HIGHWAYPROJECT
LIABILITYRISKANDEXPOSUREMANAGEMENT
PresentationOutlineLiabilityTerminologyRisksduetoProjectScopeandProjectManagementRisksinDesign-BuildProjectsContractLiabilityLimitsClaimsClassificationClaimsAdministrationLessonsLearnedforClaimResolutionLIABILITYTERMINOLOGYLiabilityTerminologyinThisPresentationLiability:Contractor’sresponsibilityfordamagescausedbyactionsdonebyClient,thirdparties,ornature.Sowearenottalkingaboutcontractor’scontractualresponsibilitiesforprojectexecution.ButwearetalkingaboutsituationswhereContractoriscalledtobeliablewhileheshouldnotbe.LiabilityRisk:Probableandpotentialsituations(events)leadingtoContractor’sliabilityLiabilityExposure:AmountoflosscausedtoContractorduetoaliability(situation)LiabilityRiskManagementDefineContractlimits(allparties’responsibilitiesandrights)MinimizeContractor’sliabilityrisks(delays,disruptions,prolongations,andadditionalcosts)ReduceContractor’sliabilityexposure(latecompletionandadditionalcosts)ClaimforExtensionOfTime(EOT)andAdditionalCostsDisputeClientclaimsDisputesub-contractorsclaimsFileinsuranceclaimsProjectRisks
ClientandContractorCompletionRiskDelayincompletionDelayinClientrevenueoperationProjectcostoverrunincompletionFinancingRiskRevenueRiskPoliticalRiskForceMajeureRiskPartneringRiskRISKSDUETO
PROJECTSCOPEandPROJECTMANAGEMENTPROJECTSCOPE40-monthprojectstartedinSeptember2006528kmoftollroadMorethan950bridgesincludingoverpasses,underpasses,junctions,andelevatedbridges2Tunnels132x106m3ofearthworksRegionNo.OfSegmentsApplicationContractsDesignTeamsConstructionTeamsCenter7(M1toM7)334West9(W1toW9)335ProjectExecutionArrangementProjectManagementCharacteristicsAdesign-buildprojectFastTrackAlignmentispartlypre-defined.ClientisDPNrepresentingtheAlgerianGovernment’sMinistryofPublicWorks.Therearealso10Willayaswiththeirowngoverningbodiesandauthorities.ProjectManagementCharacteristicsNottoexcludeotherAlgerianministriesinvolveddueto:InfrastructuresimpactsWorkforcerequirementMaterialsinquiryImportingLandacquisitionEnvironmentimpactsSecurityneedsLiabilitycoverageContractRequirementsContractorisresponsibleforFinalDesignandtheContract:RequirestheConstructedworkstobeof“bestQuality”SetsouttheClient’sdesignreviewprocessanddefinesresponsibilitiesoftheContractor’sExternalControlTeamProvidesaschematicQualityPlanHasSpecialTechnicalSpecificationsbutdoesnotdefinedetaileddesignspecificationsProvidesforsomesegmentstheClient’sGeometricDesignDrawingsContractorOrganizationTheClientOrganizationClientManagementIdealClientattitudeGovernmentContractManagementTargetandcostorientedIdeal&GovernmentalFraud/corruptionpreventionOriented.PublicwelfareisprimaryconcernDesignApproval“SONO”byDPN.ContractortakesthemainResponsibilityIdeal“Approval”byGovernment.Governmentshareresponsibility.FastTrackingConstructionisallowedunderconditionsifDesigndoesnotget“SONO”GovernmentalConstructionisnotallowedifdesignisnotyetapprovedDefectorDeviationNegotiation/promptsolutionHopefullymoreideal&lessGovernmentalIdentifyresponsibility.Lengthyprocedure.Hesitatetomakedecisions.Itispublicservant'sattitude.TheClientManagementDPNisanewlyformedorganizationwithintheMinistryofPublicWorks.DPNhasnodesign-buildmanagementexperienceandpracticeformajortransportationprojects.BesideGovernmentalandPoliticalobligations,DPNhasnootherincentive.RISKSin
DESIGN-BUILDPROJECTSDesign-BuildContractMainpartoftheriskiswiththeJV.Alump-sum-priceorunit-rates-based-pricecontractConstructionexpertiseincorporatedduringdesignphaseleadingto‘constructible’designsContractorincontrolandWorkonSitecanstartearlierthanmoretraditionalprocurementroutesExpectationtodeliverontimeandwithinbudgetClientinstructedchangeslikelytoincurhighcostandnegativeaffectstothetimeforcompletion3R’sofDesign-BuildProjectsRisksResponsibilitiesRelationshipsDesign-BuildProjectsRisk-SharingFullRiskCostofdesignDesignliabilityChangesinsubcontractorpricesDelaysSharedRisk/NoRiskAlignmentdesignRiskofobtainingpermitsRight-of-WayacquisitionUtilityrelocationsQuantitygrowthSecurityDifferingsiteconditionsChangesingovernmentallawHazardouswasteEnvironmentalapprovalsDesign-BuildProjectsResponsibilitiesDesigncoordinationConstructabilityreviewsDesignQC/QAConstructionQC/QADesignservicesduringconstructionDefectscorrectionafterconstructionDesign-BuildProjectsRelationshipsContractCo-LocationofContractor/Designer/ClientClient/ContractorContractor/DesignerPartneringCONTRACTLIABILITYLIMITS(MainItems)GoverningLawConventionsA1TheContractshallbegovernedbyandconstruedinallrespectsaccordingtoeffectivelawsandlegislationsinHostCountrybeinginforceatthetimeoftender.CCAPA75AllprovisionsintheContractwhichareagainstthelawsandregulationsinAlgeriashallbedeemedasineffective.Civillaw(Order75-58,26September1975)Civillitigationlaw(Order66-154,8June1966)Publiccontractsregulations(Decree02-250,24July2002)Commerciallaw(Order75-59,26September1975)Biddingregulations(Order03-03,19July2003)Insurancelaw(Order95-07,25January1995)Taxlaws(Order2000-06,23December2000)Invoicepreparationregulations(Decree95-305,7October1995)CCAGforpubliccontracts(21November1964)MaterialquarryingregulationsLaborandforeignworkerslawsEnvironmentalregulationsCustomlawsSecuritylawsContractCeilingPriceConventionsA15WestandCenterContractshaveceilingpricesnotincluding:PriceadjustmentduetoinflationAdditionalcostsforclaimsrelatedto:DelaysforapprovingAPSandAPDofCategoryIIILandacquisitionandutilitiesrelocationGettingpermitsDelaysforimportinggoodsSupplementedworksLateCompletionPenaltyConventionsA8TheContractdurationof40months(startedfromSeptember2006)isforApplicationContractsNo.1,2,and3.CCAPA50.1LatehandoverPenaltiesareappliedaccordingtotheContractSchedulewithoutanypriornotification.Note:Noliquidateddamageschargeforlatecompletion.ConventionsA27impliessamepenalties.ContractProlongationConventionsA8.2IfanyreasonattributedtoClientortoanybodyassignedorhiredbyhimindirectlyordirectlycausesContractordelayinplannedexecution,theContractperiodshouldberationallyprolongedfortimeagreedbythebothparties.TheadditionalcosttoContractorduetothisdelayshouldbecompensatedbyClient.DelaysResolutionCCAPA49.3WhenResidentEngineer(RE)assessesthattheactualworkprogressisdelayedevenwithcontractoracceleratingmeasures,heshallrequireacatch-upplanfordelays.ShouldContractorfailtoprovideasatisfactoryplanwithin10days,REmaydisapprovethetemporarybilloftheverymonthuntilasatisfactoryplanisprovided.REmaysuggesttoClienttoapplydelaypenalties.ProductQualityCCAPA7Constructionqualityshallatnotimebereducedundertheconditionthattheconstructionscheduleandspeedarewarranted.Theguaranteeofconstructionqualityshallbeabsolute.CCAPA14Contractorshallbetheonlypartyresponsibleforconstructionquality.APDDocumentsCCAPA19.1Thedetailpreliminarydesign(APD)providedtotheContractorbytheClientshallnotrelievetheContactorofanyresponsibility.Contractorshallnotshifthisresponsibilitiesonthepretextofcertainmistakesandomissionsinthedrawings.ForceMajeureCCAPA55.1&ConventionsA39ForceMajeureshallmainlymean:Wars,Invasions,hostileactions,mobilization,confiscationAllresultsofanucleareventSeriousanarchyinpublicorderCCAPA55.1EvenincaseofForceMajeure,theentireorpartiallossesofContractor’sequipmentsshallnotbereimbursedsincetheinsurancechargesforthesaidequipmentsarealreadyincludedinthecontractprices.CCAPA55.2ProlongationofconstructionperiodIncaseofForceMajeureaffirmedbybothparties,theyshallnegotiateontheprolongationoftheconstructionperiod.ConventionsA39requiresthesame.ExceptedRisksConventionsA12.1Ifdamagesorlossesoccurduetofollowingrisks,ContractorshouldimmediatelyinformClientandrectifythedamagesifClientrequires.Contractorisentitledtoprolongationandtocompensationforadditionalcosts.War,invasionRevolution,militarycoup,civilwarRiotsExplosives,radioactivitySupersonicpressurewaveUseoroccupationofapartorwholeofawork,tunnel,bridgestructurebytheClientwithoutagreementofbothpartiesDesignofallpartsofaworkbyClientNaturaldisastersSevereWeatherCCAPA56:SevereWeather–ProlongationofConstructionPeriodThepredictablesevereweathereachyearisspecifiedto20days.Flood,severerainfall,andstrongwindsarementionedinthecontractforspecificworksinadditiontoothernaturalphenomena.Theprolongationisdeterminedbasedonthespreadofsevereweatherimpact.InsuranceCCAPA28Contractorprovides:TransportinsuranceforimportedgoodsThirdpartycivilliabilityinsuranceOccupationalaccidentinjuryinsuranceInsuranceforsiteworksbeforecommencementCCAPA28.6ShouldContractorfailtosignormaintaininsurance,Clientshallsignormaintaininsuranceandtherelativeexpensesshallbedeductedfromconstructionbills.ConventionsA12.2requiressimilarinsurances.DefectsLiabilityCCAPA27PerREinstruction,ContractorshallreplacetheproductsnotconformingtotherequirementsofCCTP,drawings,andworkinstructions.Theinstructionshallsetadelayofexecution.CCAPA69.1Thedurationofthedefectsliabilityperiodshallbeoneyearandcountedfromtheprovisionalcompletionacceptance.CCAPA64PerformanceGuaranteeContractorsubmittedaperformanceguaranteeequalto10%ofthetotalvalueoftheContract.Thisguaranteeshallbetransformedtoqualityguaranteeafterprovisionalcompletionacceptance.OtherLiabilityRisksSecurityLatepaymentsPriceadjustmentsDamagesto:EnvironmentNearbystructuresandresidentsOtherprojectsUtilitiesRoadsandrailroadsLabTestsSubcontractingNightworksLabordisputesMaterialsquarryArchaeologicalfindingsConfidentialityPatentsFinancingCCAPA67ContractMortgageThisApplicationContractshallbemortgageable.TheaccountingserviceinchargeofpaymentshallbeBanqueAlgéériennedeDéveloppement.TerminationCCAPA71.1EachPartyisentitledtopartiallyorcompletelydissolvetheContractundertheCaseofForceMajeurewhensuspensionexceeds180daysorthenatureofForceMajeureleadstotermination.CCAPA71.2TerminationinCaseofContractor’sfaultsSubcontractingofworkswithoutClientpriorapprovalBankruptcyorlegalliquidationDeathofContractorFailuretomitigatedefectswithinthegiventimelimitSettlementofDisputesCCAPA72ShouldthetwopartiesfailtosettlethedisputewithfriendlynegotiationortheverdictmadebyNationalContractCommitteearenotacceptedbytheContractor,thedisputeshallbesubmittedtoanarbitrationcourt.ConventionsA48ThegoverninglawisAlgerialaw.CLAIMSCLASSIFICATIONClaimNaturesAnEOTclaimshouldbefiledforaneventaffectingthesubstantialcompletionofthewholeoftheWorksorSection.AnAdditionalCostclaimshouldbefiledwheneveraneventcausescostincludingallexpenditure,includingdesigncosts,whollyandnecessarilyincurred,whetheronorofftheSite,overheads,depreciationinContractor’sEquipment,financecostsandotherchargesproperlyallocablethereto,butdoesnotincludeanyallowanceforprofit.ClaimsClassificationBasedonClaimNature:EOT(ExtensionOfTime)AdditionalCostBoth(EOTandCost)BasedonApplicationContracts:ApplicationContractNo.1ApplicationContractNo.2ApplicationContractNo.3ClaimsClassificationBasedonSectionandSubsections:CenterorWestM1throughM7W1throughW9BasedonExecutionStage:DesignPlanning,survey,andpreparationConstructionexecutionProvisionalcompletionDefectsdiscoveryandcorrectionSubstantialcompletionClaimsClassificationBasedonProjectWorks:RoadwaysEarthworksBridges(overpasses,underpasses,junctions,andelevatedbridges)TunnelsRetainingwallsDrainageSignalingParapetsandbarriersLandscapingandmore……ClaimsClassificationBasedonClaimStatus:NewContinuingFilednotresolvedResolvedWithdrawnStatusofParticularsNotprovidedGuesstimateDetailedClaimsClassificationBasedonClaimAmount:MinorWithclaimvaluelessthanonemillionDinarsOrfordelayoflessthan1weekforamajorworkortaskOrdelayforaminorworkortaskMajorWithclaimvaluegreaterthanonemillionDinarsOrfordelayofmorethan1weekforamajorworkortaskNotes:(1)Claimvalueanddelayareguesstimatedforissuingaclaimnotice.(2)Amajorworkortaskhasavalueofgreaterthan1%oftotalpriceofconstructioncontractforagivensection(M1,M2orW1,W2).ClaimsClassificationBasedonEntitlement:Low(lessthan25%)Moderate(between25%and75%)High(morethan75%)Notes:(1)EntitlementrepresentstheContractor’scontractualrightwithoutprejudice.(2)EntitlementisguesstimatedbytheclaimsmanagersatSite,West/CenterHO,andJVwhichcouldbedifferentvalues.ClaimsClassificationPriceCentersClaimsClassificationBasedonClaimHeadings:DelaysforapprovingAPSandAPDLandacquisitionUtilitiesrelocationGettingpermitsandauthorizationsDelaysforimportinggoodsandequipmentsSupplementedworksChangesinworksUnforeseensiteconditionsClaimsClassificationClaimHeadings:ExceptedrisksForceMajeureSevereweatherMobilizingforeignworkersInsuranceclaimsDefectsliabilitySecurityClaimsClassificationClaimHeadings:LatepaymentsPriceadjustmentsEnvironmentalDamagesDamagestonearbystructuresDamagestoresidentsDamagestootherprojectsDamagestoutilitiesDamagestoroadsandrailroadsClaimsClassificationClaimHeadings:LabTestsSubcontractingNightworksLabordisputesMaterialsquarryArchaeologicalfindingsConfidentialityPatentsClaimsClassificationClaimNatureApplicationcontractSubsectionExecutionstageProjectWorkClaimStatusClaimAmountEntitlementPriceCenterheadingClaimHeadingCLAIMSADMINISTRATIONClaimsManagementTasksKeepcopyofrelevantcorrespondencesInitiate,manage,andresolveclaimsClaimNoticesClaimsStatusReportsClaimParticularsAdministrateClaimFilesClaimsnegotiationandresolutionDisputeClientandthirdpartyclaimsPositiveandNegativeDefensesReviewVariationOrdersandSupplementaryAgreementsClaimManagementTomaintaintheentitlementtopursueaclaim,theContractorshouldshow:CauseandeffectsrelationshipclearlyexpressedConditionsprecedentsatisfiedMitigationeffortsusedandcontinued(bestendeavors)FullparticularsorinterimparticularssubmittedContemporaryrecordsmaintainedStatusreportssubmittedClaimManagementConditionsPrecedentConditionsPrecedentforclaimsis:“AdministrationrequirementsofContractforfilingandprocessingclaims”including:SendingnoticePreparingparticularsMaintainingrecordsSubmittingclaimsstatusreportClaimresolutionprocessIssuingvariationordersClaimManagementConditionsPrecedentStep1-SubmitclaimnoticeAssoonasadelayingoradditionalcosteventcanbereasonablyforeseenNotlaterthan10daysaftercommencementofsuchaneventStatingtheprobableextentofthedelayandcostCitingtheprovisionsoftheContractapplicableSpecifyingdefiniteentitlementClaimManagementConditionsPrecedentStep2-Within28daysofclaimnotification,submitbyfurtherwrittennoticetotheClient:FullanddetailedparticularsofthecauseandactualextentofthedelayandcostAprogramidentifyingtheeffectsofthedelayDetailsofthemeasureswhichtheContractorhasadoptedand/orproposestoadopttoavoid,reduceormitigatethedelayingandcostingeffectsDetailsofthedocumentsmaintainedtosupportsuchclaimClaimManagementConditionsPrecedentStep2forwhen:AneventhascontinuingeffectContractorisunabletodeterminewhethertheeffectofaneventwillactuallycausedelaytosubstantialcompletionofthewholeoftheWorksorSectionItisnotpracticablefortheContractortosubmitfullanddetailedparticularsSubmitaClaimStatementtothateffectwithreasons,togetherwithinterimwrittenparticularsincluding:DetailsofthelikelyconsequencesoftheeventonprogressoftheWorksorSectionAnestimateofthelikelyextentofthedelayandcostClaimManagementConditionsPrecedentStep3-SubmitthestatusreportAtmonthlyintervalsaspartoftheMonthlyProgressReportDonotsubmitiftheClientnotifiesinwritingthatitisnotnecessaryProvidefurtherinterimwrittenparticularsuntiltheactualdelayandcostisascertainable,whereuponimmediatelysubmitfulldetailedparticularsInitiatingandQuantifyingclaimsClaimsStatusReportsClaimsNoticeProcess(FortheTimeBeing)LESSONSLEARNEDforCLAIMRESOLUTIONPRE
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 机械工程师资格证书考试复习攻略
- 了解纺织机械操作专业的认证试题及答案
- 2024年质量工程师考试的常见误区解析试题及答案
- 机械工程师资格证书考试自动控制系统试题及答案
- 纺织机械操作证书考试中的信息采集技巧试题及答案
- 纺织机械操作系统的运用探讨试题及答案
- 数字化工作环境的CAD工程师试题及答案
- 商务礼仪师考试的课程安排与内容分析试题及答案
- 发电厂除氧器的类型及结构(热力发电厂课件)
- 商务礼仪师考试重点知识梳理试题及答案
- 建设工程消防验收现场评定工作报告(第三方机构模板)
- 正确认识孩子性格特
- 《幼儿园保育教育质量评估指南》图文详解课件
- 《智能建造技术与装备》 课件 第十章 智能施工与智慧工地
- 物业环境部培训课件
- 如何培训加油站站长
- 仓库管理制度及流程(3篇)
- 钢结构大棚安拆专项施工方案
- 《工业机器人系统维护》试卷7及答案
- 2024年(新课标卷)高考物理试题评析交流 课件
- 机器的征途:空天科技学习通超星期末考试答案章节答案2024年
评论
0/150
提交评论