版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、Chapter 13: Material Requirements PlanningApplication 1: Calculating an MRP RecordItem H10-A is a produced item (not purchased) with an order quantity of 80 units. Complete the rest of its MRP record using the fixed order quantity (FOQ) rule.Item: H10-A Lot Size: FOQ=80 unitsDescription: Chair seat
2、assembly Lead Time: 4 weeksWeek31323334353637383940Gross requirements60354560Scheduled receipts8020Projected on-hand inventory 2010040404040554040Planned receipts008080Planned order releases8080.Material Requirements PlanningApplication 3: MRP Record using the lot-for-lot (L4L) RuleRevise the H10-A
3、record using the lot-for-lot (L4L) Rule.Item: H10-A Lot Size: L4LDescription: Chair seat assembly Lead Time: 4 weeksWeek31323334353637383940Gross requirements60354560Scheduled receipts8020Projected on-hand inventory 20100404040405500Planned receipts004060Planned order releases4060Material Requiremen
4、ts Planning Application 4: Material Requirements Plan for Single Product Case.A firm makes a product (Item A) from three components (Items B, C, and D). The latest MPS for product A calls for completion of a 250-unit order in week 8, and its lead time is 2 weeks. The master schedule and bill of mate
5、rial for Product A are given below.Item: End Item A Lead Time: 2 wks.Week12345678MPS Quantity250MPS Start250a.Develop a material requirements plan for items B, C, and D, given the following inventory data. Blank MRP records are also provided. ITEMData CategoryBCDLot-sizing ruleL4LFOQ=1000L4LLead tim
6、e2 weeks1 week3 weeksScheduled receiptsNone1000(week 1)NoneBeginning inventory02000Application SupplementItem: End Item A Lead Time: 2 wks.Week12345678MPS Quantity250MPS Start250Item: BLot size: L4LLead Time: 2Week12345678Gross Requirements 500250Scheduled Receipts 00Projected On-hand Inven. 00Net R
7、equirements500250Planned Order Receipts500250Planned Order Releases500250Item: CLot size: FOQ = 1000Lead Time: 1Week12345678Gross Requirements1000 500250Scheduled Receipts100000Proj. On-hand Inv. 2001200200200200700700450450Net Requirements03000Planned Order Receipts01000Planned Order Releases1000 I
8、tem: DLot size: L4LLead Time: 3Week12345678Gross Requirements 500 Scheduled Receipts 0Proj. On-hand Inven. 0 Net Requirements500Planned Order Receipts 500 Planned Order Releases 500 Explanation of the Above TableYour Question: What determines the order time in B and C of the forks that are not on we
9、ek 6? How come, for example, in B you are ordering 500 in week 3 for the right fork when it only needs 250? and in C when 1000 is ordered in week one for the right fork when it only needs 500?Answer: You must follow the decisions down the BOM for each fork. They are color coded, as above. Basically,
10、 you end up multiplying requirements for the level above, by the number required at the next level. As a result, your requirements keep growing with each level down the BOM that you go. BLUE = decisions about materials required for the leftmost fork of the bill of materialsPURPLE = decisions about m
11、aterials required for middle forkGREEN = decisions about materials required for right forkHere is a step-by-step explanation of the color-coded table:RIGHT FORKWell start with the right fork first (GREEN NUMBERS). Luckily, no other fork requires any Ds, so we only have one thing to do, and then were
12、 done with the table for D. Assembling one A requires us to have 2 Ds available in week 6, so for 250 As, well need to make sure we have 500 Ds available in week 6. Because we have zero scheduled receipts of D and zero projected on hand inventory for D, we have a net requirement of 500 Ds. We are or
13、dering Lot-for-Lot, meaning that we want to have 500 Ds arrive in our factory at the beginning of Week 6. In order to have this, well have to place an order for materials (500 Ds) at the beginning of Week 3 (3 weeks earlier, due to the 3 week Lead Time).Next, building each D requires one B. Thus for
14、 500 Ds to be started in week 3, we need to make sure that 500 Bs are available in Week 3. So, you must go up to the table for B, and input a Gross Requirements for B during week 3 of 500 units. Since were not expecting any receipts and have no inventory, this leads to a Net Requirement of 500 Bs, a
15、nd again were using Lot-for-Lot, so we need 500 to arrive during week 3, and thus need to place an order for 500 during week 1.Finally, building a B requires 2 Cs to be available. Since well need 500 Bs in Week 1, wee need to have 1000 Cs available. Luckily, we have a scheduled receipt of 1000 Cs in
16、 week one plus 200 Cs in inventory on-hand, so we are covered, and do not need to place any additional orders for this fork.LEFT FORKNext, the left fork (BLUE NUMBERS). Assembling one A requires us to have one B available in week 6 (meaning, for 250 As well need to have 250 Bs available at the start
17、 of week 6). So, our Gross Requirements for B during Week 6 is 250. Since were not receiving any and not holding any in inventory, well place an order in Week 4 for 250 Bs, due to the 2 week Lead Time.Moving down the left fork, we need 2 Cs to assemble each B, so our gross requirement of Cs will be
18、250 * 2 = 500 Cs during Week 4. During Week 4, we will have 200 Cs projected to be onhand inventory, so we will only have a Net Requirement of 300 Cs. Since we are ordering fixed order quantities of 1000, we will plan to receive an order of 1000 Cs during Week 4, and due to the one week Lead Time, w
19、ell place the order for 1000 Cs during Week 3.MIDDLE FORKFinally, the middle, and easiest/shortest, fork (PURPLE NUMBERS). For each A, we need one C. Thus, for 250 As during Week 6, well need to have 250 Cs available. So, our gross requirement will be 250 Cs in Week 6. We will have 700 Cs in on-hand inventory left over from our order that we receive in w
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 华师大版初中科学第5章《1 食物的消化和吸收》课件1
- 华师大版初中科学3、水是常用的溶剂16课件
- 医院陪护制度
- 医疗仪器设备备品备件管理制度
- 第四单元课题1 爱护水资源 九年级化学人教版2024上册
- 7《鹿角和鹿腿》核心素养分层学习任务单-2022-2023学年三年级语文下册新课标(部编版)
- 【寒假阅读提升】四年级下册语文试题-现代文阅读(四)-人教部编版(含答案解析)
- 心源性脑栓塞及小动脉闭塞性脑梗死
- 2024年惠州申请客运从业资格证2024年试题
- 2024年资阳客运从业资格证考试模拟试题
- 2024-2025学年九年级上学期期中考试英语试题
- 2024-2030年手机游戏行业市场深度分析及前景趋势与投资研究报告
- GB/T 20279-2024网络安全技术网络和终端隔离产品技术规范
- 安全工程导论课件:事故致因理论
- 山东省青岛实验中学2024-2025学年七年级上学期期中考试数学试题(无答案)
- 2024年安能物流合作加盟协议版
- 2024年湖南烟草专卖局招249人考试高频难、易错点500题模拟试题附带答案详解
- 生活饮用水、公共场所卫生管理系列国家强制性标准解读答案-2024年全国疾控系统“大学习”活动
- 质量管理体系过程方法和风险思维专业解读与应用之7:5 领导作用-5.3组织的岗位、职责和权限(雷泽佳编制-2024B1)
- 第二次月考卷-2024-2025学年统编版语文六年级上册
- 车辆采购服务投标方案(技术方案)
评论
0/150
提交评论