1、bbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbb港馨西区住宅楼工程检验、试验计划目 录第一节 编制依据········································&

2、#183;·2第一节 工程概况··········································2第三节 试验工作部署···

3、;···································31、建立现场试验管理程序············

4、3;··················32、建立现场试验管理程序·····························

5、83;·33、试验管理保证体系···································34、试验设施设备··········&

6、#183;····························45、试验工作要点···················

7、3;···················56、试验管理各部门职责····························

8、3;····6第四节 主要材料试验计划··································81、钢筋工程········&#

9、183;··································82、砼工程··············&#

10、183;······························103、防水工程··················

11、·························164、砌筑工程·······················

12、3;···················175、装修工程·····························&#

13、183;·············176、外墙外保温工程··································

14、83;··187、安装工程···········································188、节能环保检测·

15、83;·····································199、回填土工程···········

16、······························1910、其他检测··················

17、83;·······················20第五节 施工试验见证取样内容························

18、;······20第六节 质量保证措施······································21第一节 编制依据一、主要规程、规范类 别名

19、 称编 号国家混凝土结构工程施工质量验收规范GB50204-2002(2012)国家混凝土结构试验方法标准GB50152-2012国家砌体结构工程施工质量验收规范GB50203-2011国家屋面工程质量验收规范GB50207-2012国家地下工程防水技术规范GB50108-2008国家地下防水工程质量验收规范GB50208-2011国家建筑结构检测技术标准GBT50344-2010行业蒸压加气砼建筑应用技术规程JGJ/T17-2008行业外墙外保温工程技术规程JGJ/144-2004行业塑料门窗工程技术规程JGJ/103-2008行业普通混凝土配合比设计规程JGJ55-2011行业泵送混凝土技

20、术规程JGJ/T10-2011行业钢筋机械连接通用技术规程JGJ107-2010行业建筑工程冬期施工规程JGJ104-2011企业钢筋滚轧直螺纹接头技术规程Q/HJ08-2010二、主要标准类 别名 称编 号国家砼强度检验评定标准GB/T50107-2010国家建筑工程施工质量验收统一标准GB50300-2013国家混凝土外加剂中释放氨的限量GB18588-2001国家土方合成材料应用技术规范GB50290-1998国家混凝土质量控制标准GB50164-2011国家砌体工程现场检测技术标准GB/T50315-2011行业砌筑砂浆配合比设计规程JGJ98-2010行业普通混凝土用砂、石质量检验标

21、准JGJ55-2006三、主要法规 序号类别名 称 编 号1国家中华人民共和国建筑法中华人民共和国主席令1997年第91号2国家建设工程质量管理条例中华人民共和国国务院令第279号3国家工程建设标准强制性条文中华人民共和国建设部建标200085号4地方关于转发建设部房屋建筑工程和市政基础设施工程实行见证取样和送检的规定的通知京建质2000578号5地方房屋建筑工程和市政基础建设工程试行见证取样和送检的规定建建200211号令6地方关于”北京市建设工程施工试验实行有见证取样和送检制度的暂行规定”的通知京建质2009289号7地方”预防混凝土工程碱集料反应技术管理规定(试行)京建质20095.4号

22、8地方房屋建筑工程和市政基础设施工程实行见证取样和送检的规定建建2000211号9地方建筑工程资料管理规程DB11/T695-2009类 别名 称编 号国家建设工程质量管理条例国务院令(第279号)国家相关工程建设标准强制性条文/地方关于转发北京市建设工程见证取样质量检测单位资质条件管理规定的通知京建质2001229号地方关于转达发建设部房屋建筑工程和市政基础设施工程实行见证取样和送检的规定的通知京建质2000578号第二节 工程概况工程名称:港馨家园西区住宅楼建设地点:北京市顺义区港馨家园2组团北侧、胡各庄C区南侧建设单位:北京仁和日升房地产有限公司建筑面积:总计76000 (地下19000

23、 ,地上57000) 其中:1楼地下2771;地上19351 2楼地下2737;地上19212 3楼地下2729;地上17237 地下车库11363建筑层数:3栋地下2层、地上18层住宅楼;3栋地下2层、地上16层住宅楼;整体地下1层车库及2栋地上2层无地下室沿街商业组成。建筑高度:59.90 m建筑耐火等级:一级抗震等级一级,抗震设防裂度8度,结构安全等级一级 。建筑场地类别类 。主要结构类型:CFG桩复合地基、梁筏板基础,现浇剪力墙结构 。建筑耐久年限:70年各栋号住宅楼的地下部分位于地下车库内,与地下车库有机的连在一起,成为地下车库及战时防空设施的一部分。第三节 试验工作部署1、建立现场

24、试验管理程序项目部总工程师为试验管理体系主要负责人。项目部技术质量部、工程部为一级试验管理机构,各分包单位为二级试验管理机构。工程项目部试验管理日常部门为技术质量部。项目部每月至少检查一次各分包单位试验工作,要求各分包单位严格按此计划组织试验工作,做好施工现场材料取样复试和试块、试件的制作工作及相关信息、资料的收集、存档。2、试验工作总则施工现场试验工作是工程质量管理体系的重要组成部份,必须严格执行国家有关规范、规程、技术标准及企业质量管理程序,必须严格执行北京市建设工程施工试验实行有见证取样和送检制度的暂行规定,保证本工程的试验工作顺利进行,保证工程质量能有效的得到控制并符合合同要求,工程技

25、术资料完整、齐全、真实、有效。3、试验管理保证体系各种原材料进场,物资部收集出厂材质证明原件试验员核对物资检验单和厂家相关证明材料按相关要求现场取样(监理见证)专业试验检测(监理见证或平行检验)物资部按进场计划单填写物资进场检验单(材料名称、规格、数量、使用部位、存放地点)安质部联系监理见证物资部、工程部(各专业施工班组)配合取样工作物资管理部整改试验报告整理各种标准试验(钢筋原材力学性能、混凝土强度、砂浆强度、土的标准击实等)进场材料报验(质量安全管理部)成品、半成品检测工程实体检测竣工检测质量安全管理部技术管理部工程管理部试验检测4、试验设施设备1)各种试验仪器设备的性能和精确度应符合国家

26、标准有关规定,有明显标识,定期检定,专人管理并建立管理台帐,现场试验应配置主要设备见下表。序号名称数量序号名称数量1标准养护室(或标准养护箱)1间12气泵1台2砼试模:100×100×100三联塑料试模40个13砼振动台1台3砂浆试模:70.7×70.7×70.7三联铸铁试模8把14冷热空调1台4抗渗试模:185×175×150塑料试模12个15电炉子2000w(炉丝10根)1个5坍落度筒3个16铁笼子10个6天平1000g精度1g1个17钢丝锯1把7盘称10kg精度5g1台18油刷(5cm宽)、大抹子、小压子、开刀各2把8取土环刀2

27、00cm³3套19养护室电源220v防潮插座2个9湿温度计1块20百叶箱1个10高低温度计1块21个养护架子3个 11温湿度自动控制器1套2)试验室应有专用的标准养护室和操作间,标准养护室要求温度为20±2,湿度要求95%以上。(参见规范普通混凝土力学性能试验方法)3)在单位工程开工前,项目部技术负责人与建设、监理单位共同确定承担有见证试验的检测机构。每个单位工程只能选定一个承担有见证试验的检测机构。5、试验工作要点1)做好有序的试验,技术质量部、物资部、工程部根据施工组织设计指定好的流水段施工流程、实物工作量及材料进场计划,做好试验工作各环节的交圈接口工作,防止出现漏验少

28、验的现象。2)施工现场试验管理应分工明确、责任到人;从事施工现场试验工作的专职试验人员必须持证上岗。3)加强学习规范和技术标准,做到随时掌握现场施工情况、材料情况与国家规范技术标准要求的相符性。4)施工现场的试验室应具备与该工程试验业务相适应的工作环境,且保证试验工作必要的能源、照明、温度、湿度、通风等条件。5)各项试验制度和操作规程应悬挂在试验室明显位置。6)施工现场试验室必须配备与工程实际情况相适应的试验设备和计量器具,并应在开工前提交配置计划。7)试验仪器设备的放置应便于操作人员操作,养护室与操作间应分开设置。8)试验室的仪器设备、试验工具,应按要求分类、定期鉴定、检测、自检,及时做出标

29、识。9)试验仪器设备、试验工具应有专人管理并建立台账。10)施工现场试验工作必须实行有见证取样和送检制度,各种取样送检和试验原始记录必须真实完整,不得涂改、抽换或丢失。11)项目部技术部门编写试验计划,并在开工前向试验人员做好书面技术交底。6、职责1)技术质量部职责项目部技术员·负责现场试验室、标养室的检查和指导工作。·负责制定本工程试验工作计划(方案),并对试验员进行交底。·负责现场试验项目的数据审核,发现问题及时向技术负责人汇报。·负责收集、整理原材料合格证、复试单等试验资料。项目部试验员职责· 对负责送试的材料严格按照材料检验标准有关取样

30、的规定和试验室的规定及试验交底取样送试,对试样的代表性、真实性负责,做到不漏试、错试。· 严格按照有关规范、规程、标准的规定,制作试件,并做好试件的管理、养护、送试工作。· 根据工程实际需要,必须分别建立砂、石、砌墙砖(砌块)、混凝土试块、砂浆试块、钢筋原材、钢筋连接、钢筋连接班前检验和工艺检验、防水材料、外保温材料、外加剂(掺合料)、回填土送试台帐,并统一编号,相互衔接。· 根据试验交底的内容,进行各类原材(砂、石、钢筋、砖及砌块、外加剂、防水卷材、外保温材料等)进厂复试、施工试验(混凝土试块、砂浆试块、钢筋焊接、土壤干密度等)的取样工作,填写试验委托单并及时将

31、试样和委托单送到试验室。· 及时、准确填写混凝土、砂浆制作记录。· 负责回填土取样试验,· 负责商品混凝土塌落度抽测工作并做好记录和现场商品混凝土取样、同条件试块制作等试验工作。· 对于见证取样额材料,试验人员应与见证人员密切合作,保证试样的代表性和真实性。·认真填写试验委托单,其内容齐全保证可追溯性。· 及时取回试验报告单,交给现场相关技术人员,对不合格项目及时报告技术负责人。·负责所有试验设备的维护保养和自检。2)工程部职责负责提供各种材料的实际用量和进场计划,同时核对各工序施工前本工序所用材料的合格与否严格控制材料的合

32、理使用,保证不合格材料不用于施工。3)物资部职责负责向工程部提供材料进场情况及时向技术部上报整理合格证等材料并通知试验工、质量员,共同对材料进行取样复试,填写材料报验单等手续,实行动态管理。4)质量部负责检查核实施工过程工序验收中材料的合格及各种试验单满足规范和有关图纸技术标准的要求。5)试验管理程序项目工程师技术部工程部质量部 物资部试验工材料试验第四节 主要材料试验计划 本工程实行100%有见证取样工作,并送至见证试验室试验。有见证取样和送检是在监理人员的见证下,由施工单位的试验人员在现场取样,送至指定试验室进行试验。对施工现场的取样和送检进行见证,并有取样人和见证人签字,见证人制作见证记

33、录,见证记录应列入施工技术档案。各种见证取样和送检试验资料必须真实、完整,符合试验管理规定。一、钢筋工程本工程钢筋类别:HPB235、HRB335、HRB400E,钢筋接头形式:大于等于16采用直螺纹连接,14以下采用绑扎搭接接头、本工程钢筋使用概况 地下车库部 位主 筋 规 格箍 筋基槽筏板20、168基础梁25、1412、10柱28、25、22、20、1812、10、8墙20、18、16、14、12 梁28、2512、10 板 14、12住宅部分部 位主 筋 规 格箍 筋墙14、12 连梁25、22、20、18、168 板 14、12商业部分部 位主 筋 规 格箍 筋柱28、25、228梁

34、22、20、18、148 板 12、8、钢筋的进场检查及取样方法(1)钢筋进场进行外观检查:裂纹、锈蚀程度等。(2)同一牌号、同一炉罐号、同一规格,每60t为一验收批,不足60t也按一批计。(3)每一验收批,在任选的两根钢筋上切取试件(拉伸两个、弯曲2个)。(4)超过60t的部分,每增加40t(或不足40t的余数),增加一个拉伸试验试件和一个弯曲试验试件。(5)试验项目中如有某一项试验结构不符合标准要求(包括该项试验所要求的任一指标)不合格,则该批钢筋视为不合格。不合格钢筋不得进行使用,办理退场手续,保留可追溯性。(6)计划试验数量及见证数量种类规格数量(T)试验组数见证组数级HPB300 6

35、.51911810522 106522 1212022级HRB400E832111012633 12932214902216872218112222058010102235112528055 283511注:钢筋试件组数按进场批次、数量取样、钢筋直螺纹连接接头取样方法工艺检验:在正式施工前,按同批钢筋、同种机械连接形式的接头试件不少于3根。使用不同厂家品牌的同规格的钢筋,应重新做工艺检验。 现场检验:接头的现场检验按验收批进行,同一施工条件下采用同一批材料的同等级、同形式、同规格的接头每500个接头为一验收批,不足500个接头也按一批计,每一验收批必须在工程结构中随机截取3个试件,做单向拉伸试

36、验,在现场连续检验10个验收批,其全部单向拉伸试件一次抽样均合格时,验收批接头数量可扩大一倍。、钢筋直螺纹接头数量和取样计划部 位接 头 数 量钢筋直径282522201816基础筏板47006400地梁4320柱450120016201440墙6002006501210200梁3800地下一层柱1532525252096梁1659090一层柱1532525252096梁120二层柱60945660梁120取样组数3251022715见证组数3251022715二、混凝土工程1、地库部分砼强度等级垫层筏板独立柱外 墙(附墙柱)地 梁内墙梁板楼梯圈梁构造柱设备基础C15C40 P8C50 C40

37、P8C40 P8C40C45P8C45P8C45C25C202、主楼砼强度等级、结构层楼面标高1#楼电梯机房58.356.20C30C30电梯机房52.355.80C30C301852.152.801749.352.80C35C301646.552.801646.552.801543.752.80C35C301543.752.801440.9502.801440.9502.801338.1502.801338.1502.801235.3502.801235.3502.801132.5502.801132.5502.801029.7502.801029.7502.80926.9502.80926

38、.9502.80824.1502.80824.1502.80721.3502.80721.3502.80618.5502.80618.5502.80515.7502.80515.7502.80412.9502.80412.9502.80310.1502.80310.1502.8027.3503.55 C35C3527.3503.55C35C3513.8003.9013.8003.90-1-0.1003.05C40C40-1-0.1003.05C40C40-2-3.0503.70-2-3.0503.70层号顶板标高(m)层高(m)墙、柱、连梁砼梁、顶板 砼层号标高(m)层高(m)墙、柱、连梁 砼

39、梁、顶板 砼2#楼电梯机房58.356.20C30C30电梯机房52.355.80C30C301852.152.801749.352.80C35C301646.552.801646.552.801543.752.80C35C301543.752.801440.9502.801440.9502.801338.1502.801338.1502.801235.3502.801235.3502.801132.5502.801132.5502.801029.7502.801029.7502.80926.9502.80926.9502.80824.1502.80824.1502.80721.3502.80

40、721.3502.80618.5502.80618.5502.80515.7502.80515.7502.80412.9502.80412.9502.80310.1502.80310.1502.8027.3503.55 C35C3527.3503.55C35C3513.8003.9013.8003.90-1-0.1002.75C40C40-1-0.1002.75C40C40-2-2.853.70-2-2.853.70层号顶板标高(m)层高(m)墙、柱、连梁砼梁、顶板 砼层号标高(m)层高(m)墙、柱、连梁 砼梁、顶板 砼3#楼 电梯机房58.356.20C30C30电梯机房52.355.80C

41、30C301852.152.801749.352.80C35C301646.552.801646.552.801543.752.80C35C301543.752.801440.9502.801440.9502.801338.1502.801338.1502.801235.3502.801235.3502.801132.5502.801132.5502.801029.7502.801029.7502.80926.9502.80926.9502.80824.1502.80824.1502.80721.3502.80721.3502.80618.5502.80618.5502.80515.7502.

42、80515.7502.80412.9502.80412.9502.80310.1502.80310.1502.8027.3503.55 C35C3527.3503.55C35C3513.8003.9013.8003.90-1-0.1002.60C40C40-1-0.1002.60C40C40-2-2.7003.70-2-2.7003.70层号顶板标高(m)层高(m)墙、柱、连梁砼梁、顶板 砼层号标高(m)层高(m)墙、柱、连梁 砼梁、顶板 砼3、本工程全部采用商品混凝土,现场取样工作按混凝土等级、种类、浇灌部位进行,不得漏取。混凝土试件取样工作在混凝土的浇筑地点随机取样。必试项目:稠度、抗压强

43、度、结构实体检验(同条件强度和保护层厚度)、抗渗等级(对于抗渗混凝土) 4、取样方法及数量用于检验结构构件混凝土质量的试件,应在混凝土浇筑地点随机取样制作;每组试件所用的拌和物应从同一盘搅拌的混凝土中取出,每组试样量应满足混凝土质量检验项目所需用量的1.5倍,且不少于0.02m3。5、坍落度测定方法进场后应随车测定坍落度,将坍落度筒放置在不吸水的刚性平面上,用脚踩住脚踏板,将试样用小铲分三层均匀装入筒内,使每层捣实后,高度为全高的1/3左右,每层用捣棒振捣25次,振捣第二层时,捣棒应插至底层的表面,坍落度筒的提离应在150s内完成,提起后应该及时测量坍落度值,并做记录。坍落度应定期送指定试验室

44、检验。6、普通混凝土试件取样留置规定强度试块留置规定(每组3块):(1)拌制100盘且不超过100m3的同配合比的混凝土,其取样不得少于一组;(2)每工作班拌制的同配合比的混凝土不足100盘时,其取样不得少于一组;(3)每一现浇楼层或流水段同配合比的混凝土,其取样不少于一组;(4)同一单位工程每一验收项目中同配合比的混凝土,其取样不得少于一组; (5)现场搅拌混凝土,当在一个分项工程中浇筑相同配合比的混凝土量大于1000m3,每200m3混凝土取样不得少于一组;(6)每次取样应至少留置一组标准养护试件, 同条件养护试件的留置组数 (如拆模前, 拆除支撑前等)应确定;(7)用于结构实体检验的同条

45、件养护试件留置应符合下列规定: 对混凝土结构工程中的各混凝土强度等级,均应留置同条件养护试件;同一强度等级的同条件养护试件, 其留置的数量应根据混凝土工程量和重要性确定,不宜少于 10 组,且不应少于3 组;(8)同一强度等级的同条件养护试件,其留置的数量应根据混凝土工程量和重要性确定,不宜少于10组,且不应少于3组。同条件养护试件所对应的结构构件及结构部位,由监理(建设)、施工等各方根据其重要性共同选定。(9)建筑地面工程的混凝土,以同一配合比,同一强度等级,每一层或每 1000m2为一检验批,不足1000m2也按一批计。每批应至少留置一组试块。(10)为保证真正做到同条件养护,所留置的试块

46、放置在楼层内,为防止试块破坏,焊接钢筋笼子,将试块放在里面并上锁。 (11)对混凝土结构工程中的各混凝土强度等级,均应留置同条件养护试件。7、抗渗混凝土试块留置方法(1)连续浇筑抗渗混凝土每500m3应留置一组抗渗试件(一组为 6 个抗渗试件) ,且每项工程不得少于两组。采用预拌混凝土的抗渗试件,留置组数应视结构的规模和要求而定。混凝土的抗渗性能,应采用标准条件下养护混凝土抗渗试件的试验结果评定。 (2)冬季施工检验掺用防冻剂的混凝土抗渗性能,应增加留置与工程同条件养护 28d,再标准养护28d 后进行抗渗试验的试件。 (3)留置抗渗试件的同时需留置抗压强度试件并应取自同一盘混凝土拌合物中。

47、取样方法同普通混凝土,试块应在浇筑地点制作。8、试块留置数量(1)顶板需要制作试块:普通砼标养(28天试压)(根据每流水段浇注量立方米确定); 顶板拆模强度(同条件养护试块); 结构同条件养护试块 (2)墙体需要制作试块:普通砼标养(28天试压)(根据每流水段段浇注量立方米确定);结构同条件养护试块9、混凝土试块的制作及养护方法(1)商品混凝土必须在入模前混凝土浇筑地点随机取样制作,取样时记录取样地点、取样时间、罐车车号。(2)在制作试件前应将试模清擦干净,并在其内模涂以脱模剂。试件的制作应在150min内完成。(3)采用振动台成型时,应将混凝土拌合物一次装入试模,装料时用抹刀沿试模内壁 略加

48、插捣,并使混凝土拌合物高出试模上口。(4)人工插捣时,混凝土拌合物应分两层装入试模,每层装料厚度应大致相等。(5)采用标准养护的试件成型后应立即用不透水的薄膜覆盖表面,以防止水份蒸发,并应在室温为20±3情况下静置一昼夜,然后编号拆模。拆模后应立即放在温度为20±2,湿度为95%以上的标准养护室中养护。养护时,试件应放在架子上,彼此间距应为1020mm,并应避免用水直接淋刷试件。(6)采用与构筑物或构件同条件养护的试件,成型后即应覆盖表面,试件的拆模时间可与实际构件的拆模时间相同。同条件养护试块制作后,与现场浇筑的混凝土同部位、同条件养护,拆模后,试件需保持同条件养护。(7

49、)做好试块后要及时填写混凝土试块制作记录。基础砼试块和取样计划序号使用部位强度等级浇筑方量(m3)标养组数结构实体同条件拆模总数1基础垫层础底板C40 P811000110101203地下室外墙C40 P810801110214地下室内墙C40160016622 地下室内独立柱C504004265地下室顶板、梁C455800601021916地下一层墙柱1#C403504262#C403304263#C40250426梁板1#C4021042262#C4045042263#C402104226注:所有砼试块试验组数按流水段留置主体砼试块取样计划序号使用部位强度等级浇筑

50、方量(m3)标养组数结构实体同条件拆模总数1首层墙柱1#C354804262#C355204263#C35420426梁板1#C35180424102#C35210424103#C35160424102二层墙柱1#C354304262#C354504263#C35380426梁板1#C35180424102#C35210424103#C35160424103三层十七层(每 层)墙柱424004264243042642350426梁板4218042244221042244216042244十八层顶层(每 层)墙柱424004264243042642350426梁板4218042210422104

51、22104216042210注:所有砼试块试验组数按流水段留置三、防水工程1、防水卷材取样方法同一品种、牌号和规格的卷材堆放在一起,严禁混放,取样后在试件上做标记。GFZ聚乙烯丙纶防水卷材每1000卷为一验收批,在每批产品中随机选取5卷进行单位面积质量、面积、厚度等外观质量检查。在截取试样时去掉卷材的端部300mm后,顺纵向切取长度为1.5m的全幅卷材试样2块,2,一块作物理性能检验,另一块备用。抽检的卷材在取样前作规格及外观的检查,全部指标达标后即为合格。第一次送检若有一项不合格,则该批卷材不合格。试验取样计划部位面积()试验组数见证组数基础底板165001717墙面400044顶板9000

52、99飘窗顶1-1#100111-2#130112-1#110112-2#120113-1#110113-2#10011屋面1-1#400111-2#650112-1#400112-2#600113-1#400113-2#400112、聚合物水泥基防水涂膜必试项目:拉伸强度、断裂伸长率、低温柔性、不透水性取样规定:每10t为一验收批,共取5 。第一次送检若有一项不合格,则该批材料不合格。试验取样计划部位用量(T)试验组数见证组数厨房卫生间1-1#4111-2#5.5112-1#5.5112-2#4113-1#4113-2#411四、砌筑工程1、加气砼砌块:检验项目:立方体强度2、取样规定:同品种

53、、同规格、同等级的砌块,每1万块为一验收批,不足一万块也按一批计。每批从尺寸偏差和外观质量检验合格的砖中,随机抽取试验试样一组(9块)。3、砂浆强度的检验:取样规定:250m³砌体的砌筑砂浆为一检验批,不足250m³为一检验批,每次做一组标准养护试块,每组6块;冬季施工砂浆试块的留置为2组,一组标准养护试块、一组同条件试块,测试检验28天强度。检验项目:抗压强度,每次做一组标准养护试块,每组3块。检验项目:稠度,每次20。检验项目:分层度,每次20。检验项目:拌合物密度,每次20。加气砼砌块试验取样计划部位用量(m3)试验组数见证组数地下室18011主楼1-1#500221

54、-2#560222-1#500222-2#540223-1#500223-2#50022五、装修材料1、外墙面砖、室内地砖:检验项目:吸水率 取样规定:·以一生产厂的产品每5000为一验收批,不足5000m²也为一验收批。· 按规定随机抽取。可以从表面质量,尺寸偏差合格的试样中抽取。吸水率5 个试件。2、外窗检验项目:抗风压性能、气密性、水密性、保温性能取样规定:同一品种、类型、规格每100樘为一个检验批,每批抽查10,不少于6樘 。试验取样计划部位面积()试验组数见证组数主楼1-1#1000111-2#1200112-1#1100112-2#1100113-1#

55、1100113-2#1000113、门窗玻璃检验项目:遮阳系数、可见光透射比、中空玻璃露点取样规定:同一厂家、品种、类型为一个检验批,每批抽查不少于3块 。4、户门检验项目:安全性能取样规定:单位工程建筑面积5000时为一个检验批,抽查不少于2樘 。5、大理石检验项目:弯曲强度、耐冻融性 取样规定:·同一产地、品种、类别、等级每100M3为一个检验批 。·从外观质量,尺寸偏差检验合格的试样中抽取。每组5 块。六、外墙外保温工程本工程保温做法所用材料均需有产品合格证书、盖有CAL和CMA章的法定检测部门出具的检测报告。1、挤塑聚苯板试验项目:导热系数、压缩强度同一厂家同一品种的产品,单位工程面积在20000以下时各抽查不少于3次,20000以上时各抽查不少于6次。抽样数量2 。 第一次送检若有一项不合格,则该批材料不合格。试验取样计划部位面积()试验组数见证组数主楼1-1#5000331-2#7000332-1#5500332-2#6500333-1#5500333-2#5000332、耐碱纤网格布试验项目:力学性能、抗腐蚀性能同一厂家同一品种的产品,单位工程面积在20000以下时各抽查不少于3次,20000以上时各抽查不少于6次。抽样数量2m。七、安装工程1、电缆电线试验项目:截面、导电电阻值同一厂家产品各种规

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论