隧道爆破施工要小专项方案
目录
1.编制依据............................................................................6
1.1.1招标设计文件..................................................................6
1.L2相关规范、规程.................................................................6
1.2编制目的...........................................................................7
13适用范围...........................................................................7
2.工程概况...........................................................................7
2.1项目隧道概况......................................................................7
2.2隧道工程情况表...................................................................7
2.3气候、水文......................................................................10
2.4施工条件........................................................................10
3.施工总体部署.......................................................................11
3.1施工组织机构及职能分工..........................................................11
3.1.1组织结构.....................................................................11
3.1.2职能分工.....................................................................11
3.2施工进度计划.....................................................................12
3.2.1进度计划.....................................................................12
3.2.2工期安排.....................................................................13
3.3资源配备情况.....................................................................14
33.1人员配备.....................................................................15
3.3.2机械准备情况................................................................15
3.4主要材料计划....................................................................16
3.5总体施工方案.....................................................................16
351隧道洞身开挖方法..............................................................16
3.5.2隧道洞身段施工................................................................16
3.6施工准备情况....................................................................25
3.6.1施工内业准备.................................................................25
3.6.2安全管理准备工作.............................................................26
3.7炸药库设置......................................................................27
4、爆破设计与施工.....................................................................27
4.1简述.............................................................................27
4.2爆破技术参数设计概述............................................................27
4.2.1单位炸药消耗量...............................................................27
4.2.2炮眼直径.....................................................................27
423炮眼深度......................................................................28
4.2.4炮眼数目....................................................................28
4.2.5炮眼利用率..................................................................28
426炮眼布置......................................................................28
4.3.隧道开挖爆破设计...............................................................29
4.3.1.□级围岩全断面或上下台阶开挖法..............................................29
4.3.2□级围岩预留核心土开挖法....................................................33
4.3.3口级围岩CD法开挖...........................................................37
434□级围岩双侧壁导坑法开挖......................................................39
4.4.爆破施工技术措施...............................................................42
4.5:网内通风.........................................................................44
4.6降尘.............................................................................45
4.7供电.............................................................................45
4.8监控量测........................................................................45
4.8.1监测目的.....................................................................45
4.8.2预警内容....................................................................45
4.83量测内容...................................................................46
4.8.4、控点布置.................................................................49
4.8.5确保监测质量的措施.........................................................51
4.9超前地质预报.....................................................................51
4.9.1超前地质预报内容.............................................................52
4.9.2各种预报手段的选择和结合....................................................53
4.9.3地质预报实施与预报结果处理..................................................54
5、爆破安全校核.......................................................................56
5.1隧道爆破地震的安全距离..........................................................56
5.2飞石最大距离的计算..............................................................57
5.3爆破冲击波安全距离的计算........................................................57
6、爆破器材管理.......................................................................57
6.1爆破器材的申购、领用............................................................57
6.2爆破器材的装卸..................................................................58
6.3爆破器材的运输..................................................................58
6.4爆破器材的储存、销毁............................................................58
6.4.1储存.........................................................................58
6.4.2销毁.........................................................................60
7、爆破施工管理.......................................................................61
7.1安全管理原则....................................................................61
7.2作业原则........................................................................61
7.3爆破区域管理....................................................................61
7.4装药管理........................................................................61
7.5安全警戒........................................................................62
7.6瞎炮处理........................................................................63
7.7控制飞石........................................................................64
7.8放炮警戒工作....................................................................64
7.9起爆............................................................................64
7.10爆破后检查.....................................................................65
8、危险源辨识及预防措施...............................................................65
8.1重大危险源辨识..................................................................65
8.2重大危险源风险预测分析..........................................................68
8.2.1坍塌.........................................................................68
8.2.2爆破伤害....................................................................68
8.2.3高空坠落.....................................................................69
8.2.4机械伤害....................................................................69
8.2.5物体打击....................................................................69
8.3危险因素预防措施.................................................................69
8.3.1坍塌.........................................................................69
8.3.2爆破伤害....................................................................70
8.3.3机械伤害.....................................................................70
8.3.4高空坠落....................................................................71
8.3.5物体打击.....................................................................71
9、质量保证措施........................................................................71
9.1方案可行与执行..................................................................71
9.2施工机械设备的管理..............................................................72
9.3加强施工监测....................................................................72
9.4质量验收标准....................................................................72
1U、安全保证措施......................................................................72
10.1技术措施........................................................................72
10.1.1施工现场安全措施............................................................72
10.1.2爆破安全措施...............................................................73
10.1.3隧道施工安全九条规定.......................................................73
10.1.4盲炮哑炮处理...............................................................74
10.1.5炸药的临时存放..............................................................75
10.1.6爆破安全性校核及有效控制...................................................75
10.1.7爆破警戒...................................................................78
10.1.8复杂地层掘进技术措施.......................................................80
10.2管理措施.......................................................................81
10.2.1建立安全生产保证体系........................................................81
10.2.2建立并落实各项安全制度.....................................................81
10.2.3安全生产责任制..............................................................82
10.2.4安全技术交底、安全教育培训制度.............................................82
10.2.5火工用品领用、清退制度.....................................................82
10.2.6门禁管理制度...............................................................83
10.2.7人员进出管理措施............................................................83
10.2.8安全文明施工奖罚制度.......................................................84
103安全生产责任制..................................................................84
10.3.1项目经理安全生产责任........................................................84
10.3.2项目总工程师安全生产责任...................................................85
10.3.3项目副经理安全生产责任.....................................................86
10.3.4专职安全员(安保部)安全生产责任...........................................88
10.3.5民爆物品管理员职责..........................................................89
10.3.6现场安全员职责..............................................................90
10.3.7爆破员职责.................................................................90
10.3.8押运员的职责...............................................................91
10.3.9保管员职责.................................................................91
10.3.10巡守员职责................................................................92
10.3.11汽车驾驶员职责.............................................................93
10.3.12领(退)料员职责..........................................................93
11、安全检查和验收....................................................................93
11.1检查人员........................................................................93
11.2检查形式和方法.................................................................94
11.3验收程序.......................................................................94
12、应急预案...........................................................................94
12.1总贝IJ........................................................................................................................................................94
12.2安全事故上报程序...............................................................95
123应急救援组织机构及职责..........................................................95
12.4事故应急的目的和适应范围.......................................................96
12.5应急措施.......................................................................96
12.6应急响应.......................................................................97
12.7事故应急预案...................................................................97
12.7.1坍塌........................................................................97
12.7.2爆炸伤害...................................................................99
12.73机械伤害..................................................................99
12.7.4高空坠落...................................................................100
12.7.5物体打击...................................................................100
12.7.6事故应急物资、设备.........................................................101
12.7.7关闭事故应急救援程序......................................................103
12.8应急救援路线..................................................................103
235国道金华婺城至武义公路婺城段TJ-2合同段隧道爆破安全专项方案
隧道爆破安全专项方案
1.编制依据
贯彻国家安全生产的法律法规、国务院393号令《建筑工程安全生产管理条例》、
国务院466号令《民用爆炸物品管理条例》等爆破施工相关的法律法规,保障施工现场
爆破安全,防止伤亡事故发生,使工程建设顺利进行,特制定隧道爆破施工安全方案。
施工现场的爆破施工必须符合有关安全运行规程。
1.1.1招标设计文件
序号名称
1《235国道金华婺城至武义公路婺城段工程TJ-2合同段招标文件》
2《235国道金华婺城至武义公路婺城段工程TJ-2合同段投标文件》
3《235国道金华婺城至武义公路婺城段工程TJ-2合同段两阶段施工图设计第一册》
4《235国道金华婺城至武义公路婺城段工程TJ-2合同段两阶段施工图设计第四册》
5《235国道金华婺城至武义公路婺城段工程施工安全总体风险评估报告》
6《235国道金华婺城至武义公路婺城段工程TJ-2合同段安全专项风险评估报告》
7《中交一公局隧道四十项规定》
8相关勘察文件
1.1.2相关规范、规程
序号名称编号
1《中华人民共和国安全生产法(2014-12-1修)》主席令第13号
2《中华人民共和国环境保护法》主席令第9号
3《建设工程安全生产管理条例》国务院令第393号
《安全事故报告和调查处理条例》国务院令第493号
《民用爆炸物品管理条例》国务院令第466号
4《隧道施工安全九条规定》四部联合印(2014)104号
5《劳动防护用品监督管埋规定》国家安监总局第1号
6《公路水运工程安全生产监督管理办法》交通部令2016年第9号
7《浙江省安全生产条例》浙江省人大公告2016年第45号
8《浙江省交通建设工程质量和安全生产管理办法》浙政令2012年第300号
9《关于进一步加强隧道工程质量管理的通知》浙交[2013]219号
10《爆破安全规程》GB6722-2014
11《公路隧道施工技术规范》GB10204-2009
12《爆破作业人项目管理要求》GA991-2012
13《公路工程施工安全技术规范》JTGF90-2015
14《隧道施工技术规范》JTGF60-2009
15《工业雷管编码通则》GA441-2003
16《民用爆炸物品存储治安防范要求》GA837-2009
235国道金华婺城至武义公路婺城段TJ-2合同段隧道爆破安全专项方案
序号名称编号
17《小型民用爆炸物品存储库安全规范》GA838-2009
18《民用爆炸物品警示标识登记标识通则》GA921-2010
19《爆破作业人员安全技术考核标准》GA53-93
20《公路工程施工安全技术规范》JTGF90-2015
21《土方与爆破工程施工及验收规范》GB50201-2012
22《公路水运工程施工安全标准化指南》ISBN978-7-114-10665-1
23《公路工程建设现场安全管理标准化指南》ISBN978-7-114-10088-8
1.2编制目的
为认真贯彻执行“安全第一、预防为主、综合治理''的方针,确保施工质量,防止安
全事故的发生,为隧道爆破施工提供科学的指导依据,特制定本施工方案,以规范作业
队施工,保障施工人员的安全,实施安全质量生产管理标准化。
1.3适用范围
本施工方案适用于235国道金华婺城至武义公路婺城段工程TJ-2合同段范围内的
隧道爆破施工。
2.工程概况
2.1项目隧道概况
本标段起讫桩号K7+700〜K11+568(婺城段终点)段路线长度约为3.868km,主
要工程内容为路基(含防护、排水工程)、桥涵、隧道、交叉、三改及配套设施等工程
(不含绿化、交通安全设施、隧道机电)及婺城段全线起讫桩号(K0+000〜KU+568)
段范围内的的路面工程(含底基层、基层、沥青混凝土面层)等工程的施工完成、缺陷
责任期缺陷修复及保修期保修责任。
木项目上马山分离式隧道左洞长1062米,右洞长1072米,隧道洞身开挖27.36
万nV;和安分离式隧道左洞长258米,右洞长220米,隧道洞身开挖5.79万m3;大
山分离式隧道左洞长748米,右洞长783米,隧道洞身开挖19.55万nV;隧道爆破方
量合计52.70万n?。
隧道长度隧道开挖量
隧道名称/m备注
左洞右洞(万1^)
上马山隧道1062107227.36分离式
大山隧道74878319.55分离式
和安隧道2582205.79分离式
2.2隧道工程情况表
(I)隧道基本情况
235国道金华婺城至武义公路婺城段TJ-2合同段隧道爆破安全专项方徭
隧道形式分离式隧道
净高(m)5.05.0
净宽(m)1414
通风左右洞各4组16台中112cm纵向射流通风(全隧道)
照明隧道专用照明灯具(LED型),分级电脑自动定时控制
消防灭火器,消防栓,给水栓
(2)隧道洞身围岩等级分类情况
235国道金华整城至武义公路整城段TJ2合同段磋道存班安全专项力突
隧道洞身围岩等级情况分类统计表(不含明洞)
围岩等级V级出岩级围岩匚级围岩
合计
村副类型S5JQS5aS5bS4JQS4aS4bS3JQS3S3gS3gl
上马山右洞605640610132063625221032
上马山左洞685540870107061825221022
和安右洞312500172609800197
和安左洞640002122011600223
火山右洞2054200407005122522763
大山左对20533004579.8045022522725
小计263243130148123436.802430.2100网3%2
合计636707.82616.23962
百分比(%)16.0517.8666OK100
注:表中除百分比外,其余的位均为m,且为单洞长度,
今中交一公同桥陡工程有限公司第9页
235国道金华婺城至武义公路婺城段TJ-2合同段隧道爆破安全专项方案
2.2隧道地质情况
(1)上马山隧道进出洞口位于丘陵斜坡和沟谷附近,植被发育,自然坡度为20-330;
表面覆盖较厚的含角砾粉质黏土和含碎石粉质黏土,灰黄色,可塑中密,下伏基岩为凝
灰质粉砂岩;隧道穿过坡洪积、残坡积、强风化-中风化岩体,青灰色,岩体呈碎块状
镶嵌结构,裂隙较发育,岩质较硬。受断层F2影响,进洞口段岩体破碎,软弱。隧道
洞身围岩大部分为中-微风化的凝灰质粉砂岩,局部夹凝灰质砂岩,顶板最大埋深约
155m。总体围岩地质条件较好,但洞身局部存在节理密集带以及受断层F3、F4影响,
局部地段岩体破碎,软弱,易碎,围岩地质条件较差。隧道区地下水主要为基岩裂缝水
和构造裂缝水,赋存于裂隙内,水量贫乏,由大气降水补给,水文地质条件较简单。
(2)大山隧道进出洞口位于丘陵坡麓,乔灌木比较茂盛,自然坡度为7-17。;表面
覆盖较薄含碎石粉质黏土,灰黄色,可塑,下伏基岩为凝灰质粉砂岩;隧道穿过坡洪积、
残坡积、强风化-中风化岩体,青灰色,岩体呈碎块状镶嵌结构,裂隙较发育,岩质较
硬。隧道洞身围岩大部分为中-微风化的凝灰质粉砂岩,局部夹凝灰质砂岩,顶板最大
埋深约170m。节理裂隙不发育,岩体较完整、新鲜、岩芯面光滑新鲜,质坚硬,围岩
总体地质条件较好,但洞身局部存在节理密集带以及受断层F5、F6影响,局部地段岩
体破碎,软弱,易碎,围岩地质条件较差。隧道区地下水主要为基岩裂缝水和构造裂缝
水,赋存于裂隙内,水量贫乏,由大气降水补给,水文地质条件较简单。
(3)和安隧道进出洞口位于丘陵坡麓,乔灌木比较茂盛,自然坡度为7-17。;表面
覆盖较薄含碎石粉质黏土,灰黄色,可塑,下伏基岩为凝灰质粉砂岩;隧道穿过坡洪积、
残坡积、强风化-中风化岩体,青灰色,岩体呈碎块状镶嵌结构,裂隙较发育,岩质较
硬。隧道洞身围岩大部分为中■微风化的凝灰质粉砂岩,局部夹凝灰质砂岩,顶板最大
埋深约60m。隧道区地下水主要为基岩裂缝水和构造裂缝水,赋存于裂隙内,水量贫乏,
由大气降水补给,水文地质条件较简单。
2.3气候、水文
项目处于亚热带季风气候区,温暖湿润,四季风明,雨量充沛,年平均气温17.3℃,
一月份月平均气温4.9C,七月份月平均气温29.4C。雨量充沛,全区多年年平均降雨
量1440.27毫米,但降雨量和降水日数受季风和台风的影响分布不均,一般3・7月上旬
为春雨及梅雨季节,约占年降雨量的55%以上,最大月降雨量常出现在6月份。
2.4施工条件
中交一公局桥隧工程有限公司
235国道金华婺城至武义公路婺城段TJ-2合同段隧道爆破安全专项方案
(1)交通条件
木项目区域内主要道路有汀杨线等地方县乡村道路,道路宽6m,现状为水泥碎路
面,厚度20cm,弯道多,会车条件少。
(2)施工用电
沿线电网设施分布不均,公路建设专线未架设,隧道施工用电需从就近电网架设专
线供电。
(3)通讯
施工区沿线通讯线路完备,均装有有线电话。无线电话讯号可覆盖全境。
(4)施工用水
隧道用水采用隧道附近打井,经抽水泵汇集至蓄水池。
(5)工程用材料等
当地物资市场供应丰富,施工材料来源充足,所需物资材料均可向当地市场购买。
3•施工总体部署
3.1施工组织机构及职能分工
3.1.1组织结构
隧道施工组织结构图
3.1.2职能分工
工程部:隧道施工方案编制,技术交底,优化设计变更。
试验室:原材进场检验,混凝土及压浆料质量控制。
测量组:施工放样,监控量测。
安保部:安全交底和培训,义明、环保管理。
物设部:机械设备购置、租赁、进场检验、维修、保养,材料调拨。
综合部:后勤保障,宣传报道。
计合部:经营核算、成本分析。
财务部:资金管理。
质检部:工程质量控制,过程巡检,工序交接检。
隧道负责人:施工过程管理。
爆破班组:爆破施工。
开挖班组:开挖施工。
中交一公局桥隧工程有限公司
235国道金华婺城至武义公路婺城段TJ-2合同段隧道爆破安全专项方案
支护班组:初支施工。
二衬班组:衬砌施工。
出渣班组:出渣施工。
拌和站:隧道施工用混凝土生产。
3.2施工进度计划
3.2.1进度计划
VJQ级围岩作业进度指标(循环进尺0.5m)
项目测量放样超前支护开挖出硝架立钢架(含临时钢架)锚网喷合计
时间(h)0.5平均3.53.01.53.512
备注每天进尺1m
Va级围岩作业进度指标(循环进尺0.5m)
项目测量放样超前支护开挖出硝架立钢架(含临时钢架)锚网喷合计
时间(h)0.5平均3.53.01.53.512
备注每天进尺1m
Vb级匿岩作业进度指标(循环进尺0.75m)
项目测量放样超前支护开挖出砧架立钢架锚网喷碎合计
时间(h)0.5平均3.53.01.53.512
备注每天进尺L5m
IVJQ级围岩作业进度指标(循环进尺0.75m)
项目测量放样超前支护钻眼爆破通风出渣架立钢架锚网喷碎合计
时间(h)0.5平均2.02.00.53.01.52.512
备注每天进尺L5m
IVa级围岩作业进度指标(循环进尺1.0m)
项目测量放样超前支护钻眼爆破通风出渣架立钏架锚网喷碎合计
时间(h)0.5平均2.02.00.53.01.52.512
备注每天进尺2.0m
Wb级围岩作业进度指标(循环进尺1.2m)
项目测量放样超前支护钻眼爆破通风出渣架立钢架锚网喷磴合计
时间(h)0.5平均2.02.00.53.01.52.512
备注每天进尺2.4m
III级围岩作业进度指标(循环进尺3.0m)
中交一公局桥隧工程有限公司
235国道金华婺城至武义公路婺城段TJ-2合同段隧道爆破安全专项方案
项目测量放样钻眼爆破通风出渣锚网喷碎合计
时间(h)0.54.00.54.03.012
备注每天进尺6.0m
3.2.2工期安排
隧道洞身开挖具体进度计划见下表(不含明洞):
上马山隧道进度计划表
序号项目名称工程量进度指标所需工期开始时间结束时间工期
VJQ68m1.0m/天68天
Va55m1.0m/天55天
Vb40m1.5m/天27天
左
IVJQ87m1.5m/天58天2018.02.232019.02.22364
洞
IVa0m2.0in/天0
Nb107m2.4m/天45天
暗
天
洞in665m6.0m/天111
1
工VJQ60m1.Om/天60天
程
Va56m1.0m/天56天
Vb40m1.5m/天27天
右2018.02.232019.02.11353
I\'JQ61m1.5m/天41天
洞
IVaOm2.0m/天0
IVb132m2.4m/天55天
III683
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 令我印象深刻的一个人9篇
- 2025版高考物理二轮复习 教材情境2 基于教材中“例题和习题”的情境命题
- 广西河池市校联体2024-2025学年高二上学期联考(12月) 数学试题(含解析)
- 2024-2025学年内蒙古呼和浩特市回民区九年级(上)期中物理试卷(含答案)
- 相对密度仪校准规范-编写说明
- 2025届安徽省江淮十校高三上学期第二次联考(11月)生物试题
- 课刘义庆《陈太丘与友期》课件
- 2025年中考英语一轮教材复习 写作话题11 人际交往
- 毛泽东思想和中国特色社会主义理论体系概论(山西青年职业学院)知到智慧树答案
- 《丰田教育手册》课件2
- 人教版(2024新版)英语七年级上册第二次月考综合测试卷(含答案)
- 2024年部编版语文小学三年级上册期末质量检测题附答案
- 全国高中生物奥林匹克竞赛考试大纲
- 质量控制工作重难点分析及其应对措施
- 绿植租赁维护摆放服务实施方案
- 国家开放大学电大建筑制图基础机考网考题库及答案C完整版
- 危险废物库房建设项目竣工环保验收监测调查报告
- 2024年医院护理部年度工作计划(七篇)
- 招标代理机构选取投标方案(技术标)
- 2024年新人教版七年级上册生物课件 第三章 微生物 综合实践项目 利用细菌或真菌制作发酵食品
- “四史”(改革开放史)学习通超星期末考试答案章节答案2024年
评论
0/150
提交评论