![[名企]PC构件吊装施工方案2021_第1页](http://file4.renrendoc.com/view/cc379ac3d2e69f85eebfbb77ba989390/cc379ac3d2e69f85eebfbb77ba9893901.gif)
![[名企]PC构件吊装施工方案2021_第2页](http://file4.renrendoc.com/view/cc379ac3d2e69f85eebfbb77ba989390/cc379ac3d2e69f85eebfbb77ba9893902.gif)
![[名企]PC构件吊装施工方案2021_第3页](http://file4.renrendoc.com/view/cc379ac3d2e69f85eebfbb77ba989390/cc379ac3d2e69f85eebfbb77ba9893903.gif)
![[名企]PC构件吊装施工方案2021_第4页](http://file4.renrendoc.com/view/cc379ac3d2e69f85eebfbb77ba989390/cc379ac3d2e69f85eebfbb77ba9893904.gif)
![[名企]PC构件吊装施工方案2021_第5页](http://file4.renrendoc.com/view/cc379ac3d2e69f85eebfbb77ba989390/cc379ac3d2e69f85eebfbb77ba9893905.gif)
版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、苏州国越置业有限公司苏地2021-WG-8号地块项目(1#-11#楼、S-1、S-3#、自行车棚1-2、地下车库)_PC构件吊装施工方案_编制:_审核:_批准:_2021年6月苏地2021-WG-8号地块项目PC构件吊装专项施工方案 目录TOC o 1-2 h u HYPERLINK l _Toc29159 第一章 编依据和说明 PAGEREF _Toc29159 3 HYPERLINK l _Toc21388 第一节 编制依据 PAGEREF _Toc21388 3 HYPERLINK l _Toc11006 第二节 编制说明 PAGEREF _Toc11006 4 HYPERLINK l
2、_Toc4151 第二章 工程概况 PAGEREF _Toc4151 5 HYPERLINK l _Toc15311 第一节 工程概况 PAGEREF _Toc15311 5 HYPERLINK l _Toc10451 第二节 PC构件概况 PAGEREF _Toc10451 10 HYPERLINK l _Toc32067 第三章 进度计划与施工准备 PAGEREF _Toc32067 11 HYPERLINK l _Toc15957 第一节 工期计划 PAGEREF _Toc15957 11 HYPERLINK l _Toc7982 第二节 施工准备 PAGEREF _Toc7982 12
3、 HYPERLINK l _Toc8102 第三节 预制构件二次运输与堆放 PAGEREF _Toc8102 15 HYPERLINK l _Toc7434 第四节 PC构件检查 PAGEREF _Toc7434 16 HYPERLINK l _Toc14880 第五节 现场准备 PAGEREF _Toc14880 17 HYPERLINK l _Toc18873 第四章 PC吊装施工 PAGEREF _Toc18873 19 HYPERLINK l _Toc11317 第一节 施工流程 PAGEREF _Toc11317 19 HYPERLINK l _Toc13524 第二节 PC吊装施工
4、部位及顺序 PAGEREF _Toc13524 19 HYPERLINK l _Toc23214 第三节 整体施工顺序 PAGEREF _Toc23214 38 HYPERLINK l _Toc19673 第四节 现场吊装与施工 PAGEREF _Toc19673 42 HYPERLINK l _Toc24805 第五节夏季高温施工混凝土的养护措施 PAGEREF _Toc24805 50 HYPERLINK l _Toc4270 第六节 外脚手架选型 PAGEREF _Toc4270 53 HYPERLINK l _Toc7455 第七节 PC构件吊装注意事项 PAGEREF _Toc745
5、5 54 HYPERLINK l _Toc461 第八节后续施工 PAGEREF _Toc461 55 HYPERLINK l _Toc372 第九节 预制构件连接节点 PAGEREF _Toc372 55 HYPERLINK l _Toc22103 第十节 叠合板支撑体系 PAGEREF _Toc22103 55 HYPERLINK l _Toc1364 第五章 地下室临时支撑 PAGEREF _Toc1364 63 HYPERLINK l _Toc13274 第一节 基本情况分析 PAGEREF _Toc13274 63 HYPERLINK l _Toc26754 第三节 运输道路 PAG
6、EREF _Toc26754 65 HYPERLINK l _Toc29135 第六章 PC质量验收 PAGEREF _Toc29135 66 HYPERLINK l _Toc26698 第一节 预制构件验收方法与标淮 PAGEREF _Toc26698 66 HYPERLINK l _Toc29986 第二节 PC吊装验收内容和标准 PAGEREF _Toc29986 67 HYPERLINK l _Toc18293 第三节 驻厂监理验收规定 PAGEREF _Toc18293 68 HYPERLINK l _Toc18647 第七章 安全保证措施 PAGEREF _Toc18647 68
7、HYPERLINK l _Toc29390 第一节 一般安全遵守事项 PAGEREF _Toc29390 68 HYPERLINK l _Toc25862 第二节 吊装安全注意事项 PAGEREF _Toc25862 69 HYPERLINK l _Toc3767 第三节 事故预防措施 PAGEREF _Toc3767 69 HYPERLINK l _Toc24195 第四节 施工机械安全措施 PAGEREF _Toc24195 70 HYPERLINK l _Toc24240 第八章 预制构件成品保护 PAGEREF _Toc24240 71 HYPERLINK l _Toc19689 第九
8、章 文明施工及环境保护措施 PAGEREF _Toc19689 71 HYPERLINK l _Toc22228 第十章 突发事件应急预案 PAGEREF _Toc22228 73 HYPERLINK l _Toc17391 第十一章 群塔防撞措施 PAGEREF _Toc17391 74 HYPERLINK l _Toc1930 第一节 编制依据 PAGEREF _Toc1930 74 HYPERLINK l _Toc4068 第二节 塔机布置概述 PAGEREF _Toc4068 75 HYPERLINK l _Toc24966 第三节 塔机平面布置图 PAGEREF _Toc24966
9、75 HYPERLINK l _Toc16388 第四节 塔机安装高度及高差 PAGEREF _Toc16388 76 HYPERLINK l _Toc742 第五节 群塔管理组织机构设置 PAGEREF _Toc742 82 HYPERLINK l _Toc9180 第六节 群塔防碰撞使用方案 PAGEREF _Toc9180 83 HYPERLINK l _Toc29872 第七节 群塔作业保障措施 PAGEREF _Toc29872 83 HYPERLINK l _Toc12904 第八节 安全管理措施 PAGEREF _Toc12904 84 HYPERLINK l _Toc16517
10、 第九节 应急预案 PAGEREF _Toc16517 85 编依据和说明 编制依据1、建筑工程施工质量验收统一标准(GB50300-2013);2、混凝土结构工程施工质量验收规范(GB50204-2015);3、混凝土结构工程施工规范(GB50666-2011)4、建筑施工模板安全技术规范(JGJ 162-2008);5、建筑施工扣件式钢管脚手架安全技术规程(JGJ 130-2011);6、建筑施工高处作业安全技术规范(JGJ 80-2016);7、建筑施工起重吊装工程安全技术规程(JGJ 276-2012);8、建筑机械使用安全技术规程(JGJ 33-2015);9、施工现场临时用电安全技
11、术规范(JGJ46-2005);10、装配式混凝土结构技术规程(JGJ 1-2014);11、建筑施工安全检查标准(JGJ 59-2011);12、混凝土异形柱技术规程(JGJ 149-2017);13、建筑施工临时支撑结构技术规范(JGJ 300-2013);14、建筑施工易发事故防治安全标准(JGJ/T429-2018);15、预制混凝土构件质量评定标准 GB321;16、桁架钢筋混凝土叠合板15G366-1;17、装配式混凝土结构连接节点构造 15G301-12;18、水泥基灌浆材料应用规范GB/T 50448-2015;19、装配式混凝土建筑技术标准GB/T51231-2016;20、
12、装配式整体式混凝土结构工程施工质量验收规范DB33/T1107-2014;21、建筑机械使用安全技术规程JGJ33-201222、建筑工程绿色施工规范GB/T50905-2014;23、建设部37#部令及建质办【2018】31号关于实施危险性较大的分部分项工程安全管理规定有关问题的通知;24、建建发【2017】454号关于印发装配式混凝土结构施工质量安全控制要点(试行)的通知25、装配式砼建筑技术标准GB/T51231-201626、装配式住宅建筑检测技术标准JGJ/T485-201927、苏州城发建筑设计院有限公司提供的建筑、结构图纸等;28、当地政府相关文件;29、本工程施工组织设计及施工
13、总进度计划安排。第二节 编制说明本专项施工方案编制的范围为:PC构件二次运输,PC构件吊装等的相关施工方法、安全和质量措施等;对于预制构件的制作,因由专业构件厂制作,本方案不做相关说明;对于与预制构件相连的梁、板等的钢筋绑扎、支模和混凝土浇筑,因与传统作业类似,可参照相关的专项施工方案或本项目施工组织设计。第二章 工程概况第一节 工程概况一、参建概况工程名称:苏地2021-WG-8号地块(1#-11#楼、S-1、S-3#、自行车棚1-2、地下车库)工程地点:苏州市吴中区甪直镇苏州市吴中区甪直镇鸣市路北侧,长虹北路东侧 建设单位:苏州国越置业有限公司 设计单位:苏州城发建筑设计院有限公司监理单位
14、:苏州卓越建设项目管理有限公司施工单位:江苏省建筑工程集团有限公司二、工程概况本工程为苏州吴中甪直长虹北路项目(主要包含 1#11#住宅楼、地下车库),本工程是住宅项目,总建筑面积 103022.68m,地下室建筑面积 28785 平方米。地下 1 层,地上住宅单体 16 层18 层,建筑高度最高 54.35m。地下汽车库非人防区共 5 个防火分区。 本工程各分项指标如下:房屋建筑工程明细单名称面积(平方米)层数其它(高度、单跨等)地上地下地上地下1#6901.40159.751612#6901.40151.351613#6685.84157.081614#6901.40169.051615#
15、6901.40128.791616#4828.82376.571717#6901.40137.591618#7329.90989.931719#4828.82604.2517110#7760.20156.7518111#楼7760.20156.47181S1#186.78010S2#1138.44020S3#304.79010非人防地库017776.5510人防地下室07878.1510基本风压为0.45KN/m2,基本雪压为0.45KN/m2,地面粗糙类别为C类。墙体:0.000以上:(1) 外墙采用B06轻质砂加气混凝土砌块,砂加气砌块砌筑专用粘结剂砌筑。墙体厚度除注明者外为200厚(图中
16、为粗实线墙体)。(2) 内墙(防火墙、楼梯墙、电梯、走道等砖墙)B06轻质砂加气混凝土砌块,专用粘结剂砌筑。墙体厚度除注明者外为200厚。0.000以下地下室外墙为P6抗渗钢筋混凝土墙,内墙为B06轻质砂加气混凝土砌块,专用粘结剂砌筑,无地下室部砖基础为水泥实心砖。砂浆强度详结构设计说明。混凝土:除结施图中已有说明外结构构件的混凝土强度等级均按以下要求:地下室顶板(室外)、底板、内外墙、柱子:强度等级C35;抗渗等级: P6;主楼范围内竖向构件:强度等级C45、C35、C30。主楼梁板:强度等级C35C30。混凝土为预拌(商品)砼。钢筋:HPB300级钢筋,HRB400级钢筋。外墙:玻璃幕墙、
17、石材幕墙、涂料墙面。三、施工条件1、气象条件本工程所在地区年平均气温15.017.7,呈南高北低分布。极端最高气温38.042.0,极端最低气温为-15.0-7.0。年平均相对湿度76%82%,无霜期230天260天。2、 周围环境概况地块位于吴中区甪直镇。项目北至丰、西至长虹北路东侧、南至鸣市路,东至待建的(经三路)。原厂地原为本场地原为苏州檀雨玩具有限公司厂区,后拆迁形成。厂区围墙未拆除。1、基坑北侧:地下室外墙红线约11.313.4m,距离现有围墙约11.313.4m,围墙外为丰登路及其绿化,绿化带有燃气、给水管线。地下室外墙到燃气管线17.021.4m,到给水管线约14.220.0m。
18、2、基坑东侧:地下室外墙距离红线约9.2m9.7m,距离现有围墙约27.829.4m,围墙外为居民小区绿化带,绿化带下有燃气管线,地库距离小区楼房最近约63.5m。 3、基坑南侧:地下室外墙距离红线约5.111.1m,距离现有围墙约26.529.2m。围墙外为鸣市路及其绿化。绿化内有高压电线及通信管线、污水管线。地下室外墙到高压电线约34.3m。 4、基坑西侧:地下室外墙距离红线约9.0m9.4m,距离现有围墙约20.5m。红线外为长虹北路,道路下有燃气及通信管线,地下室外墙到燃气管线约25.528.0m。西侧中部地库外有2F售楼处,为桩基础,地下室外墙距离售楼处约8.7m。另该为拆迁场地,场
19、地内部还有众多建筑基础及废弃管线,围护施工前应对妨碍围护施工的地下障碍物进行清障处理。 四、PC结构(1) 本方案所述的PC结构是指本工程1#11#楼PC结构叠合板,PC外围护墙,具体使用部位:项 目PC叠合板楼层PC外围护墙备注1#、4#楼216层116层2#、5#楼216层116层3#楼416层7#楼416层6#、9#楼417层8#楼217层117层10#楼518层11#楼518层(2) 工程结构为剪力墙结构体系,采用预制装配式构件,主要预制构件有预制叠合楼板,预制蒸压轻质墙板(ALC)等;PC构件混凝土标号:C30,PC外围护墙混凝土标号:C45C30。 各单体高层PC结构概况(1)楼栋
20、PC构件仅为叠合板,单块构件起重量控制在1.3t,PC外围护墙单块构件起重量控制在3t以下;(2)各单体内隔墙采用蒸压轻质混凝土墙板,采用人工安装。1#、4#楼叠合板叠合板编号叠合板X边长(mm)叠合板Y边长(mm)单层数量(个)单块叠合板面积(m2)单块叠合板厚度(mm)叠合板体积(m3)单块叠合板重量(t)本层叠合板面积(m2)PCB12370292016.92600.0411.046.92PCB2a19353320 16.43 600.3850.96 6.43 PCB2b19353320 16.43 600.3850.96 6.43 PCB3a1935272015.26600.3160.
21、795.26PCB3b1935272015.26600.3160.795.26PCB4a4170185017.71 600.463 1.167.71 PCB4b4170185017.71600.463 1.167.71PCB4c4170185017.71600.463 1.167.71PCB51805 227014600.240.74PCB63170192016600.36 0.916PCB73170162015.14600.31 0.775.14PCB81520 227033.45600.60.5210.35PCB92270 247035.6601.02 0.84 16.8PCB10a168
22、5 2220 13.74600.220.563.74PCB10 b1685 2220 13.74600.220.563.74PCB111320 222022.93600.360.445.86PCB12a13202360 23.11600.380.476.22PCB12 b13202360 23.11600.380.476.22PCB12c13202360 23.11600.380.476.22PCB13a1570 417036.55601.170.98 19.65PCB13a1570 417036.55601.170.98 19.65PCB13c1570 417036.55601.170.98
23、 19.65PCB14a1675252014.221600.250.564.221PCB14b1685252014.246600.250.644.246PCB1519702820 35.55 600.990.8316.65PCB16a1935 2670 35.17 600.930.77 15.51PCB16b1935 2670 35.17 600.930.77 15.51PCB17a2635 312038.22601.471.1624.66PCB17b1935312036.04601.080.9118.12KTB1620282031.75 600.30.265.25KTB2620 1470 3
24、0.91600.150.142.73KTB3620227011.4600.080.211.4KTB4620146010,91 600.050.140,91 YTB1a1620293514.75 600.290.714.75 YTB1b1620293514.75 600.290.714.75 YTB2a1620 2510 34 607.20.6112YTB2b1620 2510 34 607.20.6112合计本层共计叠合板个数69本层叠合板体积共:32.272 本层叠合板面积共: = sum(I2:I38) * MERGEFORMAT 419.4672#、5#、8#楼叠合板叠合板编号叠合板X边
25、长(mm)叠合板Y边长(mm)单层数量(个)单块叠合板面积(m2)单块叠合板厚度(mm)叠合板体积(m3)单块叠合板重量(t)本层叠合板面积(m2)PCB12370292016.92600.0411.04 6.92PCB2a1935332016.43 600.3850.96 6.43 PCB2b1935332016.43 600.3850.96 6.43 PCB3a1935272015.26600.3160.795.26PCB3b1935272015.26600.3160.795.26PCB4a4170185017.71 600.463 1.167.71 PCB4b4170185017.716
26、00.463 1.167.71PCB4c4170185017.71600.463 1.167.71PCB52070227014600.240.74PCB63170192016600.36 0.916PCB73170162015.14600.31 0.775.14PCB81520 227033.45600.60.5210.35PCB92270 247035.6601.02 0.84 16.8PCB10a1685 2220 13.74600.220.563.74PCB10b1685 2220 13.74600.220.563.74PCB111320 222022.93600.360.445.86P
27、CB12a13202360 23.11600.380.476.22PCB12b13202360 23.11600.380.476.22PCB12c13202360 23.11600.380.476.22PCB13a1570 417036.55601.170.98 19.65PCB13b1570 417036.55601.170.98 19.65PCB13c1570 417036.55601.170.98 19.65PCB14a1675252014.221600.250.564.221PCB14b1685252014.246600.250.644.246PCB1519702820 35.55 6
28、00.990.8316.65PCB16a1935 2670 35.17 600.930.77 15.51PCB16b1935 2670 35.17 600.930.77 15.51PCB17a2635 312038.22601.471.1624.66PCB17b1935312036.04601.080.9118.12KTB1620282031.75 600.30.265.25KTB2620 1470 30.91600.150.142.73KTB3620227011.4600.080.211.4KTB4620146010,91 600.050.140,91 YTB1a1620293514.75
29、600.290.714.75 YTB1b1620293514.75 600.290.714.75 YTB2a1620 2510 34 607.20.6112YTB2b1620 2510 34 607.20.6112合计本层共计叠合板个数 = sum(D2:D38) * MERGEFORMAT 69本层叠合板体积共: = sum(G2:G38) * MERGEFORMAT 32.272本层叠合板面积共: = sum(I2:I38) * MERGEFORMAT 419.4673#楼叠合板叠合板编号叠合板X边长(mm)叠合板Y边长(mm)单层数量(个)单块叠合板面积(m2)单块叠合板厚度(mm)叠合
30、板体积(m3)单块叠合板重量(t)本层叠合板面积(m2)PCB1aL1930312026600.720.912PCB1bL1930312026600.720.912PCB1aR1935312026600.720.912PCB1bR1935312026600.720.912PCB2aL1935267025.15600.620.7710.3PCB2bL1935267025.15600.620.7710.3PCB2aR1935267025.15600.620.7710.3PCB2bR1935267025.15600.620.7710.3PCB3aL4170157026.55600.790.9813.
31、1PCB3bL4170157026.55600.790.9813.1PCB3cL4170157026.55600.790.9813.1PCB3aR4170157026.55600.790.9813.1PCB3bR4170157026.55600.790.9813.1PCB3cR4170157026.55600.790.9813.1合计本层共计叠合板个数28本层叠合板体积共:10.1本层叠合板面积共:167.86#、9#楼叠合板叠合板编号叠合板X边长(mm)叠合板Y边长(mm)单层数量(个)单块叠合板面积(m2)单块叠合板厚度(mm)叠合板体积(m3)单块叠合板重量(t)本层叠合板面积(m2)P
32、CB1aL1085292013.17600.190.473.17PCB1bL1085292013.17600.190.473.17PCB2aL2160342017.39600.441.17.39PCB2bL2160342015.15600.311.15.15PCB3aL4620157017.25600.431.087.25PCB3bL4620157017.25600.431.087.25PCB3cL4620157017.25600.431.087.25PCB3dL4620156017.25600.431.087.25PCB1aR1085292013.17600.190.473.17PCB1bR
33、1085292013.17600.190.473.17PCB2aR2160342017.39600.441.17.39PCB2bR2160342017.39600.441.17.39PCB3aR4620157017.25600.431.087.25PCB3bR4620157017.25600.431.087.25PCB3cR4620157017.25600.431.087.25PCB3dR4620157017.25600.431.087.25PCB4L2570337018.66600.521.38.66PCB4R2570337018.66600.520.678.66PCB5a148030201
34、4.47600.270.674.47PCB5b1480302014.47600.270.674.47PCB5aR1480302014.47600.270.674.47PCB5bR1480302014.47600.270.674.47合计本层共计叠合板个数 = sum(D2:D23) * MERGEFORMAT 22本层叠合板体积共: = sum(G2:G23) * MERGEFORMAT 7.95本层叠合板面积共: = sum(I2:I23) * MERGEFORMAT 133.27#、10#、11#楼叠合板叠合板编号叠合板X边长(mm)叠合板Y边长(mm)单层数量(个)单块叠合板面积(m2)
35、单块叠合板厚度(mm)叠合板体积(m3)单块叠合板重量(t)本层叠合板面积(m2)PCB12370292016.92600.421.04 6.92PCB2a1935332016.43 600.420.96 6.43 PCB2b1935332016.43 600.420.966.43 PCB3a1935272015.26600.320.795.26PCB3b1935272015.26600.320.795.26PCB4a4170185017.71600.461.167.71PCB4b4170185017.71600.461.167.71PCB4c4170185017.71600.461.167.
36、71PCB5a4170157034.47600.80.6713.41PCB5b4170157034.47600.80.6713.41PCB5c4170157034.47600.80.6713.41PCB61970282036601.080.9118PCB7a1935267035.16600.930.7615.48PCB7b1935267035.16600.930.7615.48PCB8a2635312038.22601.481.2124.66PCB8b1953312036.03601.090.8918.09合计本层共计叠合板个数 = sum(D2:D17) * MERGEFORMAT 32本层
37、叠合板体积共: = sum(G2:G17) * MERGEFORMAT 11.19本层叠合板面积共: = sum(I2:I17) * MERGEFORMAT 185.371#、4#楼外围护墙 外围护墙编号单块外围护墙重量(t)外围护墙编号单块外围护墙重量(t)1-PCTC12.121-PCTC80.841PCWQ3-A1.71-PCTC71.381PCWQ2-A2.391-PCTC61.391PCWQ1-A1.471-PCTC50.841-PCTC21.461-PCTC41.41PCWQ4b-A1.451-PCTC31.651PCWQ4a-A1.651PCWQ5b-A1.31-PCTC101.
38、11PCWQ5a-A1.141-PCTC92.122#、5#、8#楼外围护墙 外围护墙编号单块外围护墙重量(t)外围护墙编号单块外围护墙重量(t)2-PCTC21.892-PCTC50.842PCWQ1-A2.392-PCTC61.392PCWQ2-A1.72-PCTC71.382PCWQ3-A2.122-PCTC80.842-PCTC12.862-PCTC91.12PCWQ5a-A1.142-PCTC101.652PCWQ5b-A1.132PCWQ4a-A1.452-PCTC30.842PCWQ4b-A1.462-PCTC41.38 PC构件概况PC建筑特点 PC构件建筑与传统建筑相比,其设
39、计形式和施工方法,有不同的工艺和工序搭接,其主要特点是:(1)、产业化流水预制构件工业化程度高;(2)、成型模具和生产设备一次性投入后可重复使用,耗材少,节约资源与费用;(3)、现场装配、连接可避免或减轻施工对周边环境的影响;(4)、工业化节能降耗成效显著,节电、节水、节能、建筑废弃物得到抑制,扬尘、噪声污染得到有效控制;(5)、工程施工周期短;(6)、劳动力资源投入相对减少;(7)、机械化程度有明显提高,操作人员劳动强度得到自效缓解;(8)、高空湿作业减少。本工程PC概况、预制构件主要用于栋号楼的1-18层楼面以及内墙,分为3种构件类型:PC预制叠合板、PC外围护墙、ALC内墙隔板。、本工程
40、所有预制构件混凝土强度为C45C30。(3)、双向叠合板之间采用后浇带形式接缝。(4)、预制构件的吊环应采用未经冷加工的 HPB300 级钢筋制作。(5)、本项目装配式设计中预制构件为非结构抗侧力构件。(6)、预制构件预埋接线盒及管线;预留烟道等穿楼板洞口。PC预制叠合板PC外围护墙预制装配式构件的产业化。所有预制构件全部采用在工厂流水加工制作,制作的产品直接用于现场装配。 工厂加工生产 现场吊装施工(8)在设计过程中,运用BIM技术,模拟构件的拼装,减少安装时的冲突。外墙PC结构采用螺纹盲孔。内墙剪力墙全灌浆套筒、高强灌浆施工的新技术施工工艺,将PC结构与PC结构进行有效连接,增加了PC结构
41、的施工使用率,降低PCF的施工率,提高施工效率。第三章 进度计划与施工准备第一节 工期计划PC构件主要用于主要用于栋号楼的1-18层,计划于2021年8月13日开始施工,2022年2月5日完工,工期为183天。进度计划详附图;第二节 施工准备一、项目管理组织架构项目管理组织架构图如下:项目经理项目技术负责项目副经理施工员安全员材料员质检员试验员资料员预算员各施工班组各分包单位机械管理员二、主要管理人员岗位职责:(一)、项目经理岗位职责(邵乃1、遵照国家施工规范、工程质量和安全生产检验评定标准,以及地区有关规定和制度,负责本工程总的组织和领导,并做好协调工作。2、对本工
42、程的质量、安全生产、劳动保护、经济效益、工期承担全面责任。3、认真执行公司的质量、安全、工期、管理目标,确保质量、安全生产目标的实现。4、负责组织和健全本工程质量保证体系,安全生产体系和防火体系,确保和支持质安人员履行责任范围内的各项工作。5、坚持质量和安全第一,处理好质安与施工矛盾,领导开展质检评比活动,提倡文明施工,确保环境卫生,创建施工现场标准化管理。6、服从接受上级主管部门对质量、安全、财务、卫生的监督检查和业务指导,负责落实整改事项,贯彻公司制定的各项管理制度和规定。7、负责对本工地业务技术骨干的管理和使用,监督检查他们的工作质量和效率,组织对业务技术骨干和工人的培训和教育,不断提高
43、队伍的思想觉悟、职业道德、安全意识、技术素质和管理水平。8、负责经济分配,提倡集体研究,增强透明度,做到正确处理国家、集体、个人三者之间的利益,对职工分配贯彻“按劳取酬”的原则,并与质量、安全紧密挂钩,关心职工生活和劳动保护,做到不断改进职工生活和劳动条件。9、负责领导并做好ISO9001系列质量体系的工作。10、负责领导并做好IS014001/18001系列环境/安全体系贯标的有关工作。(二)、项目副经理岗位职责(施洪兵1、配合项目经理完成日常工作;2、直接领导现场施工管理部,负责现场整体管理工作。3、在项目经理短期不在项目时,暂时实施项目经理职责,并完成项目经理委
44、托其他任务。(三)、技术负责人岗位职责(陈1、根据本项目部创优指标,负责制订具体单位工程的创优措施和实施计划。2、遵照国家和地区颁发的规范、标准、规定,以及设计要求,结合工地现场和实际条件,负责编制单位工程的施工组织设计(施工方案),经审批后,贯彻实施。3、对负责施工的工程质量、安全生产、劳动保护、工期等负有技术责任。4、负责组织各要素、工种熟悉图纸,统一归纳问题,做好图纸会审前的准备工作,以及会审纪要的整理签认工作。5、在整个施工过程中,负责贯彻各项专业技术标准,严格执行施工验收规范和质量检验评定标准以及有关规定。6、负责单位工程,分部分项工程的技术交底和安全生产技
45、术交底,负责对采用的新技术、新材料、新工艺应用的技术攻关和技术交底及安全技术教育,组织职工开展技术操作竞赛活动。7、负责对工程材料、构件等的数量、规格、型号、质量方面的检查和检验工作,以及混凝土、砂浆等的试配工作。8、负责单位工程的测量定位,找平、放线工作,负责技术复核,组织隐蔽工程验收,分部分项质量内评。负责整理和向资料员提供施工技术资料、施工总结及竣工图。9、参加质量检查活动和技术会议,以及各阶段工程验收工作,负责处理质量事故,对重大质量事故做到及时上报,协同有关部门及时处理。10、协助做好ISO45001列质量体系的有关工作。11、协助做好IS014001/18001系列环境/安全体系贯
46、标的有关工作。(四)、安全员岗位职责(陈占1、严格遵照国家和地区颁发的安全生产方针、政策、法规、标准,以及劳动保护规定办事;按照建设部及市有关标准、规定做好现场及资料工作。2、对本工地安全生产有监督保障责任,并以身作则,模范遵守有关安全生产的制度和规定。3、负责对职工进行定期和不定期安全教育,做好公司、工地、班组(或工种)三级教育,记录和登记签证工作。4、参加审查施工组织设计(施工方案)中有关安全生产的部分,并提出改进意见。5、对不具备安全生产的设备、设施,有权责令停止使用。6、每天检查施工现场的安全生产情况,指出和帮助解决事故隐患,及时反映安全生产动态,提出改进措施
47、。负责向资料员提供安全资料。7、对违章指挥、违章操作以及不遵守安全管理制度和规定的班组、职工,有权责令其改正或停工整改,对屡教不改或造成直接经济损失的处以罚款。8、对项目中安全方面存在的问题及状况及时或定期向项目经理汇报。9、负责对公司、项目部安全管理和场容场貌管理制度的逐项落实、实施。(五)、质检员岗位职责(田杰)1、严格遵照国家和地区颁发的施工规范、工程质量检验评定标准和有关规定。履行工程质量监督职责,负责制定和执行工程质量检查计划。2、负责对进场材料、构件、成品、半成品、设备、器材以及现场制作的混凝土、砂浆、预制和加工构件等的质量监督(包括对质保试验资料)和验证工作,对劣质产品有权让材料
48、员退换。3、负责对分部分项工程的内部检测和等级评定,对不合格项目有权令其返工,直至合格,才能准许转入下一道工序,做到层层把好质量关。4、负责对班组、个人所完成项目的质量验收工作。5、负责对职工进行质量控制和职业道德教育。深入现场,及时反映质量动态,找出原因,提出改进质量的措施,参加质量事故的处理。6、参加上级组织的质量检查活动,接受上级指导和批评,负责监督整改事项的实施,参加隐蔽工程的验收、中间验收、竣工验收,负责整理和向资料员提供质量检验评定资料。并对现场文明施工的有关规定进行落实检查。(六)、施工员岗位职责(韩朝伟)1、严格遵守国家和市颁发的规范、标准、规定以及设计要求,结合本工地的实际情
49、况,参与编制单位工程的施工组织设计(施工方案),经审批后,贯彻实施。2、对负责施工的工程质量、安全生产、劳动保护、工期等负有直接责任。3、负责组织本工种熟悉图纸,统一归纳问题,做好图纸会审前的准备工作。4、在整个施工过程中,负责贯彻各项专业技术标准。严格执行施工规范和质量检验评定标准、以及有关规定。5、负责安排各班组的具体施工任务,负责对班组进行技术交底及安全技术教育,尤其是采用新技术、新材料、新工艺等,组织开展职工技术操作竞赛活动。6、负责对工程材料、构件等的规格、型号、质量方面的检查和验收工作,以及混凝土、砂浆等的试配工作。7、参与单位工程的测量定位、找平放线工作,参与隐蔽工程验收,分部分
50、项质量内评,向资料员提供施工技术资料,施工总结及竣工图。8、参加质量检查活动和技术会议,以及各阶段工程验收工作,参与处理质量事件,对重大质量事故做到及时上报,协同有关部门及时处理。(七)、测量员岗位职责(张1、遵守先整体后局部和高精度控制低精度的工作程序。即先测设场地整体平面控制网,再以控制网为依据进行各局部建筑物的定位放线和标高测设。2、选用科学、简捷和精度合理、相称的方法,合理选择正确使用仪器,在测量精度满足工作需要的前提下,力争做到省工、省时、省费用。3、严格审核使用数据(设计图纸,测量起始点位、数据等)的正确性,坚持测量作业与计算工作步步有校核。4、建立一切定
51、位、放线工作要自检、互检合格后,方可申请主管部门验线的工作制度,严格执行安全、保密等有关规定,用好管好设计图纸和资料,实测时要当场做好原始记录,测后要及时保护好桩位。5、测量人员要紧密配合施工、发扬团结协作,不畏艰难,实事求是、认真负责的工作作风。6、及时整理和向资料员提供测量放线资料。(八)资料员岗位职责(周逸薇)1、严格遵守市有关施工技术资料的管理规定。2、协助技术负责人进行施工组织设计的编制和贯彻实施。3、对本工地施工的工程,负有真实、及时、完整地编制技术资料的责任。4、负责向质检员、各施工员等有关人员讲解表格的填写内容和要求,以及做好协助工作。5、负责收集和审查各种资料,对不符合要求和
52、缺少的资料责成有关人员及时补上。6、负责竣工资料的整理、分册、汇总和装订工作。7、接受有关部门对资料的审查,改正存在的缺点。8、认真做好收发文工作,做到收文及时、发文及时,当天的文件当天下发给有关人员。9、与设计院、试验室、质监站密切联络,有关竣工验收文件及时送交签章。10、能熟练使用电脑、复印机,并能进行一般的清洁、保养。11、认真做好ISO9001、ISO14001、OHSAS18001系列贯标资料。(九)、材料员岗位职责(鲍晓1、认真执行安全生产的规章制度和防火规定。2、根据施工组织设计和材料预算制度实施采购计划,确保工程进度。3、熟悉图纸,对建筑材料做到心中有
53、数,进料应和进度同步跟上。4、对所购材料、构件、设备的质量、规格、型号必须符合设计要求。由于采购、保管原因而影响工程质量或造成质安事故,应承担经济、法律责任,负责向资料员提供材料质保资料。5、负责建立材料管理制度,做到分类保管,对易燃易爆物品专地隔离存放,严格进出料管理,建立材料帐册。6、负责组织仓库值勤,设置防火防盗设施,禁止在仓库内吸烟、聚会娱乐。7、负责按规定及时采购发放劳保用品。8、施工用材料工具签发领料单,凭单发料,由领料人签认,材料拿出工地必须经项目经理签发。作业人员安排:(1)管理人员:施工现场叠合板安装主要施工员和安全员共同负责,并请叠合板厂家派专业技术人员对现场安装进行技术指
54、导。(2)作业人员:作业人员经叠合板厂家相关技术人员培训后方可上岗。(3)安排取得省住房和城乡建设厅颁发的塔吊指挥岗位证书的人员指挥塔吊。工种数量专业吊装工人12人塔吊驾驶员5人塔吊司索工5人木工110人钢筋工70人混凝土工30人架子工28人普工7人四、吊装机械选型本工程设计预制构件每栋每层叠合板2269块;单块构件起重量0.141.16t;制构件每栋每层PC外围护墙15块;单块单块构件起重量0.952.5t。最大吊装高度50.10米,经过比较选择,本项目现场设置11台塔吊进行主体结构施工(含PC构件吊装)。为便于区分和管理,塔吊根据楼号进行统一编号,分别为1#、2#、3#、4#、5#、6#、
55、7#、8#、9#、10#、11#。塔吊的最终定型应根据PC构件的平面吨位位置确定。4.1、塔吊服务区域:每个楼号各布置一台塔吊主要服务各自的楼号。4.2、相关塔吊性能参数:4.2.1安装位置:编号型号幅度南北轴位东西轴位附着建筑基底标高安装高度1#徐工GT6018-8SX35N轴以北576217轴以东36391#楼北侧-6.4059.42#徐工GT6018-8SX30N轴以北397316轴以东14712#楼北侧-6.40653#徐工GT6018-8SX35A轴以南477016轴以东53013#楼南侧-6.4056.64#徐工GT6018-8SX50N轴以北469017轴以东38624#楼北侧-
56、6.40655#徐工GT6018-8SX30A轴以南349214轴以东47545#楼南侧-6.4059.46#徐工GT6018-8SX35A轴以南470610轴以东1106#楼南侧-6.4056.67#徐工GT6018-8SX35A轴以南401317轴以西3307#楼南侧-6.4059.48#徐工GT6018-8SX30N轴以北405516轴以东14308#楼北侧-6.4059.49#GT6018-8SX35J轴以北429217轴以西14889#楼北侧-6.4070.610#GT6018-8SX35A轴以南410617轴居中10#楼南侧-6.4062.211#GT6018-8SX30A轴以南2
57、49217轴以东216311#楼南侧-6.40654.2.2、 技术性能表4.2.2.1、徐工GT6018-8SX长度30米、35米、50米预制构件二次运输与堆放1、PC板的交接检查:PC构件运输由生产厂家送至工地现场,有土建单位专职质量员接收出厂合格证,并作外观检查,以便厘清责任,发现开裂等质量问题应当场提出;2、一般情况下直接吊装,但运输车辆要经地下室顶板才能抵达起吊区域。3、施工区设置临时堆场,原则上一层的预制构件从首批进场至全部吊装完成不超过7天。PC构件分别按规格、品种、吊装顺序堆放,对于部分直接从运输车上吊装的构件,其装车顺序应和吊装顺序相适应。4、PC 构件二次运输过程中,车辆启
58、动应慢速,车速应匀,转弯错车时要减速,施工场地内车辆限速5km/h。5、堆放场地应平整、坚实,并设有排水措施;堆放区域应在塔吊工作范围内,堆垛之间宜设置通道。6、构件支垫应坚实,垫块在构件下的位置宜与脱模、吊装时的起吊位置一致;最下层放置通长垫木、垫实;各层垫木间应在一条直线上。支撑点的支座应有足够的强度,应能将堆积件重量充分地传递到场地上,控制过量沉陷,并应避免预制构件扭曲或变形。7、重叠叠放构件时,每层构件间的垫块应上下对齐,堆垛层数应根据构件、垫块的承载力确定(叠合楼板不宜大于 6 层,梯段板每跺不超过 5 块), 并应根据需要采取防止堆垛倾覆的措施。 PC外围护墙堆放方式PC外围护墙堆
59、放架图纸 叠合板叠放方式 PC构件检查预制构件运至现场后,由项目专职质量员检查预制构件是否符合要求,检查项目见第五章PC质量验收、第一节预制构件验收方法及标准、第2条预制构件验收标准。器具及仪器准备序号名称数量1钢扁担2副2缆风绳4根3对讲机20部4撬棍4根5水平仪2台6全站仪1台现场准备5.1、技术准备1、重视设计交底工作,每次设计交底前,由项目工程师具体召集各相关岗位人员汇总、讨论图纸问题,设计交底时,切实解决疑难和有效落实现场碰到的图纸施工矛盾。2、按照三级技术交底程序要求,逐级进行技术交底,特别是对不同技术工种的针对性交底,要切实加强和落实。3、做好专业多工种施工劳动力组织,选择和培训
60、熟练技术工人,按照各种工种的特点和要点,加强安排与落实。4、切实加强与建设单位、设计单位、预制构件加工制作单位以及相关单位的联系,及时加强沟通与信息联系。5、现场按照设计院提供的 PC 项目设计图纸,结合工程实际,编制具有可操作性的装配式混凝土结构施工组织设计,优化方案,确保节点,推行科学化施工领域。5.2、现场准备施工现场做到三通一平即 路通、水通、电通和平整场地的准备,搭建好现场临时设施、构件运输车辆停车场和 PC 结构的堆场准备;为了配合 PC 结构施工和 PC 结构单块构件的最大重量的施工需求,确保满足每栋房子 PC 结构的吊装距离,以及按照施工进度以及现场的场布要求,本项目配备11台
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2025年学生创新:《水果拼盘》教案点评
- 任务4.1.2 全站仪数字化测图
- 高效办公技能提升简明教程与技巧分享
- 2025年安徽绿海商务职业学院单招职业倾向性测试题库完美版
- 项目启动与推进会议纪要
- 艾灸养生知识课件
- 2025年安徽现代信息工程职业学院单招综合素质考试题库一套
- 2025年晋城货运从业资格模拟考试题
- 农作物种子买卖合同
- 2025年安徽省铜陵市单招职业适应性测试题库往年题考
- 2019年四川省绵阳市中考化学试卷
- 中国风青花瓷陶瓷文化宣传PPT模板
- 美丽乡村规划设计技术导则
- 课题成果要报格式和要求
- 经销商准入及评定表格vr
- SF-36量表(简明健康状况调查表)
- 主要河流南、北方河流的不同特征主要湖泊
- 上岗证WORD模板
- 2019第五版新版PFMEA 注塑实例
- 职业技能鉴定质量督导报告
- 钣金k因子和折弯扣除参照表
评论
0/150
提交评论