1、cspc nanhai petrochemicals project中 海 壳 牌 南 海 石 化ecu/lci projectecu/lci装置scaffolding erection procedure for ecu/lci steel structureecu/lci钢结构安装脚手架搭设方案ct-cpfc-cns-0018china petroleum first construction corporation (cpfcc)中国石油天然气第一建设公司no.daterevisionbychkdapprajune 2, 2004issued for reviewli yasong yu
2、ejunyu xuegongbjuly 6, 2004issued for reviewliu weixiongsong yuejunyu xuegong一、搭设原则building principle:确保施工作业人员的安全操作。在保证人身安全的情况下,考虑梁柱等吊装作业的通道和安装的方便性,以及脚手架搭设的简便。ensure safe operation of construction personnel, and pursue to the convenience of access of lifting activities (beam, column, etc.), installa
3、tion and scaffold building in itself with the priority of safety.二、脚手架的搭设方式building method of scaffolds:1、管廊、ecu钢结构管架吊装、安装搭设脚手架型式the scaffold type for lifting and installing steelwork on the bench and ecu a.说明:钢结构地面成榀,在榀的两侧绑扎铝合金梯子,在榀的顶梁上面安设生命绳(14mm)挂搭安全带。a. note: the steel structure is assembled as
4、one unit on the ground; ladders of aluminum alloy are fixed on the two sides of the assembling unit; and safety rope is set on the top for safety harness.b.梯子搭设和生命绳安设具体型式:the building type of ladder and safety rope is as follows: 防坠落器防坠落器生命绳生命绳扣c.榀型钢构吊装就位后,使用4根封绳拉紧(若需要,加设倒链),进行找正和固定。c. straighten an
5、d fix the assembling unit with four wind ropes on completion of placement, if necessary, set hoisting block.d.生命绳扣(1.5m、2m长)单独制作,作为挂搭安全带使用(当安全带挂绳直接挂搭横梁不够长时使用)。当横梁间距大于3m时,每根横梁上面仍使用生命绳(虚线)。d. fabricate safety rope and button with dimension of 1.5m2m separately for safety harness, specifically, when th
6、e safety harness is not long enough to hang on the beam. when the space between vertical beams is more than three meters, it also will be used. (dot line)2、高空地脚螺栓处,沿混凝土梁搭设操作平台的型式:building type of platform along concrete column on the anchor bolt at height:3、焚烧炉混凝土框架内梯子、平台施工脚手架搭设型式:scaffold building
7、type of ladder and platform in the concrete frame of incinerator:a.离地面不高的脚手架:由地面往上直接搭设或采用人可搬动式组架。for the scaffold relatively low off the ground, build it from the ground directly or adopt the movable frame.b.离立柱近,在立柱周围的脚手架型式,以抱箍的方式往外延伸,具体型式如下:b. for the scaffold close to columns, build it by hooping
8、 the column and expanding outside. the building type is as follows:立柱抱箍脚手架搭设平面布置简图c.横梁下操作平台脚手架搭设,以吊蓝的方式进行搭设,搭设型式如下:for the platform scaffold under the beam, build it as suspended basket. the building type is as follows:横梁吊蓝操作平台脚手架搭设立面布置简图4、焚烧炉混凝土框架顶(el20700)以上钢结构吊装、安装搭设脚手架型式:scaffold building type f
9、or lifting and installing steelwork on the concrete frame of incineratora.说明:钢结构地面成榀,在榀的两侧绑扎铝合金梯子,在榀的顶梁上面安设生命绳(14mm)挂搭安全带。a. note: the steel structure is assembled as one unit on the ground; ladders of aluminum alloy are fixed on the two sides of the assembling unit; and safety rope is set on the to
10、p for safety harnessb.梯子搭设和生命绳安设具体型式:ladder building type and safety rope setting type is as follows:生命绳生命绳扣防坠落器防坠落器注:钢柱插入钢筋笼内的部分,搭设铝合金梯子时,应预留插入部分的长度。note: remain inserted length when building ladder of aluminum alloy for the part where steel column inserts rebar cage c.生命绳扣(1.5m、2m长)单独制作,作为挂搭安全带使用(
11、当安全带挂绳直接挂搭横梁不够长时使用)。当横梁间距大于3m时,每根横梁上面仍使用生命绳(虚线)。c. fabricate safety rope and button with dimension of 1.5m2m separately for safety harness, specifically, when the safety harness is not long enough to hang on the beam. when the space between vertical beams is more than three meters, it also will be u
12、sed. (dot line)5、护拦搭设guardrail building:所有操作平台均搭设:带防物件坠落踢脚板的护拦保护,其具体型式如下:for all the platforms, the guardrail with toe-board in case of falling is built as follows:踢脚板护拦型式立面简图三、临时斜梯的搭设型式:building type of temporary inclined ladder钢结构的安装,由下往上,先梯子后平台。如果没有工程上使用的正式梯子,需要上高到操作平台时,采取搭设防护斜梯。其型式如下:the steel s
13、tructure is installed from down to up with ladder first and then platform. if no formal ladder is furnished on the structure, temporary inclined ladder will be installed during the duration of working on the high platform. the type is as follows:踏板平台钢跳板由钢跳板和踏板搭设的斜梯简图四、脚手架搭设时,对成品的保护措施:protective meas
14、ures on products during the duration of building scaffolds 为了保护混凝土柱梁、钢柱梁油漆,在梁柱上作为固定支点的脚手架绑扎位置,采用麻袋隔离的方式进行保护。the position on the beam where scaffolds are tied will be protected by gunny cloth in order to protect the coat on the concrete column and steel column.五、钢结构施工工艺流程:construction arrangement of
15、steel structure 1、lci部分:lci el+20700以下斜梯(由下往上安装)el+11200平面el+12900平面el+15200平面el+17700平面(结合设备安装)el+20700平面(结合设备安装)el+20700平面以上钢结构inclined ladel+20700der (install from down to up) below plane at el+11200plane at el+12900plane el+15200plane at el+17700 (combined with equipment installation)- plane at
16、el+20700 (combined with equipment installation)steel structure above el+20700el+20700平面以上钢结构施工工艺流程:steel structure construction arrangement above el+20700地面组装成榀吊装榀安装连接梁安装斜梯从下往上(el+25800、el+30500、el+34000、el+36700)安装平台assembling units on the groundlifting assembling units-installation of connecting b
17、eam- installation of inclined ladder-installation of platform from down to up.(el+25800、el+30500、el+34000、el+36700)2、ecu部分:ecuel+23250以下斜梯(由下往上安装)el+9500平台及走道el+12500平面el+16500平面el+19500平面el+20300走道el+23250平面el+23250平面以上钢结构inclined ladder under el+23250(installation from down to up)platform and walk
18、way at el+9500plane at el+12500plane at el+16500plane at el+19500walkway at el+20300plane at el+23250steel structure above el+23250el+23250平面以上钢结构施工工艺流程:construction arrangement of steel structure above el+23250地面组装成榀吊装榀安装连接梁安装斜梯从下往上(el+26350、el+29400、el+34000、el+36700)安装平台assembling units on the gr
19、oundlifting assembling units-installation of connecting beam- installation of inclined ladder-installation of platform from down to up.(el+26350、el+29400、el+34000、el+36700)六、钢结构施工程序对脚手架型式的选用:scaffold type selection of steelwork construction 1、lci部分:lcia. 斜梯安装:installation of inclined ladderel+9732平台
20、,使用地面往上直接搭设(或使用现有的可移动式组合架);on the platform at el+9732, build it from the ground directly or use the movable frame before el+12900平面以上,采用抱箍型式脚手架,即二、3、b条。above the plane at el+12900, adopt close loop type scaffold, see item 2.3 bb. el+11200平面:plane at el+11200采用吊蓝型式脚手架,即二、3、c条。或直接由地面往上搭设脚手架。adopt susp
21、ended basket type scaffold, see item2.3 c, or build scaffold from down to up directlyc. el+12900平面:plane at el+12900采用吊蓝型式脚手架,即二、3、c条。adopt suspended basket type scaffold, see item2.3 c.d. el+15200平面(即:el+14532平台):plane at el+15200在el+12930平台上安全护栏内直接施工。construct directly on the platform with guardra
22、il at el+12930e. el+17700平面:plane at el+17700第一方案:由el+12930平台直接搭设脚手架the first plan: build scaffolds directly on the platform at el+12930第二方案:采用吊蓝型式脚手架(即二、3、c条)。因此平面离上一层梁间距较大,需在混凝土柱间拉生命绳,安装人员将安全带挂搭在生命绳上沿梁走动。the second plan: adopt suspended basket type scaffold (i. e. item 2.3.c). due to the large spa
23、ce between plane and beam, the safety rope is set between concrete columns. the construction personnel move along the beam with safety harness joined with safety rope.钢结构梁由梯子侧(北侧)往南安装,具体安装施工详见附图一(46-8320-9300-0104)the steel structure is constructed from the north to south, and the detailed construct
24、ion method can be seen in the attachment. (46-8320-9300-0104)f. el+20700平面:plane at el+20700由el+17700平台直接搭设脚手架及采用吊蓝型式脚手架(即二、3、c条)。build scaffolds directly on the platform at el+17700 or adopt suspended basket type scaffold.g. el+20700平面以上成榀钢结构吊装:for lifting assembled unit above the plane at el+20700
25、采用二、4条内容阐述型式;同时,在平台外侧,采用二、2条型式加设临时平台,详见附图二(46-8320-9300-0105)。refer 2.4; at the same time set temporary platform outside the platform per item2.2. see detailed drawing. (46-8320-9300-0105)h. el+20700平面以上梁安装时,使用生命绳方式固定安全带。for the installation of beam above el+20700, hang safety harness with the safet
26、y rope.i. el+20700平面以上斜梯安装时,采用抱箍型式脚手架(即二、3、b条)和生命绳固定安全带的方式。for the installation of inclined ladder above el+20700, adopt hoop-type scaffold per item 2.3.b and fix safety harness with safety ropej. el+25800、el+30500、el+34000、el+36700平台安装,安全带固定在生命绳或已安装的梁上。for the installation of platform at el+25800,
27、el+30500, el+34000 and el+36700, safety harness will hang on the rope or installed beam.2、ecu部分:ecua.斜梯安装:installation of inclined ladderel+9732平台,使用地面往上直接搭设(或使用现有的可移动式组合架);on the platform at el+9732, build it from the ground directly or use the movable frame before el+12500平面以上,采用抱箍型式脚手架,即二、3、b条。ab
28、ove the plane at el+12900, adopt close loop type scaffold, see item 2.3 bb.el+9500平台及走道,由地面往上直接搭设(或使用现有的可移动式组合架);for the platform and walkway at el+9500, build it from the ground directly or use the movable frame before c. el+12500平面:plane at el+12500采用吊蓝型式脚手架,即二、3、c条。el+13800平台在el+12500平台上直接施工。adop
29、t suspended basket type scaffold, see item2.3 c. the platform at el+13800 will be constructed directly on the platform at el+12500d. el+16500平面:plane at el+16500采用由el+12500平台直接往上搭设脚手架或吊蓝型式脚手架(即二、3、c条)。build scaffolds directly on the platform at el+12500 or adopt suspended basket type scaffold, see i
30、tem2.3 c.e. el+19500平面:plane at el+19500一部分采用由el+16500平台直接往上搭设脚手架,一部分采用吊蓝型式脚手架(即二、3、c条)。build scaffolds directly on the platform at el+16500 or adopt suspended basket type scaffold, see item2.3 c.f. el+20300走道、el+20500平台:walkway at el+20300 and platform at el+20500在el+19500平台上直接施工。build directly on
31、the platform at el+19500g. el+23250平面:plane at el+23250在用吊蓝型式脚手架(即二、3、c条)及由el+19500平台直接往上搭设脚手架。adopt suspended basket type scaffold, see item2.3 c. or build scaffolds directly on the platform at el+19500 h. el+23250平面以上成榀钢结构吊装:for lifting assembled unit above the plane at el+23250采用二、1条内容阐述型式;同时,3轴线
32、外侧(南侧)地脚螺栓部位,采用二、2条型式加设临时平台,详见附图三(46-8320-5000-0106)。refer item 2.1; and for the position of anchor bolts outside the axis (the south side), refer to 2.2. see attached drawing 3 (46-8320-5000-0106)i. el+23250平面以上梁安装时,使用生命绳方式固定安全带。for the beam installation on the plane above el+23250, fix the harness
33、 with safe rope.j. el+23250平面以上斜梯安装时,采用抱箍型式脚手架(即二、3、b条)和生命绳固定安全带的方式。for the installation of inclined ladders above el+23250, adopt close loop type scaffold (item二3 b) and fix the harness with safe rope.k. el+26350、el+29400、el+34000、el+36700平台安装,安全带固定在生命绳或已安装的梁上。for the installation of platform at el
34、+26350, el+29400, el+34000 and el+36700, fix the safety harness on the safe rope or installed beam.3、选用及施工说明:adoption and descriptiona.以上未详尽的脚手架搭设位置或方式,根据施工实际情况进行调整和增设;for the scaffolds building, which is not detailed above, adjust and modify according to the actual site condition在施工有设备就位的钢结构时,与中鼎项目
35、有关人员联系,由中鼎项目有关人员协调设备安装单位,结合实际设备的安装尺寸进行施工。construct according to the actual installation dimension of equipment when equipment is furnished on the steel structure. consideration shall be given to contact with? project personnel and ask them to coordinate with other equipment installation contractor.
36、七、消耗材料用量计划:planned material quantity takeoff 序号no.名称name规格spec.数量quantity备注remark1英标脚手架管bs steel tube6 m1000根set2英标固定卡扣bs fixing coupler每袋30个30 set per bag130袋bag3英标旋转卡扣bs rotating coupler每袋30个30set per bag17袋bag4英标连接卡扣bs coupler for connection150个set5英标梯子卡扣bs coupler for ladder500个set6钢丝绳steel cabl
37、e14 mm500 m7钢丝绳扣wire rope buckle300个set8麻绳hemp500 m9麻袋gunn bag100个set10铝合金梯子aluminum alloy ladder6 m100个set11钢跳板steel gangplank900块set12方木square wood100根set需要时使用if necessary13木板wood board100150宽(width)800 m14砂轮切割机sand-disc cutter4001台set15倒链hoisting block2吨ton8台set16镀锌铁丝galvanized wire128捆bundle17防坠
38、落器falling guarder6个set下面是赠送的中秋节演讲辞,不需要的朋友可以下载后编辑删除!谢谢中秋佳节演讲词推荐中秋,怀一颗感恩之心老师们,同学们:秋浓了,月圆了,又一个中秋要到了!本周日,农历的八月十五,我国的传统节日中秋节。中秋节,处在一年秋季的中期,所以称为“中秋”,它仅仅次于春节,是我国的第二大传统节日。中秋的月最圆,中秋的月最明,中秋的月最美,所以又被称为“团圆节”。金桂飘香,花好月圆,在这美好的节日里,人们赏月、吃月饼、走亲访友无论什么形式,都寄托着人们对生活的无限热爱和对美好生活的向往。中秋是中华瑰宝之一,有着深厚的文化底蕴。中国人特别讲究亲情,特别珍视团圆,中秋节尤
39、为甚。中秋,是一个飘溢亲情的节日;中秋,是一个弥漫团圆的时节。这个时节,感受亲情、释放亲情、增进亲情;这个时节,盼望团圆、追求团圆、享受团圆这些,都已成为人们生活的主旋律。同学们,一定能背诵出许多关于中秋的千古佳句,比如“举头望明月,低头思故乡”、“但愿人长久,千里共婵娟”、“海上生明月,天涯共此时”这些佳句之所以能穿透历史的时空流传至今,不正是因为我们人类有着的共同信念吗。中秋最美是亲情。一家人团聚在一起,讲不完的话,叙不完的情,诉说着人们同一个心声:亲情是黑暗中的灯塔,是荒漠中的甘泉,是雨后的彩虹中秋最美是思念。月亮最美,美不过思念;月亮最高,高不过想念。中秋圆月会把我们的目光和思念传递给我们想念的人和我们牵挂的人,祝他们没有忧愁,永远幸福,没有烦恼,永远快乐! 一、活动主题:游名校、赏名花,促交流,增感情二、活动背景:又到了阳春三月,阳光明媚,微风吹拂,正是踏青春游的好时节。
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 仓储货物季度检查协议
- 2024年企业碳中和方案设计与实施合同
- 2024年大型设备集装箱装卸合同
- 2024年婚礼拍摄场地预定协议
- 2024年家庭教育与价值观传承协议
- 2024年婚前财产协议范本
- 2024年夫妻双方离婚后保险权益分配合同
- 2024年原料供应合同:化学品交易
- 股权激励与代持股协议书
- 科技公司合作协议书
- 辽宁省大连市金普新区2024-2025学年七年级上学期11月期中英语试题(无答案)
- 河南科技大学《材料科学基础》2021-2022学年第一学期期末试卷
- 区病案质控中心汇报
- 期中测试卷(1-4单元)(试题)2024-2025学年四年级上册数学人教版
- 2024塔吊司机的劳动合同范本
- 2024年国家公务员考试《行测》真题卷(副省级)答案及解析
- 教育局职业院校教师培训实施方案
- 2025届高考语文一轮复习:文言文概括和分析 课件
- 北京市《配电室安全管理规范》(DB11T 527-2021)地方标准
- 生涯发展展示
- 第七讲社会主义现代化建设的教育、科技、人才战略教学课件
评论
0/150
提交评论