项目风险管理

RevisedbyBLUEontheafternoonofDecember12,2020.

RiskManagementPlan

for

<project>

<author>

<date>

<version>

TableofContents

TableofContents.................................................

RevisionHistory..................................................

Purpose..........................................................

RolesandResponsibilities........................................

RiskDocumentation................................................

Activities.......................................................

ScheduleforRiskManagementActivities...........................

RiskManagementBudget............................................

RiskManagementTools.............................................

Appendix.SampleRiskDocumentationForm..........................

RevisionHistory

DateReasonForChanges

initialdraft

Name

<author>

Version

draft1

Purpose

Thisdocumentdescribeshowwewillperformthejobofmanagingrisksfor<project>.Itdefinesrolesandresponsibilitiesforparticipantsintheriskprocesses,theriskmanagementactivitiesthatwillbecarriedout,thescheduleandbudgetforriskmanagementactivities,andanytoolsandtechniquesthatwillbeused.

RolesandResponsibilities

Project

Manager

TheProjectManagerwillassignaRiskOfficertotheproject,andidentifythisindividualontheproject’sorganizationchart.TheProjectManagerandothermembersoftheProjectManagementteam<listnamesorroles>shallmeet<statefrequency;biweeklysuggested>toreviewthestatusofallrisk

mitigationefforts,reviewtheexposureassessmentsforanynewriskitems,andredefinetheproject'sTopTenRiskList.

RiskOfficerTheRiskOfficerhasthefollowingresponsibilities

andauthority:

<describewhattheriskofficerwilldo;mightincludecoordinatingriskidentificationandanalysisactivities,maintainingtheproject’srisklist,notifyingprojectmanagementofnewriskitems,reportingriskresolutionstatustomanagement;theRiskOfficershouldnormallynotbetheProjectManager.>

ProjectMemberAssigneda

Risk

TheRiskOfficerwillassigneachnewlyidentifiedrisktoaprojectmember,whowillassesstheexposureandprobabilityfortheriskfactorand

reporttheresultsofthatanalysisbacktotheRisk

Officer.AssignedprojectmembersarealsoresponsibleforperformingthestepsofthemitigationplanandreportingprogresstotheRiskOfficerbiweekly.

RiskDocumentation

RiskList

RiskData

Items

Theriskfactorsidentifiedandmanagedforthisprojectwillbeaccumulatedinarisklist,whichislocated<statewhererisklistislocated;couldbeanappendixtothisplan,orinaseparatedocument,orinadatabaseortoolsomewhere.>Thetenriskitemsthatcurrentlyhavethehighestestimatedriskexposurearereferredtoastheproject’sTopTenRiskList.

Thefollowinginformationwillbestoredforeach

projectrisk:<listanddefineriskdataitems.Some

Risk

Identificatio

n

suggestions:RiskID,classification,description,

probability,impact,riskexposure,firstindicator

thatriskisbecomingaproblem,mitigation

approaches,owner,datedue,contingencyplan,

contingencyplantrigger>

Closing

Risks

Ariskitemcanbeconsideredclosedwhenitmeets

thefollowingcriteria:<example:theplanned

mitigationactionshavebeencompletedandthe

estimatedriskexposureofprobabilitytimesimpact

islessthan2>

Activities

Participants

<Statethetechniquesthatwillbe<statewhois

Task

usedtoidentifyriskfactorsatinvolvedin

thebeginningoftheprojectandonidentifying

anon-goingbasis.Thismayinvolveprojectrisks>

aformalriskassessmentworkshop,

abrainstormingsession,interviews

atthebeginningofeachlifecycle

phase,oruseofananonymousform

availablefromtheproject’sweb

siteforsubmittingriskfactors.

Describeanyconsolidatedlistsof

riskitemsthatwillbeusedto

identifycandidaterisksforthis

project.>

Task

Participants

RiskAnalysis

and

Prioritizatio

n

TheRiskOfficerwillassigneachAssigned

riskfactortoanindividualProjectMember

projectmember,whowillestimate

theprobabilitytheriskcould

becomeaproblem(scaleofandthe

impactifitdoes(eitherrelative

scaleof1-10,orunitsofdollars

orscheduledays,asindicatedby

theRiskOfficer).

RiskOfficer

Theindividualanalyzedrisk

factorsarecollected,reviewed,

andadjustedifnecessary.Thelist

ofriskfactorsissortedby

descendingriskexposure

(probabilitytimesimpact).

<Iftheprojectplanningactivities

willincorporatescheduleorbudget

contingenciesbasedonrisk

analysis,describetheprocessof

estimatingsuchcontingenciesand

communicatingtheinformationto

theProjectManagerorbuilding

thosecontingenciesintothe

projectschedulehere.>

Risk

TaskParticipants

Management

Planning

Thetoptenrisks,orthoseriskRiskOfficer

factorshavinganestimated

exposuregreaterthan<state

exposurethreshold>areassignedto

individualprojectmembersfor

developmentandexecutionofarisk

mitigationplan.<Or,agroup

brainstormingsessionisusedto

definemitigationplansfor

individualriskitemsandtoassign

responsibilitytoindividuals.>

Foreachassignedriskfactor,Project

recommendactionsthatwillreduceMembers

eithertheprobabilityoftherisk

materializingintoaproblem,or

theseverityoftheexposureifit

does.Returnthemitigationplanto

theRiskOfficer.

ThemitigationplansforassignedRiskOfficer

riskitemsarecollatedintoa

Risk

Resolution

Risk

Monitoring

singlelist.ThecompletedTopTen

RiskListiscreatedandmade

publiclyavailableonthe

project’sintranetwebsite.

Participants

Task

EachindividualwhoisresponsibleAssigned

forexecutingariskmitigationIndividual

plancarriesoutthemitigation

activities.

TaskParticipants

<DescribethemethodsandmetricsRiskOfficer

fortrackingtheproject’srisk

statusovertime,andthewayrisk

statuswillbereportedto

management.>

Thestatusandeffectivenessof

Assigned

eachmitigationactionisreported

totheRiskOfficereverytwo

Individual

weeks.

Theprobabilityandimpactforeach

riskitemisreevaluatedand

RiskOfficer

modifiedifappropriate.

Ifanynewriskitemshavebeen

RiskOfficer

identified,theyareanalyzedas

weretheitemsontheoriginalrisk

listandaddedtotherisklist.

TheTopTenRiskListis

RiskOfficer

regeneratedbasedontheupdated

probabilityandimpactforeach

remainingrisk.

Anyriskfactorsforwhich

mitigationactionsarenotbeing

RiskOfficer

effectivelycarriedout,orwhose

riskexposureisrising,maybe

escalatedtoanappropriatelevel

ofmanagementforvisibilityand

action.

Lessons

TaskParticipants

Learned

<IftheprojectwillbestoringRiskOfficer

lessonslearnedaboutmitigationof

specificrisksinadatabase,

describethatdatabaseandprocess

hereandindicatethetimingof

enteringrisk-relatedlessonsinto

thedatabase.>

ScheduleforRiskManagementActivities

Risk

Identificatio

n

RiskList

Risk

Management

Plan

RiskReview

RiskTracking

Ariskworkshopwillbeheldonapproximately

<date>.

Theprioritizedrisklistwillbecompletedandmadeavailabletotheprojectteambyapproximately<date>.

Theriskmanagementplan,withmitigation,

avoidance,orpreventionstrategiesforthetoptenriskitems,willbecompletedbyapproximately<date>.

TheRiskManagementPlanandinitialTopTenRisk

ListwillbereviewedandapprovedbytheProject

Manageronapproximately<date>.

Thestatusofriskmanagementactivitiesand

mitigationsuccesswillberevisitedaspartofthegateexitcriteriaforeachlifecyclephase.Theriskmanagementplanwillbeupdatedatthattime.<Iftheprojectistrackingcumulativeriskexposure,thatwillbeupdatedandreviewedduringatthistime,also.>

RiskManagementBudget

<Describethebudgetavailableformanagingtheproject’srisks>.

RiskManagementTools

<Describeanytoolsthatwillbeusedtostorerisk

information,evaluaterisks,trackstatusofriskitems,orgeneratereportsorchartsdepictingrisk

managementactivityandstatus.Ifspecificquestionnairesordatabaseswillbeusedduringriskidentification,describethemhere.Iflessonslearnedaboutcontrollingtheriskitemswillbestoredinadatabaseforreferencebyfutureprojects,describethatdatabasehere.>

Appendix.SampleRiskDocumentationForm

RiskID:<sequence

number>

Classification:

<riskcategory,.,

fromSEItaxonomy>

ReportDate:<date

thisriskreportwas

lastupdated>

Description:<Describeeachriskintheform“condition–

consequence”.>

Probability:

<What’sthe

likelihoodofthis

Impact:<What’sthe

damageiftherisk

doesbecomea

RiskExposure:

<MultiplyProbability

timesLossto

riskbecomingaproblem

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论