铁路站前工程LRTLSG-3标
制梁场80T龙门吊安拆安全
专项施工方案
中国建筑股份有限公司莱荣铁路ZQSG-3标项目部
2023年5月
目录
第一章编制说明.........................................................1
1.1编制依据......................................................................1
1.2编制原则......................................................................1
1.3编制范围......................................................................2
第二章工程概况.........................................................2
2.1工程基本情况..................................................................2
2.2项目概况......................................................................2
2.3自然地理条件..................................................................3
2.4工程地质......................................................................3
2.5水文情况......................................................................3
2.6气象条件......................................................................3
第三章施工安排.........................................................4
3.1项目管理组织..................................................................4
3.2项目管理目标..................................................................5
第四章施工计划.........................................................6
第五章施工准备与资源配置计划............................................6
5.1施工准备......................................................................6
5.2龙门吊主要部件技术参数........................................................8
5.3资源配置计划..................................................................9
第六章龙门吊安装施工方法及工艺要求.....................................10
6.1安装流程.....................................................................10
6.2轨道安装.....................................................................11
6.2.1轨道基础施工.............................................................11
6.2.2走行轨道安装.............................................................12
6.2.3滑触线安装...............................................................13
6.3龙门吊组装...................................................................13
6.3.1主梁及支腿的组装.........................................................13
6.3.2大车的组装...............................................................14
I
6.3.3天车的组装...............................................................14
6.4支腿吊装.....................................................................14
6.4.1钢性支腿吊装工序.........................................................15
6.4.2柔性支腿吊装工序.........................................................17
6.5主梁吊装.....................................................................17
6.6安装天车.....................................................................18
6.7附属设施的吊装...............................................................19
6.8电气安装.....................................................................19
6.9临时设施拆除.................................................................21
6.10试车........................................................................21
第七章安全检查及验收..................................................22
7.1龙门吊整体安全检查及验收内容.................................................22
7.2吊钩安全检查及验收内容.......................................................23
7.3滑轮与护罩安全检查及验收内容.................................................24
7.4制动器安全检查及验收内容.....................................................24
7.5安全防护装置安全检查及验收内容...............................................25
7.6架体安全检查及验收内容.......................................................25
7.7传动系统安全检查及验收内容...................................................26
7.8龙门吊验收要求...............................................................26
7.9龙门吊安全检查记录表.........................................................27
7.10龙门吊验收程序及验收责任人..................................................27
7.11龙门吊设备维修保养制度......................................................28
第x章龙门吊拆除......................................................28
8.1龙门吊拆除工艺流程...........................................................28
8.2安全技术交底.................................................................29
8.3场地要求.....................................................................29
8.4拆解人员配置.................................................................29
8.5主要起重设备、机具的准备.....................................................29
8.6龙门吊拆除施工方法...........................................................30
第九章施工安全保证措施................................................34
II
9.1组织保障.....................................................................34
9.1.1组织机构.................................................................34
9.1.2应急救援小组机构及职责...................................................35
9.2技术措施.....................................................................37
9.2.1技术要求.................................................................37
9.2.2安全技术措施.............................................................37
9.3安全文明措施.................................................................38
9.3.1安全控制措施.............................................................38
9.3.2环保水保措施.............................................................39
9.3.3文明施工措施.............................................................40
9.3.4完工清场及撤场措施.......................................................40
9.4龙门吊施工应急预案...........................................................40
9.5危险源辨识及危险源原因分析...................................................41
9.5.1人为因素.................................................................43
9.5.2施工临时用电.............................................................44
9.5.3机械设备.................................................................45
9.5.4高空作业.................................................................46
9.5.5电焊与气焊安全保证措施...................................................48
9.6应急救援措施.................................................................49
9.6.1物体打击急救措施.........................................................49
9.6.2机械伤害急救措施.........................................................50
9.6.3高处坠落急救措施.........................................................50
9.6.4触电事故急救措施.........................................................52
9.7应急响应.....................................................................53
9.7.1接警与通知...............................................................54
9.7.2应急救援程序.............................................................54
9.7.3现场保护.................................................................56
9.7.4警报与紧急公告...........................................................56
9.7.5事态监测.................................................................57
9.7.6警戒与治安...............................................................57
III
9.7.7人群疏散与安置...........................................................57
9.7.8医疗与卫生...............................................................57
9.7.9公共关系.................................................................58
9.7.10应急救援人员的安全......................................................58
9.7.11应急终止与现场恢复......................................................58
第十章BIM+智慧工程项目协同管理平台.....................................59
10.1重流程、轻数据..............................................................59
10.2平台架构....................................................................59
10.3端口多样性..................................................................60
第十一章绿色施工......................................................60
11.1指导思想及原则..............................................................60
11.1.1指导思想................................................................60
11.1.2建设原则................................................................61
11.2总体目标....................................................................61
11.3组织结构....................................................................61
11.4实施内容....................................................................62
第十二章新型冠状病毒感染肺炎疫情防控措施...............................63
12.1新型冠状病毒肺炎常识........................................................63
12.1.1新型冠状病毒肺炎发病症状................................................63
12.1.2普通感冒和新型肺炎的区别................................................63
12.1.3传播途径................................................................63
12.1.4新型冠状病毒肺炎的潜伏期................................................64
12.2疫情防控组织机构............................................................64
12.2.1疫情防控领导小组........................................................64
12.2.2人员及职责..............................................................65
12.3防疫物资准备................................................................65
12.4防控制度及管理措施..........................................................66
12.4.1项目疫情防控措施........................................................66
12.4.2施工现场防控措施........................................................67
12.5应急处置....................................................................68
IV
12.5.1信息报告................................................................68
12.5.2应急处置措施............................................................68
12.5.3扩大响应................................................................69
12.5.4应急结束................................................................69
12.6应急保障....................................................................69
第十三章计算书........................................................71
13.1吊机、钢丝绳及地基承载力选用计算............................................71
13.1.1吊机选用................................................................71
13.1.2钢丝绳选用计算..........................................................74
13.1.3汽车吊抗倾覆验算........................................................75
13.1.4地基承载力验算..........................................................76
13.2龙门吊轨道基础计算书........................................................77
附件....................................................................79
1龙门吊合格证及图纸.............................................................79
2安装资质证书及特种人员证书.....................................................79
V
I
第一章编制说明
1.1编制依据
表1.1编制依据
序号类别文件名称编号
1中华人民共和国安全生产法/
国家
2危险性较大的分部分项工程安全管理规定住建部令第37号
行政
文件住房城乡建设部办公厅关于实施《危险性较大的分
3建办质(2018)31号文
部分项工程安全管理规定》有关问题的通知
4《起重机械安全规程第5部分:桥式和门式起重机》GB6067.5-2014
5《起重机设计规范》GB/T3811-2008
6《通用门式起重机》GB/T14406-2011
国家
7行业《起重设备安装工程施工及验收规范》GB50278-2010
8标准《建设工程施工现场供用电安全规范》GB50194-2014
规范
9《铁路桥涵工程施工安全技术规程》TB10303-2023
10《起重机械安全规程第一部分:总则》GB6067.1-2010
11《铁路工程基本作业施工安全技术规程》TB10301-2023
12合同xx铁路站前工程施工总价承包合同/
设计
13xx铁路站前工程施工施工图纸工程/
文件
14/
15其他80t通用门式起重机使用说明书/
1680t通用门式起重机安装图/
1.2编制原则
1安全第一原则
以人为本,坚持安全发展,坚持安全第一、预防为主、综合治理。
2坚决执行规范、规程原则
贯彻执行各项技术标准、安全技术规程,执行业主针对本工程建设制
定的各项安全管理办法、细则和规程。确保龙门吊安装质量,为实现预制
工程顺利进行提供机械保障,以适应安全生产和施工组织安排的要求。
3杜绝事故原则
1
有效对龙门吊安装、拆除过程实施监控,杜绝一般及以上安全事故的
发生。
1.3编制范围
本方案适用于莱西至荣成铁路站前三标xx制梁场龙门吊安装及拆除工
程。xx制梁场设置4台型号为MGG80/10t-40m-18m的80T龙门吊,均设
置在制梁区。
第二章工程概况
2.1工程基本情况
表2.1工程基本情况和各参建方基本情况
序号项目内容
1工程名称xx铁路站前工程LRTLSG-3标xx制梁场
2工程地址xx区
3建设单位济青高速铁路有限公司
4勘察设计单位
5咨询单位
6监理单位中铁二院(成都)咨询监理有限责任公司
7质量监督单位
8施工(总承包)单位/中国建筑第x工程局有限公司
9工程类型高速铁路工程
10施工范围xx制梁场的箱梁预制工程
2.2项目概况
xx铁路站前工程三标段xx制梁场位于山东省威海DK116+141.7~
DK164+601.79,线路长度48.46km。
xx制梁场承接xx铁路LRTLSG-3标段DK148+344.84~DK152+705.51
跨金海路特大桥、DK152+989.67~DK160+671.04跨荣乌高速特大桥、
DK161+982.90~DK164+601.79跨圣海路特大桥共16.3km范围内415孔双
线箱梁预制及架设施工,包含32m简支箱梁392孔,24m简支箱梁23孔。
2
规划梁场占地约233亩。
2.3自然地理条件
根据xx制梁场预制箱梁分布情况,并结合线路沿线实际地形确定制梁
场的场址,梁场设计位置中心里程为DK155+600xx区宋村镇郭家店村,场
址地势平坦,交通便利,制梁场占地面积233亩。
图2.3梁场平面位置
2.4工程地质
xx制梁场场区覆土层覆土层主要为:人工堆积层(Q4ml)种植土、全新
统冲洪积层(Q4al+pl)黏性土、粉土;下伏晋宁期(γ23)花岗岩。
2.5水文情况
地下水类型主要为基岩裂隙水,主要赋存于基岩风化裂隙及构造裂隙
中,受节理裂隙发育及连通程度影响富水性不均,主要受大气降水补给,
排泄方式主要为地下水径流及人工开采。勘探期间场地稳定水未见,水位
季节变幅2~4m。
2.6气象条件
xx区地处北温带,属大陆性季风气候,四季分明。年均气温11.5℃。
3
年降水量762.2毫米,夏季较为集中,6~9月份降水量约占全年70%,春
秋季降水偏少,常发生干旱。年日照时数2540.7小时,无霜期194天。冬
季漫长,盛行从大陆北部吹来的干冷冬季风,气温偏低,为半岛地区低温
站点。夏季最短,盛行从海洋吹来的暖湿夏季风,春秋两季属冬夏季风转
换期,春季大风天气较多。
第三章施工安排
3.1项目管理组织
项目管理组织机构见图3.1。具体职责如下:
场长:黄宇东,负责龙门吊安拆全面工作。
生产经理:李登科,负责龙门吊安拆现场施工工作。
总工程师:张兴茂,负责施工队对安拆方案执行的监督工作。
商务经理:李庆国,负责对龙门吊报备手续进行检查。
安全总监:任杰,负责龙门吊安拆安全技术交底和安全监督工作。
质量总监:刘位仓,负责龙门吊安拆人员进行质量培训。
工程部长:张国伟,负责对龙门吊安拆过程进行现场盯控。
技术部长:张景全,负责对龙门吊安拆方案进行编制并交底。
物资部长:侯磊,负责对龙门吊安拆设备调度工作。
计划合同部部长:史晓东,负责对龙门吊安拆过程预埋件等进行实时
监控。
4
场长
总工程师生产经理商务经理质量总监安全总监
工计安综
程划全测物试合
技合质量资验办
术同量部部室公
部部部室
图3.1项目组织机构
3.2项目管理目标
本工程施工中除了需要满足质量目标、工期目标,还应满足安全、经
济、文明施工环保等要求,具体目标见表3.2。
表3.2施工管理目标
序号项目内容
1工期目标施工进度满足施工总工期的整体目标。
杜绝龙门吊安装工程质量等级事故,减少质量通病;轨道安装、
龙门吊组装、支腿吊装、主梁安装、小车安装、附属设施及电
2质量目标
气安装质量达到国家现行验收标准,符合设计文件和有关技术
规范要求;龙门吊安装工程一次验收通过。
杜绝轻伤及以上事故发生,包括安装过程中起重机械伤害,物
体打击、高空坠落、火灾等事故;消灭责任等级高空作业安全
3安全目标
事故及大型施工设备安全事故等。杜绝责任从业人员死亡事
故;杜绝责任特种设备等事故。
首先认真落实铁路建设项目环境保护“三同时”制度,全面落实
国家主管部门批复的环、水保措施和要求,最大限度保护各生
4环保目标
态功能区原生态系统,尽量减少对自然资源、水资源及文物等
环境敏感点的影响
坚持“预防位置、防治结合”的方针,保证职工生活及工作场所
干净整洁、施工现场粉尘及有害气体不超过国家规定标准、劳
5职业健康目标动保护符合有关规定;强化劳动防护用品的使用监督,为作业
人员提供符合安全卫生标准的劳动保护设施和个人防护用品;
防止食物中毒,杜绝职业病发生,确保无疫情、无传染病发生。
现场布局合理,环境整洁,物流有序,标识醒目;工地和道路
6文明施工目标
无飞尘、无泥泞、无坑洼;材料堆码整齐、机械设备摆放整齐、
5
序号项目内容
生产生活区规划整齐;生产办公区整洁、生活居住区清洁、伙
房餐厅清洁、厕所排污区清洁;水管不漏水、电线不漏电、房
屋不漏雨、车辆不漏油、通风管道不漏风。创建文明工地。
第四章施工计划
根据总体施工计划安排,xx制梁场龙门吊安装时间为2023年2月27
日-2023年3月30日,拆除时间2023年5月31日-2023年6月30日。
表4龙门吊安装拆除时间
时长
序号工作内容起始时间结束时间备注
(天)
1龙门吊基础施工2023年2月27日2023年3月20日22/
2龙门吊进场手续报备2023年3月10日2023年3月20日11/
3龙门吊安装2023年3月21日2023年3月30日10/
4龙门吊验收2023年3月31日2023年4月11日12/
5龙门吊拆除2023年5月31日2023年6月30日31/
图4龙门吊安装计划横道示意
第五章施工准备与资源配置计划
5.1施工准备
1核实作业所需的各类技术参数及依据的可靠性,清点构件及零配件
到货情况和质量保证状态。
2作业前组织全体人员学习,由专业技术工程师讲解龙门吊结构、性
能参数,对作业进行技术交底和危害因素的辩识、学习并制定相应的防范
措施,使全体作业人员认可并熟知整个工序和要点及注意事项,能够明白
安装步骤及安装过程中的针对性危害,全员通过后方可施工,未明确上述
6
要求的人员不得参加此项施工。
3安全部要对所有进场工作人员进行安全教育培训和安全交底。
4使用经校验合格的测量工具。
5专业工程师和生产经理对参与作业的机械进行详细的检查,确认合
格后,投入使用。
6对所有特殊工种人员资格进行审查。
7对起重工器具进行检查确认。
8对使用的材料、连接件进行检查确认。
图5.1龙门吊示意
9龙门吊进场前要到
10布设龙门吊拼装、拆除安全施工警戒范围、设置各类施工警示标
志。
11龙门吊轨道基础做好防水、排水设施,轨道基础不得有雨水浸泡。
12龙门吊拼装、拆除起重机械用吊装钢丝绳等经检查合格,各类辅
助钢丝绳使用前严格检查,起重机械操作人员必须持证上岗。
13吊装指挥人员具备多年吊装经验,且持证上岗,吊装现场设专人
安全监护。
14配备足够的安全防护用品安全带、安全绳等,防护用品验收合格。
7
15龙门吊安拆请有相关安拆许可的单位和人员进行施工,相关许可
见附件。
1680T龙门吊单根主梁自重约16.5t,吊装用2台100T汽车吊。
表5.1100T汽车吊性能
主臂长度(m)
工作半径(m)
13.017.822.527.231.936.641.3
3.010080/////
3.5937762////
4.0887262////
4.579676142///
5.07262604240//
5.56558564239//
6.05955524237.531.5/
6.5545248.240.535.831/
7.05049453934.529.5/
7.5464542.5373328.7/
8.0424140.635.531.827.623.5
9.036.535.53532.529.525.722
10.0323130.63027.52420.8
11.0/27.526.627.525.722.619.6
12.0/23.523.324.52421.218.9
14.0/17.51718.519.518.816.9
16.0//1314.2151615.2
18.0//1011.21212.613.2
5.2龙门吊主要部件技术参数
表5.280吨龙门吊技术性能参数
机构名称起升机构机构名称主小车运行大车运行
项目主起升副起升项目机构机构
起重量t8010轨距mm/40000
起重速度m/min0.677运行速度m/min0-66
工作级别M3M3工作级别M3M3
最大起升
m1818机距mm//
高度
8
机构名称起升机构机构名称主小车运行大车运行
项目主起升副起升项目机构机构
电源三项50HZ380V
结构/缓冲行程mm60188
钢
支数14钢轨型号方钢35*70/
丝
绳工作
KN/车轮直径mmφ400*4φ400*8
拉力
卷扬机型号JM6//
型号YZR160L-6型号//
电CD10T电电
动功率Kw15动葫芦动功率Kw2*34*4
机机
转速r/min960转速r/min13801380
制型号液压/减型号BL22BL22
动制动速传动
N.m/i8787
器力矩器比
限位开关LX10-31限位开关LX10-11LX10-11
5.3资源配置计划
表5.3-1龙门吊安装施工机械设备配置
序号设备名称数量备注
1汽车吊2台100t
2手拉葫芦4件/
3千斤顶1台/
4交流电焊机2台/
5气割设备2套/
6框式水平仪1件/
7切割机1台/
8角向磨光机2台/
9安全带5条/
10手虎钳2把/
11力矩扳手2把/
表5.3-2龙门吊安装测量仪器配置
序号设备名称数量备注
1全站仪1台/
9
序号设备名称数量备注
2水准仪1台/
3500V兆欧表1台/
4万用电表1台/
550M钢卷尺1把/
61M钢直尺1把/
7100MM塞尺1把/
80~200MM游标卡尺1把/
90~200MM弹簧称1把/
表5.3-3劳动力配置计划
序号名称数量备注
1管理人员12/
2起重指挥1持证上岗
3起重工2持证上岗
4安拆工3持证上岗
5电工1持证上岗
6合计19/
第六章龙门吊安装施工方法及工艺要求
6.1安装流程
10
施工准备
轨道安装
支腿地面组装支腿的整体吊装及竖立缆风绳及地锚的固定
主梁地面组装主梁、大车的整体吊装
小车地面组装起重小车的整体吊装
安装机电系统安装夹轨器
拆除各类临时设施安装各种安全装置
龙门吊试吊
龙门吊安装完成
图6.1龙门吊安装流程
6.2轨道安装
6.2.1轨道基础施工
龙门吊轨道基础为120×20+40×40(单位:cm)横断面,采用C25钢筋
混凝土(如图6.2.1),基础每5m布设一个控制点进行标高控制,混凝土浇筑
完成后顶面进行拉线收浆,严格按要求控制混凝土的顶面高程及平整度,
在龙门吊基础顶面中心位置预埋M20U型螺栓。地基采用天然地基,开挖
地基后,基槽打底夯实,直接做基础,地基承载力达到120Kpa,当不满足
承载力要求时换填50cm山皮石,分层填筑分层压实,使其满足承载力要求。
原地面承载力能满足要求,后附xx制梁场地勘报告。
11
图6.2.1龙门吊轨道基础剖面示意
6.2.2走行轨道安装
龙门吊支腿走行轨道采用43kg/m钢轨。走行轨道的安装前,应注意做
好走形轨道基础的竣工测量,确保其轨道的间距、轴线等无误,轨道安装
应控制轨道的平顺、轨道接头处的顺接,并利用基础预埋件牢固固定轨道,
同时在轨道两端尽头设置限位装置。
图6.2.2龙门吊轨道安装
轨道应可靠固定,螺栓不得松动,压板不得变形,轨面不得有裂纹、
疤痕和影响安全运行等缺陷,轨道连接处安装连接铜线。
轨道基础按要求铺设完成,确定轨道中心线和基础水平距离。轨道由
安装负责人、专业工程师、质量总监三级复测验收。安装前应测量轨道的
实际情况,选择最佳位置作为门式起重机的安装基准位置。使用工具:水
12
准仪、钢卷尺、弹簧秤、塞尺,具体检测要求如下。
1大车轨距的极限偏差10mm。
2轨道接头间隙不大于2mm。轨道接头高低差及侧向错位不大于1mm。
3轨道顶面对其设计位置的纵向倾斜度不大于3/1000,全行程内高低
差不大于10mm。
4轨道顶面基准点的标高相对于设计标高允差±10mm。
5同一截面内两平行轨道的标高差,不大于10mm。
6两平行轨道的接头应错开,其错开距离不应等于起重机前后车轮的
基距。
7轨道上的车挡在吊装起重机前装好,同一跨端的车挡与起重机缓冲
器均应接触。
6.2.3滑触线安装
80T龙门吊采用架空滑触线的方式供电,滑触线采用φ10圆钢。电线
杆布置于场区主干路北侧,距离道路边缘0.5m,每隔40.6m布设一根,电
线杆高度12m,埋深2m,杆坑底部必须夯实。新建架空滑触线单线长度405m,
对地高度为10m。电线杆及低压配电箱必须各打一处接地极,其阻值不得
大于4欧姆。靠近拌合站附近的电线杆下部设置C20混凝土防撞墩,防撞
墩尺寸为1.2m*0.8m*0.8m,并在防撞墩上涂刷黄黑警示标示。
6.3龙门吊组装
6.3.1主梁及支腿的组装
主梁一般采用销轴连接,现场施工只需将销轴打入主梁上下弦的阴阳
接头中,在打销子时应调整好主梁的垂直度,各主梁的高低不能相差
10mm,绝对不能将销轴用蛮力打入。最后组装好的主梁的直线度、上拱度、
旁弯值、悬臂端上翘度、对角线相对差等均应符合设计及验收要求。
主梁上的平台构件在地面组装好,并应留出位置供吊装时绑扎钢丝绳
13
用,在绑扎钢丝绳处应设好保护钢丝绳的包角措施。
支腿在施工场地拼装完成。
图6.3.1龙门吊构件地面组装
6.3.2大车的组装
在厂内安装好的大车现场稍经调整即可安装上大车轨道上,由于超长
而分开运输的大车,则需要重新安装,组装完成后应做以下检查:
1检查基准;
2检查车轮端面的水平偏斜;
3车轮找平(包括直线度、垂直度及同位差)。
6.3.3天车的组装
在厂内安装好的天车到现场稍经调整即可安装到天车轨道上,由于超
宽而分开运输的大t位或特殊起重机的小车,则需要重新安装,应检查小车
轨道、小车车轮的平行度、垂直度及同位度,是否符合有关技术要求,具
体规定见以下:
天车轨道要求:轨道在接头处高低差不大于1mm,间隙不大于2mm,
横向错位差不大于1mm。
6.4支腿吊装
吊装选择在无大风、无雨
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 应急人财物管理制度
- 律师党支部管理制度
- 微消防日常管理制度
- 心理矫正室管理制度
- 快递员日常管理制度
- 急救与治疗管理制度
- 总店长门店管理制度
- 情景剧皮肤管理制度
- 战备食品库管理制度
- 房产项目部管理制度
- 信息用户管理制度
- 紧固件行业生产安全标准化建设考核试卷
- 2025年成都香城悦动置业有限公司招聘题库带答案分析
- 培训学员生活管理制度
- 广东省广州市增城区2023-2024学年八年级下学期期末数学试题(含答案)
- 广东省广州市番禺区2022-2023学年三年级下学期数学期末试卷(含答案)
- 分包安全生产管理制度
- 南充中考理综试题及答案
- 厂区卫生清洁管理制度
- 养老项目商业计划书
- 2025年新高考1卷(新课标Ⅰ)数学试卷
评论
0/150
提交评论