条件Inside内部Outside外部Cold冷Heat热Wet湿Dust灰尘Vapors/Mist水汽Noise噪音Vibration震动Other其它HeavyRain大雨PrimaryJobFunctions&Position基本工作行动Lifting举重Grasping抓取Pushing推Sitting座Reaching延伸Bending弯曲Kneeling跪Standing直立Pulling拖Squatting蹲Other其它SEQUENCEOFBASICJOBSTEPS工作步骤POTENTIALHAZARD潜在危险风险评估RAM(H、M、L)RECOMMENDEDACTIONORPROCEDURE控制行动措施ACTIONBY执行人DATEDUE完成日期REMARK备注Controlofdriver驾驶人员的控制Specialinjurycausedbycollisionorupsetofvehicle由撞车、翻车等引起的特殊伤害Mdrivershallundertakehisworkwithhislicense.hemusthavemuchexperienceondriving.itisstrictlyprohibitedtodrinkduringtransportation.车辆驾驶人员要持证上岗,并且驾驶经验丰富,驾驶人员在运输过程中,严禁饮酒.Requirementfortransportvehicle运输车辆的要求Injurebymovingvehicle车辆移动伤害Ltransportationvehiclemusthavegoodsafetyperformance.运输车辆车况安全性能必须良好,Pollutionduetooilspill车辆露油造成环境污染Lleakageisstrictlyprohibited.严禁有泄露现象的发生。Pipeenclose管道的封闭Strikingagainstorstruckbymovingobject移动物体打击Mitisnotallowedtomovevehicleduringpipeenclose.donotcastfastenrope.管道封闭过程中,车辆严禁移动。封车绳不可抛扔。Pipeslideduetounstableenclose管道封闭不牢滑落Lafterloadingonpipes,enclosepipesecurelyinthetruck.checktheropeconditionattimes.管道应封车牢固,运输过程中要定时检查。Traveloftransportationvehicle运输车辆的行驶Injurebymovingvehicle车辆移动伤害Lthespeedoftransportationvehiclecannotexceed30km/handcannotexceed15km/hafterenteringjobsite.运输车辆在行驶的过程中,车速不得超过30公里/小时,进入现场车速不得超过15公里/小时。Controlofcompetentpersonnel监护人员的控制Slip,triporfallonsamelevel滑倒、绊倒或坠落;Ltakecareoftheroadunderfootwhilewalking.行走过程中注意脚下。Injurebymovingvehicle车辆移动伤害;Mduringtransportation,competentpersonnelcannotsitinthecarriageorwalkinfrontofthevehicle,keepatleast2mawayfromthevehicle运输车辆在行驶过程中,监护人员不得坐在车厢内,不得在车辆前走动,距行使车辆距离应在2米外。ListofSpecificHazards详细风险列表:潜在危险编号中第3、6、7、12、13、17、21项。ChemicalList化学列表JSA实施总结及措施改进施工主管人:日期:CodeofPotentialHazards潜在危险编号Trappedinorbetweenobjects.围困2.Injuredwhistliftingorcarrying.举起或搬运受伤3.Slip,triporfallonsamelevel滑倒绊倒或坠落4Fallofpersonfromheight高空坠落5Strikingagainstfixedorstationaryobject固定物体打击6.Strikingagainstorstruckbymovingobject移动物体打击7steppingonobject踏在物体上8Exposuretoorcontactwithharmfulsubstance接触或揭漏有害物9Contactwithelectricityorelectricdischarge触电10Trappedbycollapsingoroverturningobject毁坏或倾翻物体而受限11struckbyfallingobject落物伤人12Injurebymovingvehicle车辆移动伤害13contactwithmovingmachineryorobjectbeingmachined接触移动机械14Exposuretofire火灾15Exposuretoexplosion爆炸16Injurybyhandtool传递工具伤害17Injurebyfallofground地面跌倒伤害18Asphyxiation窒息19Contactwithhotsurfaceorsubstance烫伤20poising悬空21specific特殊参加培训交底人员签字:HSE监护人签字:施工主管人签字:BJOBSAFETYANALYSIS工作安全分析Date(日期):JobTitle工作名称:loadingandunloadingofpipe管道装卸车LOCATION地点:Jobsite施工现场JSANoJSA编号:DEPARTMENT部门:汽机工程处SUPERVISOR主管人:TITLEOFPERSONWHODOESJOB工作执行人职务:PREPAREDBY编制:REVIEWEDBY审查:APPROVEDBY批准:EnvironmentalConditions环境条件Inside内部Outside外部Cold冷Heat热Wet湿Dust灰尘Vapors/Mist水汽Noise噪音Vibration震动Other其它HeavyRain大雨PrimaryJobFunctions&Position基本工作行动Lifting举重Grasping抓取Pushing推Sitting座Reaching延伸Bending弯曲Kneeling跪Standing直立Pulling拖Squatting蹲Other其它SEQUENCEOFBASICJOBSTEPS工作步骤POTENTIALHAZARD潜在危险风险评估RAM(H、M、L)RECOMMENDEDACTIONORPROCEDURE控制行动措施ACTIONBY执行人DATEDUE完成日期REMARK备注Loading装车举起或搬运受伤DamagewhenliftingandhandlingL搬运物体注意周围环境。Payattentiontothearoundwhenhandling.触电ElectricshockM车上方有电线时,要有防触电措施。Electricshockmeasuresshouldbetakenwhenthetherearewiresoverheadonthevehicle.移动物体打击StrikingbymovingobjectH管件不可抛扔,管道放置时小心谨慎。Thepipefittingscannotbethrew.Takenoticewhenplacingthepipe.高空坠落FallfromoverheadM当车的高度高于1.8米时,应有防坠落措施。Fallpreventionmeasuresshouldbetakenwhentheheightofthevehicleisabove1.8m.车辆移动伤害Damagebyvehiclemovin

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论