TABLEOFCONTENTS
TOC\o
1. INTRODUCTION.
1
1.1. DefinitionsAndInterpretations.
1
1.2. Distribution.
1
1.3. ProjectPhilosophy.
1
1.4. BriefDescriptionofProjectScope.
2
2. CONTRACTOR’SORGANIZATION.
5
2.1. Contractor’sOverallOrganizationChart.
5
2.2. ProjectTeamOrganizationChart.
5
2.3. EngineeringPlan.
5
2.4. Attachments.
5
3. DETAILEDWORKSCHEDULE.
6
3.1. Attachments.
6
4. CORRESPONDENCEPROCEDURE.
7
4.1. CorrespondenceNumbering.
7
4.1.1. CompanytoContractor
7
4.1.2. ContractortoCompany.
7
4.1.3. ContractortoSupervisingCompanyor“Jianli”.
7
4.2. ContactAddresses&Numbers.
8
4.2.1. Owner’sAddress&ContactNo.
8
4.2.2. OffshoreContractor’sAddress&ContactNo.
8
4.2.3. OnshoreContractor’sAddress&ContactNo.
8
4.2.4. Contractor’sTentativeContactParticular:
9
4.2.5. SupervisingCompanyAddress&ContactNo.
9
5. PROJECTDOCUMENTCONTROLPROCEDURE.
10
5.1. EngineeringDocuments.
10
5.1.1. OutgoingDocuments.
10
5.1.2. IncomingVendor’sDocuments.
10
5.1.3. ReturnOfVendor’sDocuments.
10
5.2. OtherDocuments.
10
5.3. Filing.
10
5.4. ControlofRevisedDocuments.
11
6. DescriptionofOrganizationChartandKeyPersonnel.
12
6.1. ProjectOrganization.
12
6.1.1. PrinciplesofProjectManagementAndExecution.
12
6.2. Implementation.
12
6.3. ProjectCommittee.
12
6.4. ProjectManager.
13
6.5SiteManager.
14
6.6 ConstructionManager.
14
6.7 ConstructionAdvisor
15
6.8 SHEManager.
16
6.8 OtherKeyPersonnel.
16
6.8.1OffshoreOffice.
16
a) EngineeringManager.
16
b) LogisticsManager.
17
c) ProjectEngineer
17
6.8.2 OnshoreOffice.
17
a) AdministrationManager.
17
b) ProcurementandContractsManager.
17
c) QA/QCManager.
18
6.9 OfficeLocations.
18
6.9.1 OffshoreOffice.
18
6.9.2 OnshoreOffice.
19
7 ENGINEERINGPLAN.
20
7.1. General.
20
7.1.1. EngineeringPlan.
20
7.1.2. DisciplineandInterdisciplinaryCheck.
21
7.1.3. TechnicalEvaluationandVendorDocumentsReview.
21
7.1.4. SeamlessTeamCommunication.
21
7.2. BasicEngineering.
21
7.3. DetailedEngineering.
22
7.4. ComputerAidedEngineering.
22
7.5. HAZOPStudy.
22
8. DRAWING&DOCUMENTAPPROVALPROCEDURE.
23
8.1. General.
23
8.2. ApprovalItems.
23
8.3. LocalAuthoritiesApproval.
23
8.4. TimeforApproval.
23
8.5 DocumentFlowControl.
23
8.6 Vendor/SupplierDocument.
23
8.7 Definition.
23
8.7.1 ForApproval.
24
8.7.2 ForInformation.
24
8.7.3 ApprovedForConstruction/Final.
24
8.7.4 Owner’sComment
24
8.8 Indication.
25
8.9 Attachments
26
9 PROCUREMENTPROCEDURE.
31
9.1 SpecificPlansForProcurement.
31
9.2 ProcurementProcedure.
31
9.2.1 PreparationOfVendorList.
31
9.2.2 VendorPre-Qualification.
31
9.2.3 RequestForQuotation.
32
9.2.4 BidAnalysis.
32
9.2.5 PlacingOrders.
32
9.2.6 SpareParts.
32
9.2.7 ProcurementProcessFlow.
33
9.3 ATTACHMENTS
33
10 EXPEDITINGPROCEDURE
34
10.1 ResponsibilityAndDuties.
34
10.2 PrincipleOfExpediting.
34
10.3 Inspection.
35
10.4 Report.
35
10.4.1 ShopVisitReport.
35
10.4.2 Expediting/ShippingStatusReport.
35
10.4.3 ProgressTracking.
35
10.5 ImportandCustomsClearance.
36
10.6 Attachments.
36
11 CONSTRUCTIONWORKPLAN.
40
11.1 WorkPlanOfFieldConstruction.
40
11.1.1 Principles.
40
11.1.1.1 SafePerformanceOfWork.
40
11.1.1.2 CloseCommunicationwithOwner.
40
11.1.2 Subcontracting.
40
11.1.2.1 SelectionofSub-contractors.
40
11.1.2.2 ControlofSub-contractors.
41
11.1.2.3 RecordEvaluation.
41
11.1.3 TemporaryFacilities.
41
11.1.4 ConstructionUtilities.
41
11.2 SHEPlan.
41
11.2.1 General.
41
11.2.2 SHEPolicy.
41
11.2.3 SHEObjective.
42
11.2.4 SHETarget
42
11.2.5 MajorItemsofSHESystem.
42
11.3 Materials.
44
11.3.1 MaterialsPurchased.
44
11.3.2 MaterialsSchedule.
44
11.4 Mobilization.
44
11.4.1 MajorConstructionEquipmentMobilization.
44
11.4.2 ProjectPersonnelPlan.
44
11.4.3 TemporaryFacilityPlan.
44
11.5 Attachments.
44
12 QA/QCPLAN.
45
12.1 QualityObjective.
45
12.2 QualityPolicy.
45
12.3 InspectionandTestingPlan.
45
12.4 GeneralInspectionProcedure
45
13 PROGRESSREPORTINGPROCEDURE.
46
13.1 General.
46
13.2 ProgressReporting.
46
13.3 ContentsofReport.
46
13.4 ProgressReportForm.
47
13.4.1 ProjectProgressReport(Form01)
47
13.4.2 EngineeringProgressReport(Form02).
47
13.4.3 ProcurementProgressReport(Form03).
47
13.4.4 FieldConstructionProgressReport(Form04).
48
13.5 Attachments.
48
14 SCHEDULECONTROLPROCEDURE.
55
14.1 General.
55
14.2 PlanningSoftware.
55
14.3 ControlMethod.
55
14.3.1 StepsOfControl.
55
14.3.2 OverallControl.
55
14.3.3 PlanningandControlFlow.
56
14.4 ProgressReporting.
56
14.5 WeeklySchedule.
56
14.6 Attachments.
56
15 CHANGEINWORKPROCEDURE.
57
15.1 General.
57
15.2 Change.
57
15.3 ChangeProposalFormat.
57
16 TURN-OVERPROCEDURE.
62
16.1 General.
62
16.2 IndividualTurn-Over.
62
16.3 Definitions.
62
16.3.1 Turn-Over.
62
16.3.2 MechanicalCompletion.
62
16.3.3 Unit.
62
16.4 WorkLists.
62
16.4.1 DetailedListOfOutstandingWork.
62
16.4.2 PunchList.
63
16.5 Notices.
63
16.5.1 MechanicalCompletion.
63
16.5.1.1 Contractor’sNotice.
63
16.5.1.2 Owner’sComments.
63
16.5.1.3 RepairWork.
63
16.5.2 CertificateOfMechanicalCompletion.
64
16.6 PreparationForOperation.
64
16.7 CommissioningAndOperationalTest.
64
16.8 FlowOfTurnoverProcedure.
64
16.9 Attachments.
65
INTRODUCTION.
ThisProjectExecutionPlanprescribestheschemetheContractorproposestoemployforexecutingtheWork.Namely,itoutlinestheorganization,andtheprinciples,location,andmannerofperformingtheWorkandgivingdetailedprocedures.
DefinitionsAndInterpretations.
InthisProjectExecutionPlanthefollowingwordsandphrasesshallhavethemeaningsasfollows
“Company”shallbeinterpretedasVopakShanghaiLogisticsCo.,Ltd.
“Owner”,wherevermentionedshallhavethesameinterpretationas“Company”andviceversa.
“Contractor”shallbeinterpretedasRotaryEngineeringLimitedandChinaInternationalWater&ElectricCorp.(S)PteLtdConsortium.
“RCC”,wherevermentionedshallhavethesameinterpretationas“Contractor”andviceversa.
“SupervisingCompanyor“Jianli”shallbeinterpretedasAudexPteLtd/ShanghaiCoking&ChemicalProjectConstructionSupervisionCo.Ltd.
“LDI”shallbeinterpretedasZhejiangTITANDesign&EngineeringCo.,Ltd.
Distribution.
ThisProjectExecutionPlanshallbedistributedtothekeypersonnelintheProjectasfollows:
Company’sProjectManager/DeputyProjectManager/SHEManager(2EnglishCopyand2ChineseCopy)
Contractor’sProjectManagerandSiteManager
Contractor’sConstructionManager
SupervisingCommittee’sChiefSupervisorandDeputyChiefSupervisor(1EnglishCopyand1ChineseCopy)
Others(SiteManagerwilldecidethedistributionrequirements)
ProjectPhilosophy.
SafetyFirst
Emphasisonqualityofdesignsmaterialsandworkmanship
Successfulon-scheduleexecutionandperformance
Controlofconstructionandoperationcosts
Easeofoperationandmaintenanceoftheplant
BriefDescriptionofProjectScope.
VopakShanghaiLogisticsCo.,LtdintendstorealizeaproductlogisticsterminalatShanghaiCaojingChemicalPark.
Theterminalwillbecompletedwithtanker,coasterbargeberthingandloadingfacilitiesandwillbeusedforstorageanddistributionofliquidchemicalproductsforthelocaland exportmarket.Eachproductwillhavetheoptionsofbeingtransportedinandouteitherbyship,coasterbarge,truck,railcarordrums.
Theterminalwillbebuiltinphasesoveraperiodtobedecidedbymarketdevelopment.Thisdescriptiononlycoversthefacilitiesasrequiredfortheinitialphase.Theterminallayoutsaswellasthelocationforberthingplacesarearrangedinsuchawaythatsmalladaptationscanbemadetosatisfyalternativerequirementsandfutureextensionscanberealizedoptimallyatminimumcost.
Theoffshorefacilitiesareforreceivingproductsfromoceanvesselsandarealsofordischargingproducttosmallervesselsandbargesfordistribution.Theoffshorefacilitiesshallconsistoftwojettieswhichcanbertha5,000DWTto25,000DWTvessels,twojettieswhichcanbertha1,000DWTto12,000DWTvesselandtwojettieswhichcanbertha1,000DWTto5,000DWTvesselsberthingsimultaneously.
Theonshorefacilitiesconsistofproductstoragefacilities,chemicalspumpingfacilities,drummingandwarehousingfacilities,truckandrailloadingfacilitiesfordedicatedclients.
Theutilityfacilitiesshallconsistofpotablewatersystem,plantairsystem,instrumentairsystem,nitrogensystem,firefightingsystem,wastewatertreatmentandslopsystem,andoffgastreatmentsystemforhazardouschemicalsshallbeprovidedfortheonshoreandoffshorefacilities.Airconditioningandventilationshallbeprovidedforthebuildings.Refrigerationsystemshallbeprovidedforrefrigeratedwarehousesandcontrolledtemperaturewarehouse.
Theterminalshallhaveamainofficebuildingattachedwiththecentralcontrolroom,aworkshop,afoamtruckbuilding,anintegrateddrummingandwarehousebuilding,truckloadingsheds,aircompressorshed,mainsubstationandguardhouse.
VopakShanghaiLogisticsCoLtd.(hereinaftercalledEmployer)shallbethemanagingcompanyandprovidetheknow-howandtechnologyfortheoperationoftheterminal.
Thescopeofworkshallincludeengagingalocaldesigninstituteforallgovernmentauthorityapprovalandliaisonwithgovernmentauthority,detailedengineering,procurementofallequipmentandmaterialandfieldinstallationanderectionaspercontractdocumentrequirement.
Thefollowingaregeneraldescriptionsoftheworkelements.Theseworkelementsdescriptionisjustaguidelineandthedetailedscopeofworksshallbeaspercontractrequirement:
a.Projectmanagement
-- LiaisonwithEmployer
-- Projectcontrolandreporting
-- Schedulecontrolforengineering,procurementandconstruction
b.Engagedesigninstitute
-- EndorsementofalldrawingforsubmissiontoGovernmentAuthority
-- LiaisonwithallGovernmentAuthority
c.Detailedengineering
-- PreparationofP&IDiagram,plotplan,areaclassificationdrawingandsinglelinediagram.
-- Preparealldesigncalculationsforallfunctionalengineeringofonshorefacilities
-- Preparealldesigncalculationsforstructure(i.e.operatingplatform,piperack,pipesupport),mechanicalequipment,piping,electricalandinstrumentationengineeringofoffshorefacilities
-- Prepareallconstructiondrawingsforallfunctionalengineeringofonshorefacilities
-- Prepareallconstructiondrawingsforstructure(i.e.operatingplatform,piperack,pipesupport),embeddedsteel,mechanicalequipment,piping,electricalandinstrumentationengineeringofoffshorefacilities.
-- Preparematerialspecificationandrequisitionofallmaterials,equipmentandotheritemstobesuppliedforonshoreandoffshorefacilities
-- Reviewandapproveofvendors'documents.
-- Prepareasbuiltdrawingsanddocument
-- Preparemechanicalcatalogandoperationmanual
-- Co-ordinationwithmarinestructuredesigninstitute
d.Procurement
-- Procurementofallfunctionalengineeringbulkmaterial
-- Procurementofallequipment
-- Recommendedsparepartsforoneyearoperation
-- Packing
-- Shippingandtransportation
-- Portclearanceandhandlingcharge
-- Loadingandunloading
e.Construction
-- Alltemporaryfacilitiessuchassiteoffice,utilities,storagefacilities,laborcamp,accessroad,drainageandfencing
-- Sitesecurityservices
-- Constructionmanagement
-- Constructionlabor
-- Constructionequipment
-- Temporarymaterials
-- Consumables
-- Handtools
-- Safetyequipmentandpersonalprotectivewear
-- Landandmarinetransportation
-- Pre-commissioning
-- Constructionspares
CONTRACTOR’SORGANIZATION.
UnderContractor’spermanentorganization,theContractorshallorganizetheProjectTeam,whichwillco-ordinatebetweentheOwner,SupervisingCompanyandtheContractor’spermanentorganization.
Contractor’sOverallOrganizationChart.
OverallOrganizationChartofRotaryEngineeringLimitedisattachedasAttachment2.1.
OverallOrganizationChartofChinaInternationalWater&ElectricCorp.(S)PteLtdisattachedasAttachment2.2.
ProjectTeamOrganizationChart.
InordertoexecutetheWorkeffectivelyandsmoothly,theContractorwillorganizetheProjectTeamshownintheProjectTeamOrganizationChartattachedasAttachment2.3.
TheProjectTeamshallbeamatrixorganization.
EngineeringPlan.
DedicatedEngineeringTeamstoexecutebasicanddetailedengineeringactivities:
BasicdesignandengineeringinRELSingaporeOffice.
DetaildesignandengineeringwillbecarriedoutatLocalDesignInstitute(LDI)inHangzhou,China.
AlldetaildrawingswillbeendorsedbythelocalauthorityorqualifiedAccreditChecker.
Attachments.
Attachment2.1
OverallOrganizationChartofRotaryEngineeringLimited(REL)
Attachment2.2
OverallOrganizationChartofChinaInternationalWater&ElectricCorp.(S)PteLtd(CIWE)
Attachment2.3
ConsortiumProjectTeamOrganizationChart
DETAILEDWORKSCHEDULE.
TheProjectScheduleemployingGanttcharttechniqueisshownonAttachment3.1
Attachments.
Attachment3.1
PreliminaryMasterSchedule
CORRESPONDENCEPROCEDURE.
AllcorrespondenceinexecutionofWorksundertheProjectshallbebetweenCompany’sProjectManagerorhisRepresentative(ifCompany’sProjectManagerdirectsso)andContractor’sProjectManager.TheContractorProjectManagerorhisRepresentativeshallalsocorrespondwithSupervisingCompany(SC)orJianli’sRepresentative.
DocumentsinvolvingdesigndrawingshallbesubmittedtoOwnerandcctoSCwhileanydocumentsdealingwithconstructionshallbesubmittedtoSCandcctoOwner.
CorrespondenceNumbering.
Correspondencenumberingshallbeasfollows:
CompanytoContractor
ContractNo. :
Corresp.No. :
Attention :Mr.KhinMM
ContractortoCompany.
ProjectNo. :
Corresp.No. :RCC/CL-xxx/301P0688/FC
Attention :Mr.LeeHoiChuen
WhereRCCstandsforREL/CIWEConsortium
e.g.
L
=
Letter
F
=
Facsimile
T
=
DocumentTransmittal
MM
=
Memorandum
MOM
MinutesofMeeting
xxx
=
SerialNumber
FC
=
FilingCode
ContractortoSupervisingCompanyor“Jianli”.
ProjectNo. :
Corresp.No. :RCC/SL-xxx/301P0688/FC
Attention :Mr.SongYangGeun
WhereRCCstandsforREL/CIWEConsortium
e.g.
L
=
Letter
F
=
Facsimile
T
=
DocumentTransmittal
MM
=
Memorandum
MOM
=
MinutesofMeeting
xxx
=
SerialNumber
FC
=
FilingCode
ContactAddresses&Numbers.
Owner’sAddress&ContactNo.
TownOffice
VopakShanghaiLogisticsCo.,Ltd
Room7004,NovelBuilding
887,HuaihaiZhongLu
Shanghai20
P.R.China
Tel: (86)2164315002
Fax: (86)2164747409
SiteOffice
ShanghaiChemicalIndustrialParkC1-2-1
FengxianDistrict,Shanghai07,
P.R.China
Tel: (86)21
Fax: (86)21
OffshoreContractor’sAddress&ContactNo.
RotaryEngineeringLimited
No.17,TuasAve20.
Singapore638828
Tel: (65)68611155
Fax: (65)68623306
OnshoreContractor’sAddress&ContactNo.
ChinaInternationalWater&ElectricCorporation(s)PteLtd
80,MarineParadeRoad,
09-09ParkwayParade
Singapore449269
Tel:(65)64405186
Fax:(65)64407959
Contractor’sTentativeContactParticular:
Mr.KhinM.M
ProjectManagerofCaojingProject
Unit2802B,No800DongfangRoadBaoAnBuilding
PudongShanghai,P.R.China22
Tel:(86)58204466CellPhone:
Fax:(86)68752850
TheabovecontactnumberandaddressaresubjecttochangeswhenthesiteofficeisreadybymidOct.
SupervisingCompanyAddress&ContactNo.
AudexPteLtd/ShanghaiCoking&ChemicalProjectConstructionSupervisionCo.Ltd.
No.4319LongWuRoad
Shanghai41,PRC
Tel: (86)02164345011
Fax: (86)02164340535
PROJECTDOCUMENTCONTROLPROCEDURE.
Allincomingandoutgoingprojectdocumentsshallbecontrolledanddistributedaccordingtothisprocedure.
EngineeringDocuments.
OutgoingDocuments.
AllengineeringdocumentsgeneratedbyLDIshallbeissuedtoCompanyforreviewandapprovalbytheRCC.nagementTeam(PMT).AcopyofthedocumenttransmittalwithouttheattachmentsshallbedistributedtoContractor’sEngineeringDepartmentforinformation.
IncomingVendor’sDocuments.
OffshorePurchaseItems:
IncomingVendor’stechnicalandengineeringdocumentsforapprovalshallbereceivedbyContractor’sProcurementDepartment.ProjectEngineerorbuyerwillrecordtheVendor’sincomingdocumentsanddistributeonecopytoSeniorPM/PMandonecopytotheleadengineeronsite.Afterreviewbythedisciplineengineer,acopyofthecommenteddocumentsshallbehandedtoSeniorPM/PMwhowillreviewandinputfurthercommentsifnecessary.TwocopiesofthecommenteddocumentsshallbesubmittedtoCompanyforreview/approval.
OnshorePurchaseItems:
(Theaboveprocedurealsoappliesinprincipletotheonshorepurchaseitems).
ReturnOfVendor’sDocuments.
Vendor’sdocumentsreturnedfromCompanywithorwithoutcommentsshallbenotedandsentbacktotheRespectiveVendorsforre-submissionorincorporationwithin14calendardaysafterreceivingofthedocumentsasperITBrequirements.
OtherDocuments.
IncomingdocumentsfromCompany,Vendors,Subcontractorsetc.otherthanabovementionedshallbereceivedbyContractor’sSeniorPM/PMandcopiesdistributedtoContractor’srelevantDepartment’sconcernedforactionorforinformation.
Filing.
AlldocumentsrelatedtotheProjectshallbefiledaccordingtotheattachedProjectFileNumberingDocNo.:PRO-FIL-001.
Attachment5.1:PRO-FIL-001ProjectFileNumbering.
ControlofRevisedDocuments.
Anydocumentsordrawingsthathadbeenrevisedandreissuedasapprovedrevisionshallsupersedethepreviousdocuments.Anysupersededdocumentsshallbeappropriatelyidentifiedandberemovedfromprojectfile.Acopyofsupersededdocumentshallbekeptseparatelyforreferenceorforcontractualpurposes.However,theseshallbeclearlyidentifiedandseparatedfromlatestreviseddocument.
Alldocuments/drawingsusedatsiteshallbeapprovedforconstruction.
DescriptionofOrganizationChartandKeyPersonnel.
ProjectOrganization.
InordertoexecutetheWorkeffectivelyandsmoothlyfromtheviewpointofqualityandschedule,theContractorwillorganizetheProjectTeamshownintheProjectTeamOrganizationChartattachedasAttachment2.3
TheProjectTeamshallbeamatrixorganization.
PrinciplesofProjectManagementAndExecution.
ThefollowingprincipleswillapplytoeachphaseofProcurementandConstructionfortheWork.
Emphasisonqualityofdesignmaterialsandworkmanship.
Onscheduleperformance.
MinimumconstructionandoperationcostsfortheTerminal.
EaseofoperationandmaintenanceoftheTerminal.
Implementation.
Inordertoimplementtheaboveprinciples,theContractorplanstoexecutetheWorkby:
OrganizingaProjectTeamforthesolepurposeofexecutingtheWork.Asufficientnumberoffullyqualifiedpersonnel,especiallythosewithexperienceinterminalprojects,shallbeassigned.
AbsorbingandfullyunderstandingthespecificationsandrequirementsoftheOwnerandtakingadvantageoftheContractor’sfamiliaritywiththecodesandstandardstobeappliedtothisProject.
Makingeffectiveuseoftheinformationtechnologyformaintainingthescheduleandqualityofwork.
ProjectCommittee.
Projectcommitteeistheimplementation’schampions.TheirsupportsareessentialtothesuccessfortheWorks.Membersmeetregularly(monthlyforfirstthreemonth)todiscussimportantissues,reviewprogress,providesolutionsandmakekeydecisions.
ThecommitteemembersarecomposedprimarilyoftopmanagementoftheConsortium.
ProjectManager.
ProjectManagershallbeassignedfromamongstaffpersonnelwithabundantexperienceinmanagementofProject.Heshall:
ProjectManagerwillbeauthorizedandresponsibleforalltheprojectactivitiesagainsttherequirementsoftheEmployerwiththeassistanceandsupportoftheprojectstaffsconsistingofProjectCoordinator,ProjectEngineer,PlanningEngineerandProcurement/Engineering/ConstructionTeam..
ResponsibleandauthorizetodecideallfundamentalmanagementmattersoftheprojectandensurethatProjectExecutionProcedureisdocumented,understoodandimplementedbyallemployees.
CoordinationwithEmployerandEmployer’srepresentativeSupervisingCompany.
OverallProjectBudgeting.
OverallControlandManagementofEngineering,ProcurementandConstructionSchedule.
Engineering.
Planning/SchedulinginengineeringmattersincludingDocumentRegister.
Basic/DetailedDesignandEngineering.
Preparationofrequisitionofequipmentwithpriorityoncriticallongleaddelivery.
TechnicalBidEvaluationofequipmentwithpriorityoncriticallongleaddelivery.
Checkingofdisciplinevendor’sprintsandincorporatingintodesignwithitsresultsfordisciplineworks.
DeliveryofIFA(IssueForApproval),IFC(IssueForConstruction)drawingsanddocuments.
Supervisingoninitialdesignandconversiondesign.
FieldEngineeringSupports.
LocalAuthorityApproval.
As-BuiltDrawings/MechanicalCatalogues.
ManagementandControlofEngineeringSchedule.
g) Procurementservices.
ConfirmationonSpecificationsofEmployer’spreferredVendorsandApproval.
Pre-qualificationofVendorsnotlistedinrecommendedlistbyEmployerandproposeforEmployer’sApproval.
Commercialevaluation,selectionofVendors/Manufacturers.
Releasepurchaseorderofmaterials.
Forwardingandexpeditingofmaterials.
ManagementandControlofProcurementSchedule.
h) Pre-commissioningandCommissioningAssistance.
6.5SiteManager.
SiteManagershallberesponsibleforfollowingactivities:
a) SiteManagerwillbeauthorizedandresponsibleforallconstructionactivitiesagainsttherequirementsoftheEmployerwiththeassistanceandsupportoftheconstructionteam.
b) CoordinationwithEmployer,Employer’srepresentativeSupervisingCompanyandsub-contractors.
c) OverallConstructionScheduleManagementassistedbyPlanningControlEngineers.
PlanningandSchedulingconsistsofConstructionMasterSchedule,ThreeMonthsLook-aheadConstructionSchedule,MonthlyConstructionScheduleandWeeklySchedule.
MonitoringandAnalysis.
StudyofCountermeasuresandReportingwillconfirmtheschedulevarianceincomparisonwiththeoriginaltargetandmaycallsomerequirementsofnecessarycountermeasurestosuccessfullyattaintheoriginalcompletiontargetontime.
ProgressMeasurement.
ControlofSubcontractorPlanningTeams.
Reportingontheconstructionprogress,qualityissueandSHEissuetoProjectManagement,EmployerandSupervisingCompany.
Preparingandcontrollingmanpower,equipmentandmaterialsineachdisciplineinaccordancewithconstructionscheduleandprogress.
ConstructioncostcontrolandBudgeting.
SubcontractSourcingandManagement.
Safety,QA/QC,SHE.
FieldMaterialControl.
ManageSiteConstructionmattersandlocalengineeringactivitiesbysubcontractors.
ManagingLocalProcurement.
CustomsClearanceandonlandtransportationtoSite.
6.6 ConstructionManager.
Immediatelyuponawardofcontract,theConstructionManagerwillbeappointedtotakecontrolofallsiteconstructionactivities.
a)HewillberesponsibletoSiteManager.Refertositeorganizationalchart,histeamconsistsof:(tobeupdatedasrequired)
Civil&StructureTeam
MechanicalTeam
ElectricalTeam
I&CTeam
PaintingandInsulationTeam
ShopFabricationTeam
EachteamisheadedwithaspecialtyteammanagerwhoreportstoConstructionManager.
b)TheConstructionManagerwillworkcloselytocontrolscheduleandqualityofsiteworks.Heshalltakeadjustmentforanydeviationfromkeycompletiondate.
Hewillcoordinatetheworksequenceofeachteammanagerandeachspecialtyengineer.
Hewillbeinchargeintheimplementationofprojectsafetyprocedures.Safetyistheprimaryconcernofhisworks.
HeshallliaisewithQA/QCManagerfordailyconstructioninspections.
HewillbefullyresponsiblefortechnicalcommunicationandcoordinationwiththeProjectManager/SiteManagerandengineer,developingandreviewingthetechnicaldocumentsuchasdrawings,specificationsandprocedures,interpretingandclarifyingallthetechnicaldetailstotheprojectmembers,providingtechnicaldirectionorinstructiontoqualitypersonnelinvolved,proposingandreviewingcorrectiveactions,conductingfieldengineeringsuchastechnicaladaptation.
ConstructionAdvisor
ConstructionAdvisorwillbethechairmanoftheConstructionManagementTeamthatincludestheSiteManager,ConstructionManager,SHEmanagerandQA/QCManager.
a)ConstructionAdvisorshalloverviewtheconstructionstatusandhighlight/adviseonSafety,QualityandDeliveryaspectswhiletheconstructionmanagerandteamwillcarryoutconstructionexecutionundertheguidanceofSiteManager.
b) ConstructionManagerandteamwillcarryoutconstructionexecutionunderguidanceofSiteManager.ConstructionAdvisorwilloverviewtheconstructionstatusandhighlight/adviseonSafety,QualityandDeliveryaspects.
TheconstructionadvisorwillcoordinatewithEmployerandSupervisingCompanyforbetterachievementofoverallproject.
ConstructionAdvisorwillhaveregularmeetingwiththeconstructionteamtoresolveanyissuesthatmighthavecausedhinderingoftheconstructionprogress.
ConstructionAdvisorshallcoverthedutiesofprojectmanagerduringhisabsence.
Heshallalsobeattendingtheweeklymeetingonbehalfoftheprojectmanager,whowillattendonlyifnecessary.
CAshallalsoberesponsibleforcontrolofmaterialusageandwastage(formaterialssuppliedbyREL).
CAshallassistPMinprocurementservices.
SHEManager.
TheSHEManagershallberesponsiblefortheoverallprojectsafety,healthandenvironmentalprotectionobjective.Hewillbeassistedbysafetyengineerand/orsupervisorsandshallberesponsibletoensurethatallsafety,healthandenvironmentalregulationsandproceduresofOwnersarestrictlycompliedwith.TheSHEManagershall
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 青少年安全自护国旗下演讲稿模板5篇
- 海洋环境监测无人艇系统可行性分析报告
- 苹果商品化处理生产线新建项目可行性研究报告
- 铅酸蓄电池技改项目可行性报告
- 如何写一封色差地砖协议书范文
- 秋天真美丽教案中班
- 山西焦煤买卖合同
- 科技园区施工合同争议处理样本
- 项目年度总结5篇范文
- 棒球器材租赁合同模板
- 中考数学复习微专题:有理数运算中的错解及对策
- DB11-972-2013保险营业场所风险等级与安全防范要求
- 高中政治部编版教材高考双向细目表
- 轮扣式模板支撑架安全专项施工方案
- 酒店装饰装修工程验收表
- 中国行业分类代码表
- 社会组织协会换届选举会议主持词
- 呼吸科(呼吸与危重症医学科)出科理论试题及答案
- 清新个人工作述职报告PPT模板
- 公路工程通用(专用)合同条款汇编.
- 工程施工现场及常用对话场景英语集锦
评论
0/150
提交评论