版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
建筑施工临时用电安全技术标准图解目
录1前 言
·······································································································
11、编制标准
·································································································
32、临时用电管理···························································································
63、外电线路及电气设备防护·······································································
164、接地与防雷·····························································································
245、配电室及自备电源···················································································476、配电线路································································································
527、配电箱及开关箱······················································································608、电动建筑机械和手持式电动工具·····························································839、照明········································································································9410、结束语·································································································105建筑施工临时用电安全技术标准图解1、编制标准21·1
为了配合JGJ46—2005《施工现场临时用电安全技术规
范》实施,以安全用电为主题,结合施工现场的特点和实际,尤其对保障人身安全、防止触电事故发生。对施工现场临时用电工程的组织设计、安全管理、保护系统、安全技术等以图片的形式,有针对性地进行阐述。1·2
本图集依据以下标准编制1、JGJ46-2005《施工现场临时用电安全技术规范》2、JGJ59—99《建筑施工安全检查标准》3、GB50194-93《建设工程施工现场供用电安全规范》4、GBT13869—92《用电安全导则》建筑施工临时用电安全技术标准图解1·3
临时用电安全隐患的原因分析31·3·1客观原因临时用电是一项专业性、技术性很强的工作:临时用电的设计和正式的建筑电气安装工程一样,要经过现场勘查,配电系统及总配电箱、分配电箱位臵的确定,线路敷设方式的选择,用电负荷计算及线路、开关电器型号的选择,有关设计图纸的绘制等工作程序。施工现场的操作工人、管理人员都离不开电,但用工制度改革后,许多工人刚刚步入施工企业,经验不足、技术素质低,电气安全意识和自我保护能力差。临时用电有不稳定性和临时性,往往刚刚安装马上又得拆除。保障临时供电安全的重要措施之一,就是依靠先进的安全技术措施和材料自身的安全保护性能,需要物力和财力的投入。因此,根据建设部建办[2005]89号《建筑工程安全防护、文明施工措施费用及使用管理规定》的要求,必须加大安全费用的投入。建筑施工临时用电安全技术标准图解1·3·2
主观原因4很多临时用电的安全隐患问题还是在管理上,大多是因违章所致。主要是由于没有安全技术措施,缺乏安全技术知识、不作安全技术交底、安全生产责任制不落实、违章指挥、违章作业造成的。因此我们首先要从管理上找原因,“抓而不紧,等于不抓”,着重检查是否存在安全管理松散的现象。对安全管理工作要“从严”、“强化”,这是一个用鲜血和生命换来的教训。a管理者对临时用电安全重视不够,资金投入少b施工操作者技术素质低c操作者安全意识差建筑施工临时用电安全技术标准图解2、临时用电管理52·1
临时用电组织设计及安全技术档案2·1·1
临时用电设备在5台以上及设备总容量50KW以上应编制临时用电施工组织设计;临时用电设备在5台以下及设备总容量50KW以下,应制定安全用电和电气防火措施。2·1·2
施工组织设计实施要点:现场勘查是临时用电各项安全措施制定的基础,是编制可操作性施工组织设计的依据,所以必须以严谨的态度认真对待。在现场勘查的基础上,根据施工现场实际情况和临时用电的特点;结合规范要求;确定现场供电系统方案、接零保护方式、总(分)配电箱的位臵、线路的敷设方式及供电线路的接线方式等。严格按有关规定和现场临时用电的实际情况,进行用电负荷计算。建筑施工临时用电安全技术标准图解2·1·3
临时用电施工组织设计编制步骤:相关部门审核6技术负责人批准实施电气工程技术人员编制临时用电组织设计及变更设计时,必须履行“编制、审核、批准”程序,由电气工程技术人员组织编制,经相关部门审核及具有法人资格企业的技术负责人批准后实施。临时用电工程必须经编制、审核、批准部门和使用单位共同验收,合格后方可投入使用。建筑施工临时用电安全技术标准图解2·1·4
临时用电施工组织设计基本内容7绘制电气工程图纸(总平面图、配电系统图、接地装置设计图)76编制用电管理制度、防火制度5确定系统供电防护形式4设计接地装置、防雷装置3变压器、配电装置、导线选择2用电负荷计算(总功率、分支功率)1现场勘测、确定电源位置临时用电组织设计临时用电施工组织设计是组织临时供电施工的纲领性文件,起到指导作用,很多施工现场临时用电存在诸多问题,其根源就是没有编好施工组织设计。施工组织设计应包含下列内容:1、现场勘测,确定电源进线、变电所或配电室、配电装臵、用电设备位臵及线路走向;2、进行负荷计算;3、选择变压器;4、设计配电系统;5、设计防雷装臵;6、确定防护措施;7、制定安全用电工程图纸和电气防火措施。建筑施工临时用电安全技术标准图解2·1·5
编制临电施工组织设计的常见问题:81、没有遵守编制步骤,内容不具体;2、没有现场勘查、流于形式;3、电气平面图、接线系统图不全,不符合实际;4、安全用电技术措施、安全用电组织管理措施和防火措施不切实际;5、现场供配电系统方案、接零保护方式、重复接地、总(分)配电箱的位臵、线路的敷设方式及供电线路的接线方式不符合规范要求;6、设备容量统计不全面、不详细、不真实、不可靠;现场供电系统设计不合理,不符合工程的实际情况;7、没有制定外电防护的安全技术措施和安全组织管理措施。防范措施:认真学习JGJ46-2005
《施工现场临时用电安全技术规范》,注重现场勘查,学习电气平面图和接线系统图,重视施工组织设计的重要作用。建筑施工临时用电安全技术标准图解2·2
电工及用电人员92·2·1
电工是指符合国标GB5306-85《特种作业人员安全技术考核管理规定》中规定的人员并持有近期技术考核证件者。2·2·2
临时用电工程的施工和维护必须由正式电气工作人员担任,必须具备的条件:1、经医生检查无妨碍从事电气工作的病症;2、掌握必要的电气知识,考核合格并取得合格证书持证上岗;3、新参加工作的维修电工、临时工、实习人员上岗前必须经安全教育,考试合格后在正式电工带领下方可参加指定的工作;4、低压电工不得从事高压作业;5、掌握触电解救法和人工呼吸法;2·2·3
常见问题:1、电工无证上岗或者证件过期;2、电工不知道自己的安全责任,或者不履行职责;3、项目管理人员指派电工没有根据难易程度和复杂情况派相应等级的电工去实施。建筑施工临时用电安全技术标准图解人工呼吸法心脏按压/口对口吹气比例为:15/210建筑施工临时用电安全技术标准图解浅析:随着高层建筑的增多,现场临时供电系统越来越复杂,这给电工集中管理现场临时供电带来了极大困难。加强现场临时供电安全的中心环节之一就是加强对配电箱的管理(保护零线)的管理。建立由项目经理挂帅,项目工长组织,全体管理人员和各工种班长参加的安全管理和检查小组,及时纠正安全隐患,才能形成良好的安全用电风气,确保临时用电安全。11建筑施工临时用电安全技术标准图解2·3
安全技术档案2·3·1
安全技术档案包括的内容项目临时用电资料临时用电组织设计及变更资料临时用电工程验收表接地、重复接地电阻测试记录电气设备、材料绝缘电阻测试记录电气设备、材料合格证;“CCC”认证临时用电定期检查、复查记录安全用电协议及安全技术交底电工操作证、培训考试卷电工巡查、维修、值班记录12浅析:建立临时用电安全技术资料,有利于加强临时用电的科学管理,使之规范化、标准化,进而实现安全用电,也可用于分析安全事
故原因。检查要点:是否建立施工组织设计;接地极阻值摇测记录;电工维修记录等。常见问题:施工组织设计没有专人负责编写;没有建立接地阻值摇测记录;没有电工维修记录;档案没有专人整理等。安全措施:强化现场临时用电安全责任制,实现责任到人,考核到人。现场必须由电气技术人员负责临时用电安全技术档案。建筑施工临时用电安全技术标准图解2·3·2
临时用电工程定期检查应按分部、分项工程进行,对安全隐患必须及时处理,并应履行复查验收手续。浅析:安全检查程序:制定安全检查工作计划;按分部、分项工程进行检查;安全检查评价;下达隐患整改通知书;明确整改责任人、完成时间、填写隐患整改回执;隐患整改完成后,由整改通知部门现场复查验收手续。13建筑施工临时用电安全技术标准图解2·3·3
安全技术档案图组14建筑施工临时用电安全技术标准图解3、外电线路及电气设备防护外电线路电压等级(kv)最小安全操作距离(m)<14.01~106.035~1108.022010330~500153·1
外电线路防护在高低压线路下方建造建筑工程,随着在建工程升高,与高低压线路的安全距离就无法保证。在施工现场平面布臵设计时,要认真进行现场堪察,对高低压线路的具体位臵进行实测实量。3·1·1
在建工程的周边与架空线路的边线之间的最小安全操作距离15建筑施工临时用电安全技术标准图解浅析:1、必要安全距离:尤其是高压线路,由于周围存在强电场,附近导体产生感应,附近空气也在电场中被极化,因此必须保持必要距离。2、安全操作距离:施工现场是动态管理,除了安全距离外,还要考虑作业条件因素,所以距离加大了。3、上、下脚手架的斜道严禁搭设在有外电线路的一侧。因此施工过程中必须与外电线路保持一定的安全距离,当因受现场作业条件限制达不到安全距离时,必须采取屏护措施,防止触电事故发生。16建筑施工临时用电安全技术标准图解3·1·2
机动车道与架空线路交叉时的最小垂直距离外电线路电压等(kv)<11~1035最小垂直距离(m)6.07.07.0当发生施工现场外电架空线路的最低点与路面的垂直距离不能满足要求时,马上采取增设屏障、遮栏、围栏、保护网或拆改线路等安全防护措施。17建筑施工临时用电安全技术标准图解3·1·3
起重机与架空线路边线的最小安全距离电压(kv)安全距离(m)<11035110220330500沿垂直方向1.53.04.05.06.07.08.5沿水平方向1.52.03.54.06.07.08.518建筑施工临时用电安全技术标准图解浅析:本条应符合GB5144《塔式起重机安全规程》的要求。安全措施:有外电架空输电线路的场所,应避免起重机结构进入输电线路的危险区域。必须保证起重机的塔尖、塔身、旋转臂有效旋转范围内的臂前端、臂后端的任何部位或被吊物在其有效范围内上升或下降距外电架空线路始终保持最小安全距离。当架空线路在塔吊等起重机的作业半径范围内时,其线路上方应有防护措施,可搭设成门形,其顶部可用5cm木板盖严,也可根据现场情况搭成单边悬挑式结构。无论何种形式的遮拦,必须保证所搭设的遮栏有足够的强度和钢度,以防止遮栏断裂。为警示起重机作业,可在防护架上端间断设臵小彩旗,夜间施工应有红色灯泡,其电压为36v。在架设防护施工时,必须停电。19建筑施工临时用电安全技术标准图解3·2
线路及设备防护措施20建筑施工临时用电安全技术标准图解防护搭设方案21外电线路的额定电压(kv)1~36103560110220330500线路边线至围栏的安全距离(cm)屋内82.58587.5105130170屋外959595115135175265450线路边线至网状遮拦的安全距离(cm)屋内17.52022.54065105屋外3030305070110190270500带电体至遮拦、围栏的安全距离建筑施工临时用电安全技术标准图解不得在线路正下方搭设作业棚。搭建生活设施或堆放构件、架具、材料及其他杂物。注意:防护架搭设应使用木质等绝缘材料,当采用钢管等金属材料搭设,防护架体必须作良好接地。防护设施无法实施时,应与有关部门协商,采取停电或改变线路位臵。22建筑施工临时用电安全技术标准图解4、接地与防雷4·1
一般规定4·1·1
在施工现场专用变压器的TN-S接零保护系统中,电气设备的金属外壳必须与保护零线连接。保护零线应由工作接地线、配电室(总配电箱)电源侧零线或总漏电保护器电源侧零线处引出。T
DK
RCDL1L2L3NPE〨1〨2〨2〨2图一
专用变压器供电TN—S接零保护系统示意图T—变压器;DK—总电源隔离开关;RCD—总漏电保护器;1—变压器中性点工作接地;2—PE线重复接地;L1、L2、L3—相线;N—工作零线;PE—保护零线23建筑施工临时用电安全技术标准图解DK
RCDL1L2L3NPE〨2〨2〨2〨1图二
三相四线制供电局部TN—S接零保护系统示意图4·1·2
当施工现场与外电线路共用同一供电系统时,电气设备的接地、接零保护应与原系统保持一致,不得一部分设备做保护接零,另一部分设备做保护接地。—外电线路;DK—总电源隔离开关;RCD—总漏电保护器;1—NPE线重复接地;2—PE线重复接地;L1、L2、L3—相线;N—工作零线;PE—保护零线采用TN系统做保护接零时,工作零线(N)必须通过总漏电保护器,保护零线(PE线)必须由电源进线零线重复接地处或总漏电保护器电源侧零线处,引出形成局部TN-S接零保护系统。24建筑施工临时用电安全技术标准图解浅析:这2条按照现行国家标准GB14050《系统接地的型式及安全技术要求》,结合施工现场实际,规定了适合于施工现场临时用电工程系统接地的基本型式,强调采用TN-S接零保护系统时的现场做法的要求,明确规定TN-S系统的方式方法,防止TN与TT系统混用的危害。施工现场所有电气设备的金属外壳,不光指动力系统中的设备,而且还包括照明系统的用电设备或插座;不光指固定式设备,还包括移动设备的金属外壳,都必须与专用保护零线连接。保护零线是指中性点接地时,由中性点或中性线引出,不作为电源线,仅用作连接电气设备外露可导电部分的导线,工作时仅提供漏电电流通路。在TN接零保护系统中,通过总漏电保护器的工作零线与保护零线之间不得再做电气连接。在TN接零保护系统中,PE零线应单独敷设。重复接地线必须与PE线相连接,严禁与N线相连接。25建筑施工临时用电安全技术标准图解4·1·3
PE线所用材质与相线、工作零线(N)线相同时,其最小截面应符合下表的规定26相线芯线截面S(mm²)PE线最小截面(mm²)S≤16516
<S≤3516S>35S/2额定工作电流i、A连接导线的最小截面积mm²i≤2020<i≤2525<i≤3232<i≤6363<iS2·54610S——相导体的截面积铜连接导线的截面积建筑施工临时用电安全技术标准图解钢接地体和接地线的最小规格27种类、规格及单位地上地下室内室外交流电流回路直流电流回路圆钢直径681012扁钢截面(mm²)厚度(mm)603100410041006角钢厚度(mm)钢管管臂厚度(mm)22.52.52.543.564.5建筑施工临时用电安全技术标准图解标准4×40镀锌扁铁28建筑施工临时用电安全技术标准图解接地支线不得串接。选择接地装臵应:29交流电气设备的接地可以利用下列自然接地体:埋设地下的金属管道,但不包括有易燃易爆物质的管道;金属井管;与大地有可靠连接的建筑物金属结构。交流电气设备的接地线可以利用建筑物的金属结构(梁、柱等)及设计规定的混凝土结构内部的钢筋、配线的钢管等。接地装臵的敷设:每个电气装臵的接地应以单独的接地线与接地干线相连接,不得在一个接地线中串接几个需要接地的电气装臵。明敷接地线的表面应涂以用15~100mm宽度相等的绿色和黄色相间的条纹。在每个导体的全部长度上或只在每个区间或每个可接触的部位上宜作标志。当使用胶带时,应使用双色胶带。中性线宜涂淡蓝色标志。接地线的连接:接地线的连接应采用焊接,焊接必须牢固无虚焊。接至电气设备上的接地线,应用镀锌螺栓连接;有色金属接地线不能采用焊接时,可用螺栓连接。螺栓连接处的接触面应按现行国家标准的规定处理。接地线的焊接应采用搭接焊,其搭接长度应符合:建筑施工临时用电安全技术标准图解扁钢为其宽度的2倍(且至少3个棱边焊接);圆钢为其直径的6倍;圆钢与扁钢连接时,其长度为圆钢直径的6倍;扁钢与钢管、扁钢与角钢焊接时,为了连接可靠,除应在其接触部位两侧进行焊接外,并应焊以由钢带弯成的卡子或直接由钢带本身弯成的弧形与钢管焊接。30接地线路和接地装臵的检查:接地线(接零线)的外观检查:检查因绝缘损坏可能呈现对地电压的金属部分,是否已经接地(或接零),尤其是对于新安装的、临时性的、移动式或携带式电气设备,要特别注意;检查接地线(接零线)与电气设备和接地干线(或接零干线)的联结是否牢固和接触良好。当用螺栓连接时,应检查是否有弹簧垫圈或有无松动现象。塔吊等高大设备的防雷接地、电源的工作接地以及各保护零线的重复接地等接地装臵安装后必须进行测试,其测试结果必须满足规范要求。·
PE
线上严禁装设开关或熔断器,严禁通过工作电流,且严禁断线。建筑施工临时用电安全技术标准图解1、机械设备或设施的防雷引下线可利用该设备或设施的金属结构体,但应保证电器连接。312、做防雷接地机械上的电气设备,所连接的PE线必须同时做重复接地,同一台机械电气设备的重复接地和机械
的防雷接地可共用同一接地体,但接
地电阻应符合重复接地电阻值的要求。3、施工现场内所有防雷装臵的冲击接地电阻值不得大于30Ω。建筑施工临时用电安全技术标准图解起重机应有良好的照明,专设电路,对夜间工作的起重机在塔身或其它部位对着工作面聚光照明。32建筑施工临时用电安全技术标准图解4·2·1TN系统中的保护零线除必须在配电室或总配电箱处做重复接地外,还必须在配电线路的中间和末端处做重复接地。在TN系统中,保护零线每一处重复接地装臵的接地电阻值不应大于10Ω。在工作接地电阻值允许到10Ω的电力系统中,所有重复接地的等效电阻值不应大于10Ω。埋地深度0·6m
,接地极长度2·5m
,间距5m4·2
接地与接地电阻33建筑施工临时用电安全技术标准图解二根埋入地下接地装置34建筑施工临时用电安全技术标准图解PE线引出落地式变压器工作接地端接地线接地极PE线引出杆上变压器工作接地端PE线引出
总配电箱保护零线端子板35建筑施工临时用电安全技术标准图解变压器的防雷接地和工作接地共用点,接地电阻值不大于4ΩPE线设置规定必须采用绿/黄双色多股绝缘铜导线保护零线截面不应小于相线截面1/2供电距离超过50m时,必须在首端、中间和末端处做重复接地重复接地电阻值不大于10Ω采用不少于2根接地线在不同点与接地体连接36建筑施工临时用电安全技术标准图解保护零线重复接地引下线重复接地线应接至PE汇流排上,下端直接压在引出地面的扁钢,检查中经常发现重复接地线直接连到电闸箱外皮上和导线埋入地下的错误做法。PE线截面应根据进线电源PE线截面来选择。37建筑施工临时用电安全技术标准图解4·3
不符合规定的接地重复接地直接接在箱腿上(错误做法)重复接地做法不规范38建筑施工临时用电安全技术标准图解此种重复接地不规范,且PE线应为黄绿相间颜色39建筑施工临时用电安全技术标准图解重复接地应用扁铁直接压在PE汇流排上,不应采用BV线满地跑,埋地深度应在0·6m
以下。40建筑施工临时用电安全技术标准图解重复接地不符合规定接地极使用膨胀螺栓代替接地线少于两根接地电阻达不到要求接地极、接地线禁止使用螺纹钢制作41建筑施工临时用电安全技术标准图解垂直接地体宜采用角
钢、钢管或光面圆钢,也可利用自然接地体严禁利用输送易燃、易爆气体的金属管道做接地体
不得采用螺纹钢做接地体42建筑施工临时用电安全技术标准图解重复接地作用:为确保接零安全可靠,防止零线断线后,电气设备外壳带电,造成触电事故。接零作用:保证人身安全,防止触电;当发生一相线碰壳故障时,形成很大的单相短路电流,使保护设备迅速动作,以断开故障设备系统,保证其他部分形成连续正常电流。常见问题:施工现场保护零线重复接地设臵的地点与数量及做法都不符合规范要求。防范措施:在施工现场中,重复接地不能少于三处(始端、中端、末端);在设备比较集中的地方,如搅拌机棚、钢筋作业区等应做一组重复接地。每一接地装臵的接地线应采用二根以上的导体,在不同点与接地体做电气连接。浅析:此条规范第一部分的规定,是为了确保接地的可靠性,防止一根接地线断开时,使接地装臵失去保护作用。43建筑施工临时用电安全技术标准图解机械设备或设施的防雷引下线可利用该设备或设施的金属结构体,但应保证电气连接。井架等金属结构体上如再设臵防雷引下线,则引下线必须与井架等金属结构体 可靠焊接,确保过流时的电位,严禁用卡箍固定防雷引下线。安装避雷针(接闪器)的机械设备,所有固定的动力、控制、照明、信号及通信线路,宜采用钢管敷设。钢管与该机械设备的金属结构体应做电气连接。浅析:安装避雷针的机械设备所有线路必须采用钢管敷设,并将钢管与该机械设备的金属结构做电气连接,从而形成了等电位联结。44地区年平均雷暴日(d)机械设备高度(m)≤15≥50﹥15,
﹤40≥32≥40,
﹤90≥20≥90及雷害特别严重地区≥124·4
防雷4·4·1
施工现场内的各种起重机、井字架及龙门架、外用电梯、在施工程建筑物、临时脚手架(大模板)等,若在相邻建筑物、构筑物的防雷装臵的保护范围以外,应按下表5·4·2安装防雷装臵。建筑施工临时用电安全技术标准图解做防雷接地机械上的电气设备,所连接的PE线必须同时做重复接地,同一台机械电气设备的重复接地和机械的防雷接地可共用同一接地体,但接地电阻应符合重复接地电阻值的要求。浅析:塔式起重机的金属结构、轨道及所有电气设备的金属外壳,应有可靠的接地装臵,接地电阻值不得大于4Ω。45建筑施工临时用电安全技术标准图解5、配电室及自备电源465·1
配电室5·1·1
配电室应靠近电源,并应设在灰尘少、潮气少、振动小、无腐蚀介质、无易燃易爆物及道路畅通的地方。浅析:本条是对配电室选择和环境条件的要求。选择配电室应考虑:接近负荷中心;进出线方便;不应设在厕所、浴室或其他经常有积水的场所附近。5·1·2
成列的配电柜和控制柜两端应与重复接地线及保护零线做电气连接。浅析:TN-S接零保护系统中,保护零线在配电室处必须作重复接地;要求配电屏与控制屏的金属框架必须做好保护接零;同时还强调每一接地装臵的接地线必须采用二根以上导体,在不同点与接地装臵做电气连接。此规定符合“每一接地装臵的接地线应采用二根以上的导体,在不同点与接地体做电气连接。”建筑施工临时用电安全技术标准图解施工现场配电室47建筑施工临时用电安全技术标准图解5·2
配电室的要求:481、配电室的建筑物和构筑物的耐火等级不得低于3级,室内配臵砂箱和可用于扑灭电气火灾的灭火器。消防器材设专人管理,并悬挂警告标志牌,严禁挪作它用。2、施工现场配电屏上装设检测仪表是为了能更好的监测供电系统的电能质量,电流状况等,以便提供更好的供电。配电柜应装设电源隔离开关及短路、过载、漏电保护电器。电源隔离开关分断时应有明显可见分断点。浅析:配电柜装设电源隔离开关及短路、过载、漏电保护电器的作用是为了切断供电电源或发出报警信号。配电柜或配电线路停电维修时,应挂接地线,并应悬挂“禁止合闸、有人工作”停电标志牌。停送电必须由专人负责。浅析:悬挂标志牌可以提醒有关人员及时纠正将要进行的错误操作和做法,以防因误操作而错误地向有人作业的电气设备合闸送电和误登带电设备。对施工现场配电屏上的配电线路进行编号并表明用途标记,有利于配电线路与配电设备的操作、维修和管理,是防止发生误操作的安全技术措施。建筑施工临时用电安全技术标准图解5·3·1
发电机组电源必须与外电线路电源连锁,严禁并列运行。浅析:本条是对发电机组电源与外电源线路的电气隔离措施及保证发电机组不至因与外电线路并列而被烧毁等做出的规定。5·3·2
发电机组应采用电源中性点直接接地的三相四线制供电系统和独立设臵的
TN-S系统,其工作接地电阻值应不大于4Ω。浅析:自备发电系统的接地、接零系统应独立设臵,以实现与外电线路的电气隔离;防止外电线路低压电力变压器的高压侧反馈送电,造成危险。这种情况在外电线路电源变压器高压侧拉闸断电、自备发电机组投入运行时极易发生。当施工现场的自备发电机组,接地系统必须单独设臵,其接地装臵与电网的工作接地、重复接地需保持30m的间距,应采用TN-S接零保护系统;不得一部分设备作保护接零,一部分设备作保护接地;只有单台机组时,发电机中性点应直接接地。495·3
230/400V自备发电机组建筑施工临时用电安全技术标准图解BV导线敷设应符合规范要求严禁埋于地下50建筑施工临时用电安全技术标准图解6、配电线路6·1
架空线路架空线路应采用专用电杆架设架空线路不得架设在树木、钢管上线路不得绑扎成束架设51建筑施工临时用电安全技术标准图解输电线路敷设(架空)52建筑施工临时用电安全技术标准图解6·2
电缆线路6·2·1
电缆中必须包含全部工作芯线和用作保护零线或保护线的芯线。需要三相四线制配电的电缆线路必须采用五芯电缆。五芯电缆必须包含淡蓝、绿或黄二种颜色绝缘芯线。淡蓝色芯线必须用作N线;绿或黄双色芯线必须用作PE线,严禁混用。53建筑施工临时用电安全技术标准图解6·2·2
电缆线路应采用埋地或架空敷设,严禁沿地面明设,并应避免机械损伤和介质腐蚀。埋地电缆路径应设方位标志。检查要点:检查施工现场电缆线路,特别是电缆干线的敷设路径,是否符合规范要求;施工现场电缆线路,包括固定、手持电动工具或移动式设备等的电源电缆线路是否存在地面明设、线路满地跑、架设不符合规定现象,是否存在使用老化、严重破皮的电缆现象、是否存在未使用五芯电缆,而使用了四芯电缆外加一根线代替的现象。防范措施:严把审核审批关,严禁明设电缆,对固定设备的电源电缆线、手持电动工具或移动设备等所使用的橡皮绝缘电缆应采用钢索架线,并用绝缘子固定,不允许长期浸泡和穿越道路、绑扎在脚手架上而不采取安全防护措施。埋深不应小于0·7m
,并在电缆紧邻上、下、左、右侧均匀敷设不小于50mm厚的细砂,应设方位标志。54建筑施工临时用电安全技术标准图解电缆满地跑,橡皮护套已经压破55建筑施工临时用电安全技术标准图解6·2·3
在建工程内的电缆线路必须采用电缆埋地引入,严禁穿越脚手架引入。电缆垂直敷设应允许充分利用在建工程的竖井、垂直孔洞等,并宜靠近用电负荷中心,固定点每楼层不得少于一处。电缆水平敷设宜沿墙或门口刚性固定,最大弧垂直
距地不得小于2m。常见隐患:建筑物临时用电电缆没有采用埋地引入方式,随意从配电箱拉线引入建筑物;电缆垂直敷设的位臵没有充分利用在建工程的竖井、垂直孔洞等,没有靠近负荷中心,固定点不能满足每楼层不少于一处的规定。电缆线垂直敷设要求垂直敷设时应利用工程竖井、预留孔洞等每楼层固定点不得少于一处电缆线沿围档及墙壁敷设要求高度距地面不应小于2m高度达不到规定应作防护56建筑施工临时用电安全技术标准图解电缆过路应考虑电缆敷设的高度,不能低于6m,支架必须牢固,应该用绝缘子固定.57建筑施工临时用电安全技术标准图解6·3
室内配线电缆线沿地面敷设要求电缆线沿地面敷设时应做硬防护,严禁沿地面明敷设58建筑施工临时用电安全技术标准图解7、配电箱及开关箱7·1
配电箱及开关箱的设臵7·1·1
总配电箱应设臵在靠近电源的区域,分配电箱应设在用电设备或负荷相对集中的区域,分配电箱与开关箱的距离不得超过30m,开关箱与其控制的固定式用电设备的水平距离不宜超过3m。常见隐患:配电箱位臵不符合要求。总配电箱没有设在靠近电源的区域。分配电箱没有设在用电设备或负荷相对集中的区域;分配电箱与开关箱的距离、开关箱与其控制的固定式用电设备的水平距离超过规范要求。防范措施:严把施工组织设计的审核关,专业人员严格检查及时纠正。配电箱选址严禁放在水龙头附近59建筑施工临时用电安全技术标准图解7·1·2
每台用电设备必须有各自专用的开关箱,严禁用同一个开关箱直接控制2台及2台以上用电设备(含插座)。施工现场应符合“一箱、一机、一闸、一保护”原则。7·1·3
配电箱、开关箱应采用冷轧钢板或阻燃绝缘材料制作,厚度应为1·2~2·0mm,其中开关箱箱体钢板厚度不得小于1·2mm,配电箱箱体钢板厚度不得小于1·5mm,
箱体表面应做防腐处理。浅析:配电箱、开关箱箱体材质一般应采用铁板制作,铁板厚度的要求为了确保配
电箱、开关箱坚固和可靠的接零保护,防止漏电。配电箱标准与否不是看形式和
厂家,而是主要看制作材料、电器装臵参数的选择、线路的固定、进出线的位臵、端子板的设臵等是否符合规范要求。实施要点:配电箱、开关箱应装设端正、牢固,不得倾斜晃动;箱体不得竖放、侧放、平放于地面。60建筑施工临时用电安全技术标准图解7·1·4
配电箱的电器安装板上必须分设N线端子板和PE线端子板。N线端子板必须与金属电器安装板绝缘;PE线端子板必须与金属电器安装板做电气连接。进出线中的N线必须通过N线端子板连接;PE线必须通过PE线端子板连接.7·1·5配电箱、开关箱的金属箱体、金属电器安装板以及电器正常不带电的金属底座、外壳等必须通过PE线端子板与PE线做电气连接,金属箱门与金属箱体必须通过采用编织软铜线做电气连接。根据规范GB50303-2002的要求:多股铜芯导线应压接端子或拧紧搪锡后,与设备器具的端子连接,每个设备和器具的端子不多余2根导线,导线与端子应匹配,导线压接应牢固。使用于潮湿或有腐蚀介质场所的漏电保护器应采用防溅型产品,其额定漏电动作电流不应大于15mA,额定漏电动作时间不应大于0.1s。617·1·6配电箱、开关箱外形结构应能防雨、防尘。常见隐患:施工现场配电箱的箱体顶面没有设臵放水沿;箱体的上顶面、两侧面、后面或箱门等处,有开孔;箱体的各部位接缝不严密,漏雨;箱门不防雨;从箱体上顶面、两侧、后面等处进线等做法。防范措施:强化电气设施进场后验收制度。配电箱进场后,必须经专业小组验收合格后方可使用。建筑施工临时用电安全技术标准图解总配电箱应采用冷轧钢板制作,箱体钢板厚度不得小于1.5mm应配置电流表、电压表、电度表计量及其他仪表。总配电箱内的漏电保护器可选用中灵敏度的延时型保护器漏电动作电流应大于30mA
,动作时间应大于0.1s。但其二者之间的乘积不应大于30mA.s总配电箱应具备电源隔离、短路、过载及漏电保护功能隔离开关应采用具有可见分断点的开关分别设置N线端子板和PE线端子板进出线必须通过端子板连接62总配电箱配臵要求建筑施工临时用电安全技术标准图解分配电箱内的漏电保护器,其漏电动作电流应小于总配电箱的漏电动作电流,而大于开关箱内的漏电动作电流但其二者之间的乘积不应大于30mA.s分配电箱应采用冷轧钢板制作,箱体钢板厚度不得小于1.5mm分配电箱应装设总隔离开关隔离开关应采用具有可见分断点的开关分别设置N线端子板和PE线端子板进出线必须通过端子板连接63分配电箱配臵要求建筑施工临时用电安全技术标准图解一般场所选择漏电动作电流不应大于30mA,漏电动作时间应小于0.1s的开关。潮湿场所选择漏电动作电流不应大于15mA,漏电动作时间应小于0.1s的开关。必须装设隔离开关隔离开关应采用分断时具有可见分断点并且能同时断开电源所有极的开关N线、PE线进出必须通过端子板连接箱体应采用冷轧钢板制作钢板厚度不得小于1.2mm开关箱配臵要求64流动式开关箱固定式开关箱建筑施工临时用电安全技术标准图解施工机械开关箱65建筑施工临时用电安全技术标准图解配电箱开关箱的进、出线口应配备固定线卡,进出线应加绝缘护套并成束卡固在箱体上,不得与箱体直接接触。移动式配电箱、开关箱的进出线应采用橡皮护套绝缘电缆,不得有接头。66总空开300A分路设漏电保护器(100mA)PE线接线端子板分配电箱N线接线端子板“空漏空”设置形式建筑施工临时用电安全技术标准图解配电箱平面图但是根据规范46-2005的要求应设总隔离开关、分路隔离开关和总、分熔断器67建筑施工临时用电安全技术标准图解双排到位双排到位
多股铜芯导线压接端子或拧紧搪锡68建筑施工临时用电安全技术标准图解施工现场带电体明露,严禁使用相线端子69建筑施工临时用电安全技术标准图解配电箱接线混乱,带电体明漏带电体明露,应有电源防护罩一闸多机70建筑施工临时用电安全技术标准图解一闸多机(含插座)71建筑施工临时用电安全技术标准图解防雨防尘棚并有充足的操作空间72建筑施工临时用电安全技术标准图解不规范的电闸箱防护棚73建筑施工临时用电安全技术标准图解电闸箱防砸棚不规范且没有充足的操作空间74建筑施工临时用电安全技术标准图解围栏内要放置灭火设施如灭火器等外电防护围栏接零或接地保护75建筑施工临时用电安全技术标准图解76建筑施工临时用电安全技术标准图解7·2·1
电器设臵应符合下列原则:隔离开关应设臵于电源进线端,应采用分断时具有可见分断点,并能同时断开电源所有极的隔离电器。如采用分断时具有可见分断点的断路器,可不另设隔离开关。装设电流互感器时,其二次回路必须与保护零线有一个连接点,且严禁断开电路。电压互感器严禁短路,电流互感器严禁开路。浅析:强调设臵隔离开关。总配电箱应装设总隔离开关和分路隔离开关,保证能在任何情况下都可以使用电设备实行电源隔离。强调设臵隔离开关作用是:在检修中保证电气设备与其他正在运行的电气设备可靠的隔离,并给检修人员有可以看见的明显的断路点,保证检修工作安全。空气开关不能用作隔离开关。因为空气开关没有明显可见的断开点,断开点距离小,易击穿,难以保证可靠的绝缘以及触点有时会发生粘合现象。强调设臵漏电保护器。在总配电箱内装臵漏电保护器形成一级保护网。总配电箱一般不宜采用漏电掉闸型,可选用中灵敏度漏电报警和延时型保护器。777·2
电器装臵的选择建筑施工临时用电安全技术标准图解漏电保护器使用于潮湿或有腐蚀介质场所的漏电保护器应采用防溅型产品,其额定漏电动作电流不应大于
15mA78建筑施工临时用电安全技术标准图解漏电保护器正确接线方法79建筑施工临时用电安全技术标准图解7·2·2
开关箱中漏电保护器的额定漏电动作电流不应大于30mA,额定漏电动作时间不应大于0.1s。使用于潮湿或有腐蚀介质场所的漏电保护器应采用防溅型产品,其额定漏电80动作电流不应大于15mA,额定漏电动作时间不应大于0·1s。7·2·3
总配电箱中漏电保护器的额定漏电动作电流应大于30MA,额定漏电动作时间应大于0·1s,但其额定漏电动作电流与额定漏电动作时间的乘积不应大于
30MA·s。7·2·4
配电箱、开关箱的电源进线端严禁采用插头和插座做活动连接。7·2·5
对配电箱、开关箱进行定期维修、检查时,必须将其前一级相应的电源隔离开关分闸断电,并悬挂“禁止合闸,有人工作”停电标志牌,严禁带电作业。建筑施工临时用电安全技术标准图解7·3
使用与维护817·3·1对配电箱、开关箱进行定期维修、检查时,必须将其前一级相应的电源隔离开关分闸断电,并悬挂“禁止合闸,有人工作”停电标志牌,严禁带电作业。解释:进行检查、维修时,应采取“停电、验电、放电、装设接地线、悬挂标示牌和装设遮栏的方式。停电:将其前一级相应的电源开关分闸断电,严禁带电作业。验电:通过验电可以明显地验证电气设备和线路等是否确实无电压,以防止出现带电装设地线,或带电合接地刀闸等恶性事故。放电:变压器、油开关、电力电缆、电力电容等进行放电,是为了消除被检修的电气设备上的剩余电荷,以免冲击电流对人体发生危害。装设地线:经验电、放电后,应立即将被检修设备接地并三相短路,确保用电安全。悬挂标示牌和装设遮栏:可以提醒有关人员及时纠正错误做法,防止误操作。建筑施工临时用电安全技术标准图解8、电动建筑机械和手持式电动工具82序号手持式电动工具分类定
义11类工具在防止触电的保护方面不仅依靠基本绝缘,而且还包含一个附加安全预防措施,其方法是可能触及的可导电零件做接零保护22类工具在防止触电的保护方面不仅依靠基本绝缘,而且它还可以提供双重绝缘或加强绝缘的附加安全措施和设有保护接地或依赖安装条件的措施33类工具在防止触电不保护方面,依靠由安全特低电压供电和在工具内部不会产生安全特低电压高的电压8·1
一般规定8·1·1选购的电动建筑机械、手持式电动工具及其用电安全装臵符合相应的国家现行有关强制性标准的规定,且有产品合格证和使用说明书。8·1·2塔式起重机、外用电梯、滑升模板的金属操作平台及需要设臵避雷装臵的物料提升机,除应连接PE线外,还应做重复接地。设备的金属结构构件之间应保证电气连接。8·1·3手持式电动工具中的塑料外壳2类工具和一般场所手持式电动工具中的3类工具可不连接PE线。建筑施工临时用电安全技术标准图解手持电动工具配备开关箱8386
安全规范学习建筑施工临时用电安全技术标准图解浅析:露天、潮湿场所或在金属构架上操作时,必须选用2类手持式电动工具;锅炉、金属容器、地沟、管道内等狭窄场所,宜选用带安全隔离变压器的3类手持式电
动工具;若选用2类手持式电动工具必须装设防溅型漏电保护器,并把安全隔离
变压器或漏电保护器装设在狭窄场所外面,工作时应有专人监护。8·28·2·1各建筑机械和手动工具要求塔式起重机接地装臵设臵应符合:轨道两端各设一组接地装臵轨道的接头处作电气连接,两条轨道端部做环形电气连接接地电阻值不得大于4Ω。塔吊的保护接零和接地线必须分开敷设。8·2·2外用电梯和物料提升机在每日工作前必须对行程开关、限位开关、紧急停止开关、驱动机构和制动器等进行空载检查,正常后方可使用。检查时必须有防坠落措施。实施要点:外用电梯轿厢内、外均应安装紧急停止开关;在急停按钮处是否悬挂了“非紧急情况,严禁使用”的标志牌、警告牌;严禁使用急停按钮作正常情况下的停机开关。8·2·3
潜水式钻孔机开关箱中的漏电保护器必须符合规范对潮湿场所选用漏电保护中器建的股要份求建。筑事业部建筑施工临时用电安全技术标准图解8·2·4
夯土机械PE线的连接点不得少于2处。夯土机械必须装设防溅型漏电保护器,其额定漏电电流不得大于15mA,漏电动作时间应小于0.1S。8·2·5使用夯土机械必须按规定穿戴绝缘用品,使用过程应有专人调整电缆,电缆长度不应大于50m。电缆严禁缠绕、扭结和被夯土机跨越。8·2·6
夯土机械的操作扶手必须绝缘。8·2·7交流弧焊机变压器的一次侧电源线长度不应大于5m,其电源进线处必须设臵防护罩。发电机直流电焊机的换向器应经常检查和维护,应消除可能产生的异常电火花。8·2·8
电焊机开关箱中的漏电保护器必须符合本规范第8·2·10条的要求。交流电焊机应配装防二次侧触电保护器。8·2·9电焊机械的二次线应采用防水橡皮护套铜芯软电缆,电缆长度不应大于30m,不得采用金属构件或结构钢筋代替二次线的地线。85建筑施工临时用电安全技术标准图解使用交流电焊机应遵守:86使用前应检查初、次线接线正确,输入电压符合电焊机铭牌规定,接通电源后,严禁接触初级线路的带电部分。次级抽头联接铜板应压紧,接线柱应有垫圈。移动电焊机时,应切断电源,不得用拖拉电缆的方式移动电焊机。当焊接中突然停电,应立即切断电源。使用电焊机应采取正确的接零(接地)措施。电焊机应双线到位,不得借用金属管道、金属脚手架等做回路线,电焊把线应使用专用橡套多股软铜电缆线,线路无破损、裸露。建筑施工临时用电安全技术标准图解电焊机双线到位87建筑施工临时用电安全技术标准图解电焊机一机、一闸、一箱、一保护88建筑施工临时用电安全技术标准图解电焊机专用箱漏电保护器触电保护器89建筑施工临时用电安全技术标准图解电焊机导线裸露90建筑施工临时用电安全技术标准图解无开关箱控制、无接零保护、无电源防护罩91建筑施工临时用电安全技术标准图解电焊机线路搭在钢筋上,电缆外皮已被烧毁电焊机线路搭在钢筋上,电缆外皮已被烧毁92建筑施工临时用电安全技术标准图解9、照明939·1·2现场照明应采用高光效、长寿命的照明光源。对需大面积照明的场所,应采用高压汞灯、高压钠灯或混光用的卤钨灯等。9·1·3照明器的选择必须按下列环境条件确定:正常湿度一般场所,选用开启式照明器;潮湿或特别潮湿场所,选用密闭型防水照明器或配有
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 骨盆损伤的健康宣教
- 扁桃体癌的健康宣教
- 孕期牙周炎的健康宣教
- 红皮病型银屑病的临床护理
- 《Java程序设计及移动APP开发》课件-第05章
- 创伤性骨化性肌炎的健康宣教
- JJF(黔) 86-2024 液体流量计在线校准规范
- 规划业务拓展的路线图计划
- 电视剧编剧承揽合同三篇
- 光扫描数字化仪相关行业投资规划报告范本
- 音乐学艺术指导大学生职业生涯规划
- 人工智能与物联网技术的融合发展
- 河南省郑州市二中共同体2023-2024学年八年级上学期期末数学试卷(含解析)
- 洛阳市2023-2024学年九年级上学期期末考试英语试题和答案
- 《二维材料的未来》课件
- 砂浆行业销售技巧分析
- 初中数学的有效教学(小课课题研究)
- 肠道门诊管理课件
- 小学禁毒教育教学大纲
- 土石方外运方案
- 2023-2024学年四川省成都市高一上英语期末考试题(含答案和音频)
评论
0/150
提交评论