作业代码,作业名称,计划工期,计划开始,计划完成,备注
#1机组,,1172,04-05-15A,2007/8/20,
热力系统,,1172,04-05-15A,2007/8/20,
AB101,#1机组主厂房地下结构施工,143,04-06-05A,2004/10/31,
AB10101,#1机组主厂房开始浇注第一罐混凝土,0,04-06-30A,,
AB10102,#1机组主厂房基础出零米,0,,04-10-30*,
AB10103,#1机组除氧煤仓间基础开挖及桩头处理,160,04-06-05A,04-07-15A,
AB10104,#1机组除氧煤仓间基础,0,04-07-21A,04-10-22A,
AB10105,#1机组除氧煤仓间回填,90,04-10-11A,2004/11/5,
AB10106,#1机组汽机间基础开挖及桩头处理,90,04-07-16A,04-08-04A,
AB10107,#1机组汽机间基础施工,150,04-08-05A,2004/11/6,
AB10108,#1机组汽机间基础回填,150,04-10-01A,04-10-31A,
AB102,#1机组汽机房地下设施施工,198,04-09-30A,2005/8/10,
AB10201,#1机组汽机房设备基础施工完,0,,04-10-30*,
AB10202,#1机组电动给水泵基础,30,04-10-02A,04-11-06*,
AB10203,#1机组汽动给水泵前置泵基础,30,05-03-07*,2005/4/5,
AB10204,#1机组汽动给水泵基础,40,05-07-30*,2005/9/7,
AB10205,#1机组循环水泵池及凝结水泵池施工,60,04-10-01A,2004/11/6,
AB10206,#1机组汽机房0米其它泵类基础,33,05-03-07*,2005/4/8,
AB10207,#1机组汽机房沟道施工,40,05-03-07*,2005/4/15,
AB10208,#1机组汽机房地坪施工,102,05-05-01*,2005/8/10,
AB103,#1机组汽轮发电机基础工程施工,363,04-08-14A,2005/6/30,
AB10301,#1机组汽轮发电机基础出零米,0,,04-10-31*,
AB10302,#1机组汽轮发电机机座浇注完,0,,05-06-30*,
AB10303,#1机组汽轮发电机基础底板施工,122,04-08-14A,04-09-07A,
AB10304,#1机组汽轮发电机基础-2米以下柱施工,616,04-09-10A,04-10-20A,
AB10305,3000TM塔吊使用,104,04-11-17*,2005/2/28,
AB10306,#1机组汽轮发电机基础-2米以上施工,30,05-02-25*,2005/3/26,
AB104,#1机组主厂房汽机间上部结构施工,267,04-11-01*,2005/7/25,
AB10401,#1机组主厂房结顶(断水),0,,05-04-30*,
AB10402,#1机组具备行车安装条件,0,05-02-01*,,
AB10403,#1机组汽机间上部结构梁柱吊装,76,04-12-15*,2005/2/28,
AB10404,#1机组汽机间钢屋架制作与安装,120,04-11-01*,2005/2/28,
AB10405,#1机组汽机间行车轨道及行车安装,20,05-01-19*,2005/2/7,
AB10406,#1机组汽机间屋面板施工,72,05-02-18*,2005/4/30,
AB10407,#1机组汽机间加热器平台施工,51,05-07-01*,2005/8/20,
AB105,#1机组除氧煤仓间上部结构施工,267,04-09-12A,2005/7/25,
AB10501,#1机组主厂房开始结构吊装,0,04-11-01*,,
AB10502,#1机组煤斗就位,0,,05-02-09*,
AB10503,#1机组结顶,0,,05-04-30*,
AB10504,#1机组除氧煤仓间钢煤斗制作与吊装,40,04-09-12A,2005/2/26,
AB10505,#1机组除氧煤仓间钢结构吊装,145,04-11-01*,2005/3/25,
AB10506,#1机组除氧煤仓间屋面压型板施工,60,05-03-26*,2005/5/24,
AB10507,#1机组除氧煤仓间楼梯间结构施工,60,05-03-26*,2005/5/24,
AB10508,#1机组除氧煤仓间屋面结构砼施工,20,05-04-11*,2005/4/30,
AB10509,#1机组除氧煤仓间各层平台施工,116,05-04-01*,2005/7/25,
AB106,#1机组主厂房建筑工程施工,250,05-02-25*,2005/11/1,
AB10601,#1机组主厂房封闭,0,,05-07-30*,
AB10602,#1机组主厂房质监检查,0,05-10-01*,,
AB10603,#1机组主厂房墙板围护,46,05-05-01*,2005/6/15,
AB10604,#1机组主厂房墙体砌筑,62,05-05-10*,2005/7/10,
AB10605,#1机组主厂房地面,154,05-05-01*,2005/10/1,
AB10606,#1机组主厂房门窗安装,60,05-07-01*,2005/8/29,
AB10607,#1机组主厂房墙面,63,05-07-01*,2005/9/1,
AB10608,#1机组主厂房屋面防水,15,05-05-01*,2005/5/15,
AB10609,#1机组主厂房落水管安装,20,05-08-01*,2005/8/20,
AB107,#1机组主厂房建筑设备安装工程施工,150,05-06-05*,2005/11/1,
AB10701,#1机组主厂房暖通、空调投用,0,,05-11-05*,
AB10702,#1机组主厂房消防投用,0,,06-05-01*,
AB10703,#1机组主厂房照明投用,0,,05-11-06*,
AB10704,#1机组汽机间照明,85,05-08-14*,2005/11/6,
AB10705,#1机组除氧间照明,75,05-08-13*,2005/10/26,
AB10706,#1机组煤仓间照明,80,05-09-02*,2005/11/20,
AB10707,#1机组主厂房暖气,103,05-07-26*,2005/11/5,
AB10708,#1机组主厂房给排水,91,05-08-13*,2005/11/11,
AB10709,#1机组汽机间通风空调,152,05-12-01*,2006/5/1,
AB10710,#1机组除氧间空调安装,152,05-12-01*,2006/5/1,
AB10711,#1机组汽机间消防,152,05-11-01*,2006/4/1,
AB10712,#1机组除氧间消防,152,05-11-01*,2006/4/1,
AB10713,#1机组煤仓间消防,152,05-11-01*,2006/4/1,
AB108,#1机组锅炉基础工程施工,120,04-05-15A,2004/10/30,
AB10801,#1机组锅炉基础开挖及桩头处理,75,04-05-15A,04-06-29A,
AB10802,#1机组锅炉基础承台施工,60,04-06-28A,04-08-18A,
AB10803,#1机组锅炉基础柱头施工,60,04-08-12A,04-09-04A,
AB10804,#1机组锅炉房基础回填,50,04-08-27A,04-09-15A,
AB109,#1机组锅炉房地下设施施工,337,04-10-30*,2005/10/1,
AB10901,#1机组锅炉房设备基础施工完,0,,04-09-30A,
AB10902,#1机组锅炉房浅基、浅沟、埋管施工完,0,,05-10-30*,
AB10903,#1机组锅炉房回填至设计标高,0,,04-09-30A,
AB10904,#1机组锅炉房零米毛地坪施工,0,,05-11-16*,
AB10905,#1机组送风机基础,240,04-08-18A,04-09-30A,
AB10906,#1机组一次风机基础,60,04-08-18A,04-09-30A,
AB10907,#1机组捞渣机基础,180,04-09-10A,04-09-27A,
AB10908,#1机组锅炉地下沟道施工,30,05-09-01*,2005/9/30,
AB10909,#1机组锅炉0米地面施工,15,05-12-31*,2006/1/14,
AB10910,#1机组锅炉电梯井基础,134,04-09-16A,04-10-01A,
AB110,#1机组锅炉房上部结构施工,210,05-03-06*,2005/10/1,
AB11001,锅#1机组炉房封闭,0,,06-04-23*,
AB11002,#1机组锅炉房17m运转层平台,110,05-03-06*,2005/6/23,
AB11003,#1机组锅炉房墙板封闭,60,06-02-23*,2006/4/23,
AB11004,#1机组锅炉房电梯井,235,05-03-06*,2005/10/26,
AB111,#1机组电除尘器基础,32,04-08-30A,04-09-30A,
AB11101,#1机组除尘器基础开挖及桩头处理,115,04-08-30A,04-09-06A,
AB11102,#1机组除尘器基础,0,,04-09-30A,
AB11103,#1机组除尘器基础回填,115,04-09-15A,04-10-02A,
AB112,#1机组引风机基础及支架施工,391,04-10-05A,2005/11/24,
AB11201,#1机组引风机基础基础出零米,0,,04-11-28*,
AB11202,#1机组引风机基础及支架基础施工,120,04-10-11A,2004/12/10,
AB11203,#1机组引风机支架吊装,50,05-09-11*,2005/10/30,
AB113,#1机组磨煤机基础施工,25,04-08-26A,04-10-28A,
AB11301,#1机组磨煤机基础施工,404,04-08-26A,04-10-28A,
AB11302,#1机组磨煤机基础回填,180,04-10-20A,2004/11/9,
AB114,集控楼施工,291,04-07-13A,2005/8/16,
AB11401,集控楼结构结顶,0,,05-03-31*,
AB11402,集控楼交付安装,0,,05-08-10*,
AB11403,集控楼基础施工,167,04-07-13A,04-10-01A,
AB11404,集控楼结构施工,185,04-12-01*,2005/6/3,
AB11405,集控楼建筑施工,92,05-04-23*,2005/7/24,
AB11406,集控楼装修施工,58,05-06-04*,2005/7/31,
AB11407,集控楼建筑设备安装工程,68,05-06-04*,2005/8/10,
AB11408,集控楼屋面工程,40,05-03-06*,2005/4/14,
AB115,烟囱施工,554,04-06-27A,2006/4/30,
AB11501,施工到烟道口,0,,04-11-15*,
AB11502,提升平台安装及投用,0,,04-12-20*,
AB11503,烟囱外筒砼施工到顶,0,,05-07-31*,
AB11504,烟囱竣工,0,,06-04-30*,
AB11505,烟囱基础工程,180,04-06-27A,04-08-28A,
AB11506,烟囱筒体工程,150,04-09-12A,2005/7/31,
AB11507,烟囱内衬施工,179,05-09-01*,2006/2/26,
AB11508,烟囱附属设施工程,278,04-12-01*,2005/9/4,
AB11509,烟囱收尾工程,70,06-02-20*,2006/4/30,
ABJ01,#1机组锅炉钢架安装施工,60,04-09-18A,2005/3/6,
ABJ0101,#1机组锅炉钢架开始吊装,0,04-10-03A,,
ABJ0102,#1机组锅炉钢架具承载条件,0,,05-02-25*,
ABJ0103,#1机组锅炉柱基板安装,0,04-09-18A,04-09-25A,
ABJ0104,#1机组锅炉本体钢架安装,122,04-10-03A,2005/2/11,
ABJ0105,#1机组锅炉本体平台扶梯安装,109,04-10-22A,2005/2/9,
ABJ0106,#1机组锅炉大板梁及连梁吊装,13,05-02-10*,2005/2/22,
ABJ0107,#1机组锅炉钢架整体验收复查,2,05-02-23*,2005/2/24,
ABJ02,#1机组锅炉受热面安装施工,337,04-12-09*,2005/11/10,
ABJ0201,#1机组锅炉汽包就位,0,,05-03-20*,
ABJ0202,#1机组锅炉受热面开始组合、焊第一道口,0,04-12-09*,,
ABJ0203,#1机组锅炉锅炉受热面开始吊装,0,05-03-30*,,
ABJ0204,#1机组锅炉整体水压试验1,0,,05-11-10*,
ABJ0205,#1机组锅炉汽包安装,27,05-02-27*,2005/3/25,
ABJ0206,#1机组锅炉炉顶吊挂装置,88,05-01-10*,2005/4/7,
ABJ0207,#1机组锅炉水冷系统组合安装,356,04-12-10*,2005/11/30,
ABJ0208,#1机组锅炉过热器系统组合安装,307,04-12-31*,2005/11/2,
ABJ0209,#1机组锅炉再热器系统安装,385,04-12-10*,2005/12/29,
ABJ0210,#1机组锅炉省煤器组合安装,130,05-07-24*,2005/11/30,
ABJ0211,#1机组锅炉密封,119,05-12-01*,2006/3/29,
ABJ0212,#1机组锅炉锅炉水压试验,14,06-02-09*,2006/2/22,
ABJ0213,#1机组锅炉各种金属构件安装,43,05-08-25*,2005/10/6,
ABJ0215,#1机组锅炉整体水压试验2,0,,06-03-15*,
ABJ03,#1机组锅炉附属设备安装,601,04-11-09*,2006/7/2,
ABJ0301,#1机组锅炉空预器开始安装,0,04-11-09*,,
ABJ0302,#1机组锅炉空预器安装,206,04-11-09*,2005/6/2,
ABJ0303,#1机组锅炉燃烧装置安装,363,05-03-06*,2006/3/3,
ABJ0304,#1机组锅炉吹灰装置安装,261,05-06-17*,2006/3/4,
ABJ0305,#1机组锅炉刚性梁安装,240,04-12-10*,2005/8/6,
ABJ0306,#1机组锅炉露天锅炉防护设施,214,05-12-01*,2006/7/2,
ABJ04,#1机组锅炉附属管道安装,290,05-09-15*,2006/7/1,
ABJ0401,#1机组锅炉附属设备管道,113,05-09-15*,2006/1/5,
ABJ0402,#1机组锅炉吹灰管道安装,95,05-09-22*,2005/12/25,
ABJ0403,#1机组锅炉冷却水及工业水管道,388,05-03-25*,2006/4/16,
ABJ0404,#1机组锅炉空预器碱液冲洗水箱及泵的安装,20,06-02-23*,2006/3/14,
ABJ0405,#1机组锅炉锅炉客货两用电梯安装(厂家负责),75,05-10-27*,2006/1/9,
ABJ0406,#1机组锅炉定期排污扩容器,20,05-10-01*,2005/10/20,
ABJ05,#1机组烟、风、煤等管道安装,120,04-10-10A,2006/5/12,
ABJ0501,#1机组锅炉烟风道开始制作,0,04-10-10A,,
ABJ0502,#1机组锅炉风道开始安装(临时存放),0,04-12-09*,,
ABJ0503,#1机组锅炉烟风道施工完具保温条件,0,,05-01-16*,
ABJ0504,#1机组锅炉冷风道制作安装,409,04-11-05*,2005/12/18,
ABJ0505,#1机组锅炉烟道制作安装,506,04-10-25A,2006/3/16,
ABJ0506,#1机组锅炉密封风管道安装,54,06-03-08*,2006/4/30,
ABJ0507,#1机组锅炉热风道制作安装,0,04-10-10A,2006/1/9,
ABJ0508,#1机组锅炉锅炉安全监控系统冷却风道,70,05-10-30*,2006/1/7,
ABJ0509,#1机组锅炉原煤管道安装,207,05-08-29*,2006/3/23,
ABJ0510,#1机组锅炉送粉管道安装,138,05-12-01*,2006/4/17,
ABJ06,#1机组送风机及一次风机安装施工,119,05-10-20*,2006/2/15,
ABJ0601,#1机组送风机就位,11,05-10-05*,2005/10/15,
ABJ0602,#1机组送风机本体安装,77,05-10-15*,2005/12/30,
ABJ0603,#1机组送风机附属装置安装,31,05-11-30*,2005/12/30,
ABJ0604,#1机组一次风机就位,6,05-11-05*,2005/11/10,
ABJ0605,#1机组一次风机本体安装,71,05-11-11*,2006/1/20,
ABJ0606,#1机组一次风机附属装置安装,37,06-01-10*,2006/2/15,
ABJ07,#1机组冷却风机及密封风机安装施工,88,05-11-20*,2006/2/15,
ABJ0701,#1机组冷却风机安装,25,06-03-10*,2006/4/3,
ABJ0702,#1机组密封风机安装,107,05-11-23*,2006/3/9,
ABJ08,#1机组引风机安装施工,195,05-07-20*,2006/1/30,
ABJ0801,#1机组引风机就位,11,05-07-10*,2005/7/20,
ABJ0802,#1机组引风机本体安装,60,05-07-21*,2005/9/18,
ABJ0803,#1机组引风机附属装置安装,21,05-09-20*,2005/10/10,
ABJ0804,#1机组引风机保温,12,05-10-15*,2005/10/26,
ABJ0805,#1机组引风机电气设备安装,30,05-10-28*,2005/11/26,
ABJ0806,#1机组引风机热控设备安装,85,05-10-28*,2006/1/20,
ABJ0807,#1机组引风机单体调试,11,06-01-20*,2006/1/30,
ABJ09,#1机组磨、给煤机安装施工,305,05-05-01*,2006/3/1,
ABJ0901,#1机组磨煤机本体安装,305,05-05-01*,2006/3/1,
ABJ0902,#1机组磨煤机附属装置安装,143,05-10-10*,2006/3/1,
ABJ0903,#1机组给煤机安装,145,05-07-29*,2005/12/20,
ABJ10,#1机组电除尘器安装施工,263,05-08-01*,2006/4/20,
ABJ1001,#1机组电除尘器安装完,0,,06-05-01*,
ABJ1002,#1机组电除尘升压试验完,0,,06-06-01*,
ABJ1003,#1机组电除尘本体钢结构安装,111,05-08-01*,2005/11/19,
ABJ1004,#1机组电除尘本体设备安装,62,05-12-01*,2006/1/31,
ABJ1005,#1机组电除尘附属设施及管道,32,06-02-09*,2006/3/12,
ABJ1006,#1机组电除尘保温,43,06-04-20*,2006/6/1,
ABJ1007,#1机组电除尘电气设备安装,263,05-09-05*,2006/5/25,
ABJ1008,#1机组电除尘热控设备安装,59,06-03-05*,2006/5/2,
ABJ1009,#1机组电除尘单体调试,11,06-05-05*,2006/5/15,
ABJ11,#1机组尾部烟道施工,179,04-08-15A,2006/5/1,
ABJ1101,#1机组炉后烟道基础施工完,0,,04-11-30*,
ABJ1102,#1机组炉后烟道支架,20,05-08-01*,2005/8/20,
ABJ1103,#1机组炉后烟道安装,212,05-08-21*,2006/3/20,
ABJ1104,#1机组炉后烟道保温,31,05-04-01*,2005/5/1,
ABJ12,#1机组锅炉炉墙砌筑施工,168,05-11-15*,2006/5/1,
ABJ1201,#1机组锅炉炉墙砌筑施工,168,05-11-15*,2006/5/1,
ABJ13,#1机组锅炉设备及管道保温施工,258,05-11-15*,2006/7/30,
ABJ1301,#1机组锅炉本体保温,131,06-02-23*,2006/7/3,
ABJ1302,#1机组除尘装置保温,102,06-02-23*,2006/6/4,
ABJ1303,#1机组烟风管道及风机保温,131,06-03-05*,2006/7/13,
ABJ1304,#1机组锅炉附属设备及管道保温,48,06-02-23*,2006/4/11,
ABJ14,#1机组汽轮机设备及管道保温施工,267,05-11-17*,2006/8/10,
ABJ1401,#1机组汽轮发电机附机保温,31,06-06-21*,2006/7/21,
ABJ1402,#1机组除氧给水装置保温,69,06-04-16*,2006/6/23,
ABJ1403,#1机组高压管道保温,174,05-11-17*,2006/5/9,
ABJ1404,#1机组中低压管道保温,169,06-02-23*,2006/8/10,
ABJ15,#1机组全厂油漆施工,174,06-02-23*,2006/8/15,
ABJ1501,#1机组汽水管道油漆,99,06-02-23*,2006/6/1,
ABJ1502,#1机组锅炉结构油漆,72,06-05-10*,2006/7/20,
ABJ1503,#1机组附属设备油漆,82,06-04-20*,2006/7/10,
ABJ1504,#1机组操作平台油漆,39,06-05-10*,2006/6/17,
ABJ16,#1机组汽轮机本体安装施工,290,05-10-25*,2006/8/10,
ABJ1601,#1机组汽轮机台板就位,0,05-11-10*,,
ABJ1602,#1机组汽轮机扣盖完,0,06-04-20*,,
ABJ1603,#1机组汽轮机投盘车,0,,06-07-28*,
ABJ1604,#1机组施工准备,17,05-10-25*,2005/11/10,
ABJ1605,#1机组高压缸,161,05-11-11*,2006/4/20,
ABJ1606,#1机组中压缸,161,05-11-11*,2006/4/20,
ABJ1607,#1机组低压缸,161,05-11-11*,2006/4/20,
ABJ1608,#1机组扣缸后安装,86,06-04-21*,2006/7/15,
ABJ1609,#1机组轮发电机本体保温及化装板,27,06-07-15*,2006/8/10,
ABJ17,#1机组发电机和励磁装置安装施工,243,05-12-01*,2006/7/31,
ABJ1701,#1机组发电机定子吊装,0,,05-12-20*,
ABJ1702,#1机组发电机穿转子,0,,06-02-22*,
ABJ1703,#1机组施工准备,6,05-11-15*,2005/11/20,
ABJ1704,#1机组发电机本体穿转子前安装,62,05-11-21*,2006/1/21,
ABJ1705,#1机组发电机本体穿转子后安装,90,06-02-07*,2006/5/7,
ABJ1706,#1机组发电机整套风压试验,10,06-06-26*,2006/7/5,
ABJ1707,#1机组发电机附件安装,80,06-03-27*,2006/6/15,
ABJ1708,#1机组定子线圈冷却系统,52,05-12-23*,2006/2/12,
ABJ1709,#1机组励磁装置安装,31,06-06-15*,2006/7/15,
ABJ1710,#1机组盘车装置,38,06-06-08*,2006/7/15,
ABJ18,#1机组调节和润滑油系统设备安装施工,416,05-06-08*,2006/7/28,
ABJ1801,#1机组主油箱就位,0,05-07-10*,,
ABJ1802,#1机组油循环冲洗开始,0,06-04-20*,,
ABJ1803,#1机组油质取样合格,0,,06-07-20*,
ABJ1804,#1机组汽门及调速部套安装,49,06-03-05*,2006/4/22,
ABJ1805,#1机组汽轮发电机润滑油系统管道安装,237,05-09-24*,2006/5/18,
ABJ1806,#1机组冷油器安装,33,05-06-08*,2005/7/10,
ABJ1807,#1机组集装主油箱安装,62,05-06-26*,2005/8/26,
ABJ1808,#1机组顶轴油泵安装,18,05-08-10*,2005/8/27,
ABJ1809,#1机组透平油净化装置安装,18,05-08-03*,2005/8/20,
ABJ1810,#1机组EH油装置及管道安装,64,06-01-28*,2006/4/1,
ABJ1811,#1机组密封油控制系统,76,05-12-30*,2006/3/15,
ABJ1812,#1机组贮油箱及相关管道安装,25,05-09-24*,2005/10/18,
ABJ19,#1机组电动给水泵安装,130,05-08-04*,2005/12/11,
ABJ1901,#1机组电动给水泵组就位,0,05-09-01*,,
ABJ1902,#1机组电动给水泵组安装,119,06-01-02*,2006/4/30,
ABJ1903,#1机组电动给水泵组附件安装,61,06-05-01*,2006/6/30,
ABJ20,#1机组汽动给水泵安装,192,05-10-10*,2006/4/19,
ABJ2001,#1机组A汽动给水泵就位,0,05-10-10*,,
ABJ2002,#1机组A汽动给水泵本体安装,110,06-01-11*,2006/4/30,
ABJ2003,#1机组A汽动给水泵附件安装,61,06-05-01*,2006/6/30,
ABJ2004,#1机组B汽动给水泵就位,0,05-10-10*,,
ABJ2005,#1机组B汽动给水泵本体安装,110,06-01-11*,2006/4/30,
ABJ2006,#1机组B汽动给水泵附件安装,61,06-05-01*,2006/6/30,
ABJ21,#1机组凝汽器安装施工,191,05-07-01*,2006/1/7,
ABJ2101,#1机组凝汽器壳体就位安装,0,05-10-15*,,
ABJ2102,#1机组凝汽器组合,92,05-07-01*,2005/9/30,
ABJ2103,#1机组凝汽器安装,41,05-10-01*,2005/11/10,
ABJ2104,#1机组凝汽器附件安装,20,05-11-11*,2005/11/30,
ABJ2105,#1机组凝汽器内部有关管道安装,31,05-12-01*,2005/12/31,
ABJ2106,#1机组凝汽器第一次灌水试验,7,06-01-01*,2006/1/7,
ABJ22,#1机组除氧器安装施工,268,05-01-02*,2005/9/27,
ABJ2201,#1机组除氧器及水箱就位,0,,2005/2/5,
ABJ2202,#1机组除氧器就位,8,05-01-05*,2005/2/5,
ABJ2203,#1机组除氧器本体安装,18,05-07-13*,2005/7/30,
ABJ2204,#1机组除氧器附件及厂供管道安装,41,05-08-01*,2005/9/10,
ABJ23,#1机组高、低压加热器施工,123,05-05-20*,2005/9/19,
ABJ2301,#1机组高压加热器就位安装开始,0,05-06-20*,,
ABJ2302,#1机组低压加热器就位安装开始,0,05-05-20*,,
ABJ2303,#1机组高加就位,0,05-06-20*,,
ABJ2304,#1机组高加安装,25,05-06-21*,2005/7/15,
ABJ2305,#1机组高加附件及厂供管道安装,42,05-06-30*,2005/8/10,
ABJ2306,#1机组低加就位,0,05-07-01*,,
ABJ2307,#1机组低加安装,41,05-07-01*,2005/8/10,
ABJ2308,#1机组低加附件及厂供管道安装,47,05-07-10*,2005/8/25,
ABJ24,#1机组汽机附属设备安装,443,05-04-01*,2006/6/17,
ABJ2401,#1机组轴封加热器安装,17,05-08-25*,2005/9/10,
ABJ2402,#1机组真空泵安装,46,05-08-01*,2005/9/15,
ABJ2403,#1机组凝结水补充水泵安装,25,05-08-01*,2005/8/25,
ABJ2404,#1机组凝结水补充水箱安装,56,05-08-15*,2005/10/9,
ABJ2405,#1机组胶球清洗装置,28,05-11-22*,2005/12/19,
ABJ2406,#1机组水—水热交换器安装,26,05-07-26*,2005/8/20,
ABJ2408,#1机组连续排污扩容器,20,05-07-11*,2005/7/30,
ABJ2409,#1机组汽机附属设备平台、扶梯安装,40,05-07-29*,2005/9/6,
ABJ2410,#1机组柴油发电机安装,60,05-09-01*,2005/10/30,
ABJ25,#1机组高压管道施工,268,05-07-14*,2006/4/7,
ABJ2501,#1机组四大管道参加水压试验,0,05-11-15*,,
ABJ2502,#1机组高、低旁路系统管道,212,05-08-01*,2006/2/28,
ABJ2503,#1机组再热(冷段)蒸汽管道,212,05-08-01*,2006/2/28,
ABJ2504,#1机组高压给水管道,102,05-08-01*,2005/11/10,
ABJ2505,#1机组再热(热段)蒸汽管道,212,05-08-01*,2006/2/28,
ABJ2506,#1机组主蒸汽管道,199,05-08-01*,2006/2/15,
ABJ2507,#1机组给水泵再循环管道,47,05-09-25*,2005/11/10,
ABJ2508,#1机组减温水管道,162,05-09-25*,2006/3/5,
ABJ26,#1机组中、低压管道施工,377,05-07-02*,2006/7/13,
ABJ2601,#1机组辅助蒸汽管道,101,05-07-26*,2005/11/3,
ABJ2602,#1机组闭式循环冷却水管道,142,05-08-05*,2005/12/24,
ABJ2603,#1机组凝结水管道,99,05-08-25*,2005/12/1,
ABJ2604,#1机组抽汽管道,290,05-09-27*,2006/7/13,
ABJ2605,#1机组发电机定子冷却水管,57,05-12-19*,2006/2/13,
ABJ2606,#1机组加热器疏放水管道,228,05-08-12*,2006/3/27,
ABJ2607,#1机组除盐水管道,30,05-11-07*,2005/12/6,
ABJ2608,#1机组中低压给水管道,78,05-08-15*,2005/10/31,
ABJ2609,#1机组连排至除氧器加热蒸汽管道,24,05-08-21*,2005/9/13,
ABJ2610,#1机组给水泵汽轮机高压进汽管道,86,06-02-04*,2006/4/30,
ABJ2611,#1机组给水泵汽轮机低压进汽管道,92,06-02-07*,2006/5/9,
ABJ2612,#1机组开式循环水管道,67,05-07-02*,2005/9/6,
ABJ2613,#1机组生活服务用水管道,75,05-07-07*,2005/9/19,
ABJ2614,#1机组循环水(汽机房)管道,57,05-11-07*,2006/1/2,
ABJ2615,#1机组轴封系统管道,57,05-08-31*,2005/10/26,
ABJ2616,#1机组压缩空气管道,48,05-09-23*,2005/11/9,
ABJ2617,#1机组辅助蒸汽系统管道,83,05-10-14*,2006/1/4,
ABJ2618,#1机组胶球冲洗系统,20,05-11-25*,2005/12/14,
ABJ2619,#1机组凝结水疏水系统管道,22,05-10-11*,2005/11/1,
ABJ2620,#1机组加热器排空管道,22,05-11-11*,2005/12/2,
ABJ2621,#1机组抽汽系统管道,47,06-05-08*,2006/6/23,
ABJ2622,#1机组给水泵辅助系统,16,05-11-01*,2005/11/16,
ABJ2623,#1机组加热器疏放水系统管道,129,05-11-07*,2006/3/15,
ABJ2624,#1机组闭式水热交换器胶球清冼管道,33,05-08-08*,2005/9/9,
ABJ2625,#1机组加药系统,19,05-11-29*,2005/12/17,
ABJ2626,#1机组机房氢气管道,15,06-01-26*,2006/2/9,
ABJ2627,#1机组服务用水系统,10,05-08-23*,2005/9/1,
ABJ2628,#1机组取样系统,23,05-12-02*,2005/12/24,
ABJ2629,#1机组抽真空系统,20,05-09-16*,2005/10/5,
ABJ2630,#1机组冷却水系统,10,05-11-11*,2005/11/20,
ABJ2631,#1机组凝结水杂项系统管道,95,05-10-20*,2006/1/22,
ABJ27,#1机组汽轮机本体定型设计管道施工,88,06-04-21*,2006/7/17,
ABJ2701,#1机组汽机本体导汽管,76,06-05-01*,2006/7/15,
ABJ2702,#1机组汽机本体疏水管道,40,06-05-13*,2006/6/21,
ABJ2703,#1机组汽机本体杂项管道,43,06-05-16*,2006/6/27,
ABJ28,#1机组旁路系统设备安装施工,213,05-10-20*,2006/5/20,
ABJ2801,#1机组旁路系统设备安装施工,213,05-10-20*,2006/5/20,
ABJ29,#1机组全厂检修起吊设施施工,547,05-01-30*,2006/7/30,
ABJ2901,#1机组汽机房行车就位,0,,2005/3/10,
ABJ2902,#1机组汽机房行车安装,30,05-01-30*,2005/3/10,
ABJ2903,#1机组锅炉房检修起吊设施,190,05-04-30*,2005/11/5,
ABJ2904,#1机组其它起重设备安装,366,05-07-30*,2006/7/30,
ABY01,#1机组设备及系统分部试运转,147,06-03-01*,2006/7/25,
ABY0101,#1机组分部试运开始,0,06-03-01*,,
ABY0102,#1机组锅炉,95,06-03-15*,2006/6/18,
ABY0103,#1机组汽机,123,06-03-01*,2006/7/1,
ABY0104,#1机组电气,105,06-03-25*,2006/7/8,
ABY0105,#1机组热控,80,06-04-17*,2006/7/6,
ABY02,#1机组锅炉整体风压试验,43,06-05-19*,2006/6/30,
ABY0204,#1锅炉本体风压试验,43,06-05-19*,2006/6/30,
ABY03,#1机组化学清洗,41,06-06-20*,2006/7/30,
ABY0301,#1机组炉前及锅炉化学清洗完,0,,2006/7/10,
ABY0302,#1机组凝汽器碱洗,0,,06-06-25*,
ABY0303,#1机组炉前及锅炉化学清洗,21,06-06-20*,2006/7/10,
ABY0304,#1机组系统恢复,20,06-07-11*,2006/7/30,
ABY04,#1机组蒸汽冲管,22,06-07-30*,2006/8/20,
ABY0401,#1机组锅炉点火冲管开始,0,06-07-30*,,
ABY0402,#1机组蒸汽吹管,7,06-07-30*,2006/8/5,
ABY0403,#1机组系统恢复,15,07-08-06*,2007/8/20,
ABY05,#1机组整套启动,13,06-08-20*,2006/9/1,
ABY0501,#1机组具整套启动条件,0,06-08-20*,,
ABY0502,#1机组并网发电,0,,06-09-01*,
ABY0503,#1机组整组启动,3,06-08-20*,2006/8/22,
ABY0504,#1机组冲转,3,06-08-23*,2006/8/25,
ABY0505,#1机组相关试验,6,06-08-26*,2006/8/31,
ABY06,#1机组带负荷试运,60,06-09-01*,2006/10/30,
ABY0601,#1机组开始带负荷试运,0,06-09-01*,,
ABY0605,#1机组完成168考核,0,,2006/10/30,
ABY0606,#1机组系统消缺,11,06-09-16*,2006/9/26,
ABY0607,#1机组带负荷试运,15,06-09-01*,2006/9/15,
ABY0608,#1机组满负荷试运,35,06-09-26*,2006/10/30,
燃料供应系统,,167,2005/9/15,2006/2/28,
AB201,固定端输煤栈桥,167,05-09-15*,2006/2/28,
AB20101,固定端输煤栈桥交付安装,0,,06-01-06*,
AB20102,#7输煤栈桥基础施工,31,05-09-15*,2005/10/15,
AB20103,#7输煤栈桥结构,62,05-10-16*,2005/12/16,
AB20104,#7输煤栈桥封闭,59,06-01-01*,2006/2/28,
除灰系统,,608,2004/12/1,2006/7/31,
AB301,#1机组渣仓施工,117,05-09-05*,2005/12/30,
AB30101,#1机组渣仓基础施工,31,05-09-05*,2005/10/5,
AB30102,#1机组渣仓结构,36,05-10-06*,2005/11/10,
AB30103,#1机组渣仓制作与安装,72,05-04-10*,2005/6/20,
AB30104,#1机组渣仓设备安装,51,05-11-11*,2005/12/31,
AB302,#1机组沉清与回收水池施工,47,05-03-05*,2005/4/20,
AB30201,沉清与回收水池结构施工,14,05-03-07*,2005/3/20,
AB30202,#1机组沉清与回收水池防腐及设备安装,30,05-03-22*,2005/4/20,
AB303,除灰控制楼施工,395,04-12-01*,2005/12/30,
AB30301,除灰控制楼基础出0m,0,,04-12-30*,
AB30302,除灰控制楼交付安装,0,,05-11-30*,
AB30303,除尘控制楼地下结构施工,36,04-12-01*,2005/1/6,
AB30304,除尘控制楼上部结构施工,60,05-08-01*,2005/9/29,
AB30305,除尘控制楼建筑,80,05-09-30*,2005/12/18,
AB30306,除尘控制楼装饰,40,05-11-04*,2005/12/13,
AB30307,除尘控制楼建筑设备安装工程,40,05-11-04*,2005/12/13,
AB30308,除灰控制楼机务设备及管道安装,60,05-12-01*,2006/1/29,
AB30309,除灰控制楼电气设备安装,40,06-02-10*,2006/3/21,
AB30310,除灰控制楼热控设备安装,90,06-02-10*,2006/5/10,
AB30311,除灰控制楼调试,50,05-11-05*,2005/12/24,
AB304,#1机组锅炉出灰、渣系统安装,312,05-09-23*,2006/7/31,
AB30401,#1机组捞渣机安装,10,05-09-30*,2005/10/9,
AB30402,#1机组渣仓设备安装,37,05-10-05*,2005/11/10,
AB30403,#1机组锅炉出灰、渣系统电气及控制设备安装,30,05-11-10*,2005/12/9,
AB30404,#1机组锅炉出灰、渣系统调试,225,05-12-17*,2006/7/29,
水处理系统,,356,2005/9/1,2006/8/22,
ABS01,凝结水精处理及再生装置公用部分施工,356,05-09-01*,2006/8/22,
ABS0101,凝结水精处理及再生间交付安装,0,05-09-01*,,
ABS0102,凝结水精处理系统投用,0,,06-08-20*,
ABS0103,凝结水精处理及再生装置公用部分机务设备及管道安装,198,05-09-03*,2006/3/19,
ABS0104,凝结水精处理及再生装置公用部分电气,95,05-12-10*,2006/3/14,
ABS0105,凝结水精处理及再生装置公用部分热控设备安装,180,05-10-05*,2006/4/3,
ABS0106,凝结水精处理及再生装置公用部分调试,138,06-04-03*,2006/8/19,
ABS02,#1机组凝结水精处理及再生装置施工,304,05-09-20*,2006/7/20,
ABS0201,#1机组精处理装置安装,195,05-09-20*,2006/4/3,
ABS0202,#1机组精处理装置调试,151,06-02-20*,2006/7/20,
ABS03,#1机组化学取样及加药系统施工,304,05-09-20*,2006/7/20,
ABS0301,#1机组化学取样站设备安装及调试,306,05-09-17*,2006/7/20,
ABS0302,#1机组化学取样相关管道安装,159,05-12-24*,2006/6/1,
电气系统,,656,04-09-30A,2006/8/10,
AB601,#1机组A列外基础及构筑物施工,132,05-04-01*,2005/8/10,
AB60101,#1机组A列外基础施工,132,05-04-01*,2005/8/10,
AB60102,#1机组A列外防火墙施工,50,05-04-01*,2005/5/20,
AB60103,#1机组A列外事故油池施工,80,05-03-01*,2005/5/19,
AB60104,#1机组A列外架构施工,10,05-06-24*,2005/7/3,
ABD01,#1机组主变压器及高压厂用变压器施工,104,05-06-20*,2005/10/1,
ABD0101,#1机组A列外主变就位,0,05-06-20*,,
ABD0102,#1机组A列外厂高变吊装就位,0,05-06-25*,,
ABD0103,#1机组A列外主变就位,10,05-06-15*,2005/6/24,
ABD0104,#1机组A列外主变压器安装,47,05-07-24*,2005/9/8,
ABD0105,#1机组A列外厂高变就位,10,2005/8/2,05-08-11*,
ABD0106,#1机组A列外厂高变安装,9,05-07-24*,2005/8/1,
ABD02,#1机组启动/备用变压器施工,104,05-06-15*,2005/9/26,
ABD0201,#1机组A列外启备变吊装就位,0,05-06-15*,,
ABD0202,#1机组A列外启动变就位,10,05-06-15*,2005/6/24,
ABD0203,#1机组A列外启动变安装,110,05-06-09*,2005/9/26,
ABD03,#1机组6KV工作及公用配电室施工,133,05-09-20*,2006/1/30,
ABD0301,#1机组6KV工作及公用配电室交付安装,0,05-09-20*,,
ABD0302,#1机组6KV开关室受电,0,06-01-30*,,
ABD0303,#1机组6KV工作及公用配电室建筑与装修,27,05-08-25*,2005/9/20,
ABD0304,#1机组6KV高压配电装置盘柜安装,113,05-09-30*,2006/1/20,
ABD0305,#1机组厂用分支母线安装,133,05-09-10*,2006/1/20,
ABD0306,#1机组封母安装,133,05-09-10*,2006/1/20,
ABD0307,#1机组#1机组厂用电系统调试,58,05-12-07*,2006/2/2,
ABD04,#1机组400V工作及公用配电室施工,133,05-09-20*,2006/1/30,
ABD0401,#1机组400V工作及公用配电室交付安装,0,05-09-20*,,
ABD0402,#1机组400V工作、公用、保安段受电,0,,06-01-30*,
ABD0403,#1机组400V主厂房外低压厂变受电,0,,06-01-30*,
ABD0404,#1机组400V工作及公用配电室建筑与装修,51,05-08-01*,2005/9/20,
ABD0405,#1机组厂用低压配电装置安装,154,05-08-10*,2006/1/10,
ABD0406,#1机组厂用低压变压器安装,154,05-08-10*,2006/1/10,
ABD05,#1机组厂区直流系统施工,46,05-08-17*,2005/10/1,
ABD0501,#1机组110V蓄电池组安装,30,05-08-17*,2005/9/15,
ABD0502,#1机组220V蓄电池组安装,40,05-08-17*,2005/9/25,
ABD06,#1机组发电机电气与引出线安装施工,228,05-12-21*,2006/8/5,
ABD0601,#1机组封闭母线开始安装,0,06-04-22*,,
ABD0602,#1机组发电机电气与出线间设备,178,05-12-05*,2006/5/31,
ABD0603,#1机组主回路母线安装,144,06-01-28*,2006/6/20,
ABD0604,#1机组励磁回路母线安装,95,06-02-18*,2006/5/23,
ABD07,#1机组全厂电缆施工,441,05-04-01*,2006/6/15,
ABD0701,#1机组电缆沟道,电缆桥架施工完,0,,05-11-30*,
ABD0702,#1机组全厂电缆开始敷设,0,05-04-01*,,
ABD0703,#1机组电缆敷设完,0,,06-04-10*,
ABD0704,#1机组厂用系统电缆敷设完,0,,05-12-25*,
ABD0705,#1机组A列外电缆沟施工,32,05-05-01*,2005/6/1,
ABD0706,#1机组电缆桥架制作安装,422,04-12-13*,2006/2/7,
ABD0707,#1机组锅炉区域电缆安装,216,05-07-20*,2006/2/20,
ABD0708,#1机组汽机房区域电缆安装,212,05-10-14*,2006/5/13,
ABD0709,#1机组主厂房高、低压厂用电系统电缆安装,73,05-11-03*,2006/1/14,
ABD0710,#1机组集控楼及电气楼过盘电缆安装,92,05-10-17*,2006/1/16,
ABD0711,#1机组发变组系统电缆安装,147,05-11-28*,2006/4/23,
ABD0712,#1机组控制系统电缆安装,25,05-12-01*,2005/12/25,
ABD0713,#1机组直流及保安系统电缆安装,25,05-12-01*,2005/12/25,
ABD0714,#1机组电缆辅助防火封堵设施安装,150,06-01-17*,2006/6/15,
ABD08,#1机组全厂电气设备安装施工,492,05-03-02*,2006/7/6,
ABD0801,#1机组6KV高压厂用电机检查,60,05-11-04*,2006/1/2,
ABD0802,#1机组汽机车间配电装置安装,173,05-08-15*,2006/2/3,
ABD0803,#1机组锅炉车间配电装置安装,148,05-08-27*,2006/1/21,
ABD0804,#1机组电除尘电气设备安装,84,05-12-29*,2006/3/22,
ABD0805,#1机组照明段配电装置安装,27,05-09-25*,2005/10/21,
ABD0806,#1机组保安电源安装,128,05-09-30*,2006/2/4,
ABD0807,#1机组主厂房起重设备电气安装,212,05-02-14*,2005/9/13,
ABD10,#1机组柴油发电机施工,59,05-08-17*,2005/10/14,
ABD1001,#1机组柴油发电机就位,0,,05-08-17*,
ABD1002,#1机组柴油发电机安装,60,05-08-18*,2005/10/16,
ABD1003,#1机组柴油发电机单体调试,215,2004/10/30,2005/6/1,
ABD11,#1机组全厂防雷及接地施工,551,04-09-30A,2006/5/3,
ABD1101,#1机组屋外接地母线敷设,442,04-10-30*,2006/1/14,
ABD1102,#1机组室内接地母线敷设,90,05-01-13*,2005/4/12,
ABD1103,#1机组设备接地,405,05-01-23*,2006/3/3,
ABD1104,#1机组避雷针接地装置安装,35,05-04-19*,2005/5/23,
ABD12,#1机组设备及构筑物照明安装施工,279,05-06-17*,2006/3/22,
ABD1201,#1机组锅炉本体照明,120,05-06-17*,2005/10/14,
ABD1202,#1机组电除尘本体照明,30,06-02-21*,2006/3/22,
ABD13,#1机组全厂通讯、呼叫系统安装施工,346,05-08-30*,2006/8/10,
ABD1301,#1机组全厂通讯、呼叫系统主厂房区域盘柜安装,163,05-08-01*,2006/1/10,
ABD1302,#1机组全厂通讯、呼叫系统主厂房区域就地装置施工,375,05-08-01*,2006/8/10,
ABD1303,#1机组全厂通讯、呼叫系统主厂房区域线路施工,335,05-09-10*,2006/8/10,
ABD1304,#1机组全厂通讯、呼叫系统输煤区域,271,05-08-01*,2006/4/28,
ABD1305,#1机组全厂通讯、呼叫系统厂前区,335,05-09-10*,2006/8/10,
ABD14,220KV配电装置施工,314,05-02-15*,2005/12/25,
ABD1401,220KV配电装置交付安装,0,,05-05-21*,
ABD1402,220KV配电装置受电,0,,05-12-26*,
ABD1403,220KV配电装置基础施工,46,05-03-01*,2005/4/15,
ABD1404,220KV配电装置结构,31,05-04-15*,2005/5/15,
ABD1405,220KV配电装置建筑与装修,37,05-05-25*,2005/6/30,
ABD1406,220KV配电装置设备安装,163,05-07-01*,2005/12/10,
ABD1407,220KV配电装置进出线安装,112,05-08-21*,2005/12/10,
ABD1408,220KV配电装置调试,25,05-12-01*,2005/12/25,
热工控制系统,,436,2005/6/11,2006/8/20,
ABK01,#1机组控制系统(DCS)设备安装施工,139,05-07-30*,2005/12/15,
ABK0101,#1机组DCS进盘,0,05-07-30*,,
ABK0102,#1机组DCS复原试验完,0,,05-12-30*,
ABK0103,#1机组DCS系统盘柜安装,16,05-08-17*,2005/9/1,
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 现金赎楼服务合同还款时间及费用说明
- 旅游活动赞助商合同
- 商业印刷品购买协议
- 私人借款协议范本在线
- 装饰合同补充细则
- 借款协议与担保合同
- 仓储物流信息管理系统合作协议
- 设计合作终止协议解除合同条件
- 现房车库买卖合同范本
- 租房质量承诺
- 蓝色商务风汽车行业商业计划书模板
- DB21T 2748-2017 拉氏鱥池塘养殖技术规范
- 苏州大学《高等数学一》2022-2023学年第一学期期末试卷
- 运河镇江段航道疏浚工程环评资料环境影响
- 2024年心理咨询师考试题库【典型题】
- 2024年江西省公务员考试《行测》真题及答案解析
- 中药药剂学智慧树知到答案2024年中国药科大学
- 军事理论-综合版智慧树知到期末考试答案章节答案2024年国防大学
- 湖南省义务教育学校教师工作量参考标准
- 极端天气应急预案.doc
- 双门通道控制
评论
0/150
提交评论