1、越南松绑4水电站工程机电设备安装闸门密封(透光)检查方案批准:罗春华审核:吴伟文编制:张文红vietnam songbung 4 hydropower station e&mequipments installationgate seal (transmittance)inspection schemeapprover: luochunhuainspector: wu wei wenprepared by: zhang wenhongguangdong yuantian engineering companysong bung 4 hydropower station project
2、departmentapril 14th, 2014闸门密封(透光)检查方案gate seal (transmittanee) inspection scheme越南songbung4水电站尾水闸门安装好后必须进彳亍密封检查,闸 门密封检查除了用塞尺检查闸门所有水封的密封情况外,还应做透光 检查。具体方法是:seal inspection must bu taken after the installation of song bong 4hrdropower station project tailwater gate.闸门安装好后,应采用楔形木把闸门紧紧压在门槽上,使水封能 完全紧压在门槽
3、上,达到止水效果。然后用塞尺检查各水封面的接触 情况,接触情况不理想时,就增加压紧契形木的压紧力。然后做透光 检查,透光检查采用强光手电或36v行灯,在闸门外对门槽的水封处 进行照射,在闸门里面(尾水管里)检查是否有光线进去,如果在闸 门里面(尾水管里)看到光线就说明闸门密封不紧密,需要处理,直 到在闸门里面(尾水管里)看不到任何光线为止。闸门两侧密封透光 检查可以用绳了把灯缓慢放进门槽,来回几次。闸门的门楣和底坎可 以采用灯或手电照射密封。闸门内外的人员通信采用对讲机或手机联 系,以保持外部光照人员和里面检查人员位置同步。闸门底坎密封检 查吋,要求不能有水,所以闸门透光检查吋闸门位置的水应全
4、面抽干 和清理干净。after the installation of gate, press the gate on the gate slot tightly by wedge wood to press the water seal on the gate slot tightly for seal.the n in spect the con tact situati on of seal surface by feeler gauge. if thecon tact situation does not achieve ideal con dition, in crease the
5、pressure of wedge wood then take the transmittanee inspection. stand out of the gate and llluminate to the seal by glare flashlight or 36v cable lamp to check whether there is any light entering the gate (in tailwater pipe). light in the gate (in tailwater pipe ) means that gate seal is not tight an
6、d take the treatment until no light in the gate(in tailwater pipe). the transmittanee inspection of both sides of gate seal is to put the light into the gate slot slowly by rope for several times the gate head and sill seal inspection is to illuminate by light or flashlight the communication in and
7、out of the gate is by in terph one or mobile phone to keep the position synchronization of the personnel in and out of the gate it is required that there is no water during the seal inspection of gate sill, so the there shall be swab-off and cleanup.附表:闸门密封(透光)检查表attached table : gate seal (transmit
8、tanee) inspection table闸门安装质量检查记录表quality inspection record table of gate installationvnsb4-site -quality control table: is-单位工程 unit projectvietnam song bung 4 hydropower projec t图纸编号 drawing no.分部工程 part project单元工程element project检查内容purpose of inspection闸门密封(透光)检查记录 ga to seal (1ransmi t tance) inspection records承包单位 contractorhydrochina huadongals tom consorti uni (hhac)施工单位 sub- contractorguangdong yuan tian engineering corpora tion vietnam song bung 4 project department开始完成时间 commencement and completioninspect
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 药物与疾病关系图谱解析试题及答案
- 2024年汽车安全标准理解试题及答案
- 宠物营养师考试的常见问题解答试题及答案
- 省考宠物营养师技能要求试题及答案
- 2024年食品质检员考试的参考书籍试题及答案
- 了解2024年二手车评估师考试流程及试题答案
- 酒店防台抗汛知识课件
- 科学规划美容师考试的复习路线试题及答案
- 汽车的安全检测标准流程解析试题及答案
- 统计学回归预测能力试题及答案
- 24式太极拳教案(1~4课)
- 小学 三年级 心理健康《最好的老师-兴趣的作用》教学设计
- DB12T 1040-2021 建筑工程规划管理技术规范
- 产业经济学的课后复习答案
- 中国绿色经济发展之路(PPT-37张)课件
- G322-1钢筋砼过梁
- 客房控制系统——RCU系统培训PPT通用通用课件
- 压力管道安装许可证换证自评报告
- (会议纪要(2011)第29期)河南煤业化工集团有限责任公司会议纪要
- 起重机械定期检验规则概述
- 原子吸收分光光度计检定规程
评论
0/150
提交评论