广州市景明装饰施工队PAGE第17页共18页广州市景明装饰施工队广州市荔景华庭“奥特莱斯”商场玻璃、铝板幕墙分项工程施工方案编制人:田景明日期:2012/7/25目录第一部分总则·················································1一、编制依据························································1二、编制原则························································1三、施工总说明······················································1四、工程概况························································1第二部分施工部署及方案···································2一、工期安排························································2二、主要材料说明····················································2三、劳动力计划······················································2四、机械设备投入计划················································2第三部分关键施工技术、工艺及工程项目··················3一、玻璃幕墙施工····················································31、施工准备·························································32、吊挂式全玻璃幕墙安装施工·········································43、上部承重钢构安装·················································54、下部和侧边边框安装···············································55、玻璃安装就位·····················································5二、铝板幕墙施工····················································61、施工顺序························································62、施工方法·························································7四、安全生产及文明施工的措施······························121、安全管理························································122、外脚手架························································123、“三宝、四口”防护··············································134、施工用电························································135、施工机具························································146、安全施工措施····················································14第一部分总则一、编制依据1、国家现行工程建设标准强制性条文、施工及验收规范、规程。《建筑工程施工质量验收统一标准》(GB50300-2001)《建筑装饰装修工程质量验收规范》(GB50210-2001)《建筑幕墙》(JG3035-96)《玻璃幕墙工程技术规范》(JGJ102-96)《钢结构施工及验收规范》(GB50205-2001)2、建设单位提供的设计施工图纸资料、材料参数和有关技术文件。3、本工程相关的法律法规和其它要求。二、编制原则1、坚持质量第一,用户至上的宗旨,全面执行我公司“三标一体”管理方针,严格按照ISO9001:2000质量管理体系、ISO14001:2004环境管理体系和GB/T28001:2001职业健康安全管理规范的要求进行施工管理,切实贯彻执行国家施工及验收规范、操作规程和制度,确保工程质量和职业健康安全,遵循国家及市政府有关环保文件精神,采取有效措施,减少环境污染,降低噪音。2、严格执行基建程序,发挥我公司技术优势,利用先进的施工技术,科学管理,加快施工进度,确保本工程尽早交付业主使用。3、结合施工实际,合理安排施工工序。采用系统工程、网络计划、目标管理等现代化管理方法,统筹安排施工作业,安排机械、材料、劳动力的进退场,加强工程进度的科学性、计划性管理,确保施工进度和现场文明整洁。4、遵循国家有关环保文件精神,采取有效措施,降低施工噪音及粉尘污染,保持正常的生产和生活环境。5、严格遵守国家及广州市政府有关消防要求,做好消防工作。三、施工总说明该工程位于广州市越秀区文昌路荔景华庭,“奥特莱斯”商场为四层钢筋混凝土框架结构,总高度为13m幕墙,总面积约为1000㎡。外立面设计采用凤铝3mm银灰色铝板幕墙、铝合金型材15mm钢化玻璃幕墙饰面做为正面的外墙装饰,幕墙骨架采用镀锌钢材。我公司负责本工程的产品加工、制作、施工安装等服务。四、工程概况工程名称:广州“奥特莱斯”商场工程工程地点:广州市越秀区文昌路荔景华庭承包单位:广州市何铭建设工程有限公司第二部分施工部署及方案工期安排本工程计划工期为天,201年月日开工,201年月日完工。主要材料说明钢型材:采用镀锌钢材龙骨铝板:凤铝3mm银灰色铝板幕墙铝合金型材:铝合金型材壁厚不得小于2.5mm玻璃:15mm钢化清玻璃防锈处理:两丹红一银油幕墙材料包括:构件、组装件、焊条、耐候胶、结构胶、密封胶条、泡沫胶条、五金配件等所有应用于工程上的物资。劳动力计划劳动力组织按不同阶段分别来考虑和安排,为保证工程质量、提高效率及便于核算,作业队伍应保持相对稳定,并隶属于项目经理部统一安排、统筹调度。劳动力计划,见下表。劳动力计划表单位:人四、机械设备投入计划1、主要施工机械配备一览,见下表主要施工机械及工具配备一览机械或设备名称数量机械或设备名称数量挤角机2滑轮吊机4空气压缩机3φ23mm电锤2注胶设备2BX3—500型电焊机2打胶机2φ10电钻5300mm活扳手617×19双头扳手67.5m钢卷尺85.0m钢卷尺22、施工机械的使用及管理(1)开工前由设备科编制详细的设备进场计划,报主管经理批准后,负责组织设备的进场、安装、调试。如果在施工过程当中发生变化,及时反馈到公司,由公司动力部根据需要对设备进行调整,绝不影响工程施工。(2)施工机械管理措施①按ISO9002质量体系《程序文件》之《设备管理程序》的要求,确保施工现场机械设备始终处于受控状态,满足工程进度和质量的要求。所有进场的机械设备在使用前必须经公司动力部审验,合格后领取准用证方可使用,防止不合格(或未检修)设备进入施工现场。②机械保养好坏是其能否正常运转的保障。因此,所有机械设备进场后,应严格按照使用说明及机械设备安拆使用操作规程进行检查、就位、调试,需要做设备基础的,必须严格按要求做好设备基础。操作人员必须经过岗位培训持证上岗。③设备在使用过程中操作人员应按规定进行保养,定期检修,保证其运转良好,并作好记录。④按照设备使用要求作好防雨、防潮、防雷击工作,并应搭设工作棚(罩),悬挂《设备安全技术操作规程》。第三部分关键施工技术、工艺及工程项目一、玻璃幕墙施工玻璃幕墙的安装施工是一项多工种联合施工,不仅工序复杂,操作也要求十分精细。同时它又与其他分项工程的施工进度计划有密切的关系。为了使玻璃幕墙的施工安装顺利进行,必须根据工程实际情况,编制好单项工程施工组织设计,并经总承包单位确认。
玻璃幕墙施工工艺流程图
1、施工准备
(1)技术准备
eq\o\ac(○,1)技术资料收集
现场土建设计资料收集和土建结构尺寸测量。由于土建施工时可能会有一些变动,实际尺寸不一定都与设计图纸符合。全玻璃幕墙对土建结构相关的尺寸要求较高。所以在设计前必须到现场量测,取得第一手资料数据。然后才能根据业主要求绘制切实可行的幕墙分隔图。对于有大门出入口的部位,还必须与制作自动旋转门、全玻门的单位配合,使玻璃幕墙在门上和门边都有可靠的收口。同时也需满足自动旋转门的安装和维修要求。
eq\o\ac(○,2)设计和施工方案确定
设计和施工方案确定。在对玻璃幕墙进行设计分隔时,除要考虑外形的均匀美观外,还应注意尽量减少玻璃的规格型号。由于各类建筑的室外设计都不尽相同,对有室外大雨棚、行车坡道等项目,更应注意协调好总体施工顺序和进度,防止由于其他室外设施的建设,影响吊车行走和玻璃幕墙的安装。在正式施工前,还应对施工范围的场地进行整平填实,做好场地的清理,保证吊车行走畅通。
(2)材料及机具准备
eq\o\ac(○,1)主要材料质量检查
1.1玻璃的尺寸规格是否正确,特别要注意检查玻璃在储存、运输过程中有无受到损伤,发现有裂纹、崩边的玻璃决不能安装,并应立即通知工厂尽快重新加工补充。
1.2金属结构构件的材质是否符合设计要求,构件是否平直,加工尺寸、精度、孔洞位置是否满足设计要求。要刷好第一道防锈漆,所有构件编号要标注明显。
eq\o\ac(○,2)主要施工机具检查
1.1玻璃吊装和运输机具及设备的检查,特别是对吊车的操作系统和电动吸盘的性能检查。
1.2各种电动和手动工具的性能检查。
1.3预埋件的位置与设计位置偏差不应大于
20mm。
eq\o\ac(○,3)搭脚手架
由于施工程序中的不同需要,施工中搭建的脚手架需满足不同的要求。
1.1放线和制作承重钢结构支架时,应搭建在幕墙面玻璃的两侧,方便工人在不同位置进行焊接和安装等作业。
1.2安装玻璃幕墙时,应搭建在幕墙的内侧。要便于玻璃吊装斜向伸入时不碰脚手架,又要使站立在脚手架上下各部位的工人都能很方便地能握住手动吸盘,协助吊车使玻璃准确就位。
1.3玻璃安装就位后注胶和清洗阶段,这时需在室外另行搭建一排脚手架,由于全玻璃幕墙连续面积较大,使室外脚手架无法与主体结构拉接,所以要特别注意脚手架的支撑和稳固,可以用地锚、缆绳和用斜撑的支柱拉接。施工中各操作层高度都要铺放脚手板,顶部要有围栏,脚手板要用铁丝固定。在搭建和拆除脚手架时要格外小心,不能从高处向下抛扔钢管和扣件,防止损坏玻璃。
2、吊挂式全玻璃幕墙安装施工
(1)放线定位
放线是玻璃幕墙安装施工中技术难度较大的一项工作,除了要充分掌握设计要求外,还需具备丰富的工作经验。因为有些细部构造处理在设计图纸中并未十分明确交待,而是留给操作人员结合现场情况具体处理,特别是玻璃面积较大,层数较多的高层建筑玻璃幕墙,其放线难度更大一些。
(2).
测量放线
eq\o\ac(○,1)幕墙定位轴线的测量放线必须与主体结构的主轴线平行或垂直,以免幕墙施工和室内外装饰施工发生矛盾,造成阴阳角不方正和装饰面不平行等缺陷。
eq\o\ac(○,2)要使用高精度的激光水准仪、经纬仪,配合用标准钢卷尺、重锤、水平尺等复核。对高度大于
7m的幕墙,还应反复
2次测量核对,以确保幕墙的垂直精度。要求上、下中心线偏差小于
1~
2mm。
eq\o\ac(○,3)测量放线应在风力不大于
4级的情况下进行,对实际放线与设计图之间的误差应进行调整、分配和消化,不能使其积累。通常以利用适当调节缝隙的宽度和边框的定位来解决。如果发现尺寸误差较大,应及时反映,以便采取重新制做一块玻璃或其他方法合理解决。
(3)
.放线定位
全玻璃幕墙是直接将玻璃与主体结构固定,那么应首先将玻璃的位置弹到地面上,然后再根据外缘尺寸确定锚固点。
3、上部承重钢构安装
(1)注意检查预埋件或锚固钢板的牢固,选用的锚栓质量要可靠,锚栓位置不宜靠近钢筋混凝土构件的边缘,钻孔孔径和深度要符合锚栓厂家的技术规定,孔内灰渣要清吹干净。
(2)每个构件安装位置和高度都应严格按照放线定位和设计图纸要求进行。最主要的是承重钢横梁的中心线必须与幕墙中心线相一致,并且椭圆螺孔中心要与设计的吊杆螺栓位置一致。
(3)内金属扣夹安装必须通顺平直。要用分段拉通线校核,对焊接造成的偏位要进行调直。外金属扣夹要按编号对号入座试拼装,同样要求平直。内外金属扣夹的间距应均匀一致,尺寸符合设计要求。
(4)所有钢结构焊接完毕后,应进行隐蔽工程质量验收,请监理工程师验收签字,验收合格后再涂刷防锈漆。
4、下部和侧边边框安装
要严格按照放线定位和设计标高施工,所有钢结构表面和焊缝刷防锈漆。将下部边框内的灰土清理干净。在每块玻璃的下部都要放置不少于
2块氯丁橡胶垫块,垫块宽度同槽口宽度,长度不应小于
100mm。
5、玻璃安装就位
(1)玻璃吊装
大型玻璃的安装是一项十分细致、精确的整体组织施工。施工前要检查每个工位的人员到位,各种机具工具是否齐全正常,安全措施是否可靠。高空作业的工具和零件要有工具包和可靠放置,防止物件坠落伤人或击破玻璃。待一切检查完毕后方可吊装玻璃。
eq\o\ac(○,1)再一次检查玻璃的质量,尤其要注意玻璃有无裂纹和崩边,吊夹铜片位置是否正确。用干布将玻璃的表面浮灰抹净,用记号笔标注玻璃的中心位置。
eq\o\ac(○,2)安装电动吸盘机。电动吸盘机必须定位,左右对称,且略偏玻璃中心上方,使起吊后的玻璃不会左右偏斜,也不会发生转动。
eq\o\ac(○,3)试起吊。电动吸盘机必须定位,然后应先将玻璃试起吊,将玻璃吊起
2!
3cm,
以检查各个吸盘是否都牢固吸附玻璃。
eq\o\ac(○,4)在玻璃适当位置安装手动吸盘、拉缆绳索和侧边保护胶套。玻璃上的手动吸盘可使在玻璃就位时,在不同高度工作的工人都能用手协助玻璃就位。拉缆绳索是为了玻璃在起吊、旋转、就位时,工人能控制玻璃的摆动,防止玻璃受风力和吊车转动发生失控。
eq\o\ac(○,5)在要安装玻璃处上下边框的内侧粘贴低发泡间隔方胶条,胶条的宽度与设计的胶缝宽度相同。粘贴胶条时要留出足够的注胶厚度。
(2)
玻璃就位
eq\o\ac(○,1)吊车将玻璃移近就位位置后,司机要听从指挥长的命令操纵液压微动操作杆,使玻璃对准位置徐徐靠近。
eq\o\ac(○,2)上层工人要把握好玻璃,防止玻璃在升降移位时碰撞钢架。待下层各工位工人都能把握住手动吸盘后,可将拼缝一侧的保护胶套摘去。利用吊挂电动吸盘的手动倒链将玻璃徐徐吊高,使玻璃下端超出下部边框少许。此时,下部工人要及时将玻璃轻轻拉入槽口,并用木板隔挡,防止与相邻玻璃碰撞。另外,有工人用木板依靠玻璃下端,保证在倒链慢慢下放玻璃时,玻璃能被放入到底框槽口内,要避免玻璃下端与金属槽口磕碰。
eq\o\ac(○,3)玻璃定位。安装好玻璃吊夹具,吊杆螺栓应放置在标注在钢横梁上的定位位置。反复调节杆螺栓,使玻璃提升和正确就位。第一块玻璃就位后要检查玻璃侧边的垂直度,以后就位的玻璃只需检查与已就位好的玻璃上下缝隙是否相等,且符合设计要求。
eq\o\ac(○,4)安装上部外金属夹扣后,填塞上下边框外部槽口内的泡沫塑料圆条,使安装好的玻璃有临时固定。
eq\o\ac(○,5)注密封胶
5.1所有注胶部位的玻璃和金属表面都要用丙酮或专用清洁剂擦拭干净,不能用湿布和清水擦洗,注胶部位表面必须干燥。
5.2沿胶缝位置粘贴胶带纸带,防止硅胶污染玻璃。
5.3要安排受过训练的专业注胶工施工,注胶时应内外双方同时进行,注胶要匀速、匀厚,不夹气泡。
5.4注胶后用专用工具刮胶,使胶缝呈微凹曲面。
5.5注胶工作不能在风雨天进行,防止雨水和风沙侵入胶缝。另外,注胶也不宜在低于
5
的低温条件下进行,温度太低胶液会发生流淌、延缓固化时间,甚至会影响拉伸强度。严格遵照产品说明书要求施工。
5.6耐候硅酮嵌缝胶的施工厚度应介于
3
5!
4
5mm之间,太薄的胶缝对保证密封质量和防止雨水不利。
5.7胶缝的宽度通过设计计算确定,最小宽度为
6mm,常用宽度为
8mm,对受风荷载较大或地震设防要求较高时,可采用
10mm或
12mm。
5.8结构硅酮密封胶必须在产品有效期内使用,施工验收报告要有产品证明文件和记录。
eq\o\ac(○,6)表面清洁和验收
6.1将玻璃内外表面清洗干净。
6.2再一次检查胶缝并进行必要的修补。
6.3整理施工记录和验收文件,积累经验和资料。
二、铝板幕墙施工铝板幕墙施工工艺流程图1、施工顺序:根据项目工艺要求,本工程的施工顺序为:现场清理——测量放线——龙骨定位——安装后置埋件——铝板龙骨安装——铝板面板安装——氟碳喷涂2、施工方法:(1)现场清理根据现场的实际情况进行场地清理垃圾,检查施工条件,准备施工工具,准备施工。(2)测量放线根据铝板幕墙分格大样图和标高控制点、进出口线及轴线位置,采用重锤、钢丝线、测量器具及水平仪等测量工具在主体结构上测出幕墙平面、立柱、分格及转角基准线,并用经纬仪进行调校、复测。(3)龙骨定位根据相关设计单位提供图纸和标高控制点,龙骨布置图,采用重锤、钢丝线、测量器具及水平仪等测量工具在主体结构墙面上进行龙骨定位。并使用经纬仪进行调校、复测。(4)安装后置埋件本工程是改造项目,埋件采用化学膨胀螺栓后置,化学膨胀螺栓埋件固定安装须按以下步骤进行:eq\o\ac(○,1)埋件前,先在原主体结构上开挖350*300洞口,在后置埋件安。eq\o\ac(○,2)装完成后,对后置埋板刷防水涂料进行防水处理。eq\o\ac(○,3)选用后补化学膨胀螺栓:根据设计图纸要求,选用M12后补化学膨胀螺栓eq\o\ac(○,4)钻孔:根据化学膨胀螺栓规格,选用相应的钻头,检查钻头直径。钻孔时,须严格按照膨胀螺栓钻孔工艺执行。钻孔后,须检查钻入深度、垂直度。相邻化学膨胀螺栓最小间距须符合国家规范要求。eq\o\ac(○,5)清理钻孔:钻孔后,用气吹对孔洞进行清理,吹刷要彻底干净。eq\o\ac(○,6)植入化学粘合剂:清理后,每个孔洞植入一支化学粘合剂。植入前,施工人员要检查每支化学粘合剂的包装,保证每支化学粘合剂包装不破损,粘合剂不少量。严禁将半支装的化学粘合剂植入。eq\o\ac(○,7)植入螺纹锚杆:利用电钻旋入钻孔。植入时,施工人员须注意自身防护,戴好护目镜后,才准施工。eq\o\ac(○,8)所有锚固件选用化学锚栓,全部镀锌处理。已经达到防水要求。eq\o\ac(○,9)拉拔测试要求锚固件抗拉强度达到7.5KN。(5)铝板龙骨安装eq\o\ac(○,1)钢龙骨安装前先预装钢支座,钢支座连接采用8mm钢板,钢支座的预装焊接工作从幕墙工程底部开始向上安装,钢支撑与后置埋件、龙骨之间采用满焊焊接。从铝板幕墙的底部开始向上安装,可待钢支座安装校正后开始安装龙骨。eq\o\ac(○,2)幕墙立柱的安装应符合下列要求:a.应将立柱先与连接件连接,然后连接件再与主体预埋件连接并应进行调整和固定。立柱安装标高偏差不应大于3mm,轴线前后偏差不应大于2mm,左右偏差不应大于3mm。b.相邻两根立柱安装标高偏差不大于3mm,轴线前后偏差不大于2mm,左右偏差不应大于5mm;相邻两根立柱的距离偏差不应大于2mm。eq\o\ac(○,3)铝板横梁的安装应符合下列要求:a.应将横梁两端的连接件安装在立柱的预定位置,并应安装牢固。b.相邻两根横梁的水平标高偏差不应大于1mm。eq\o\ac(○,4)铝板幕墙的灯光分布由专业灯具装饰公司提出方案及施工。我方配合灯饰公司。(6)铝板面板安装eq\o\ac(○,1)施工方法:工地安装时应该先对清图号,面板号以确认其安装位置,安装须知在外部脚手架上进行。调整间隙、水平及垂直度后,固定面板组件的上下左右折边。eq\o\ac(○,2)固定铝板:侧面采用10*6铝机制平头螺丝将面板折边固定在80*80*5立柱上,上下两边采用L10*6*2mm通长铝条固定折边并用10*6铝机制平头螺丝固定于横龙骨上。(7)铝板安装技术要求1、铝板运输过程中注意成品保护,以免损坏。2、注胶前,用清洁剂将铝板与型钢框表面清洗干净,清洁后的材料再1小时内密封,否则重新清洗。3、密封胶须注满,不能有空隙或气泡。4、清洁用擦布须及时更换以保持干净。5、应遵守标签上的说明使用溶剂,且在使用溶剂场所严禁烟火。6、注胶之前,应将密封条或防风雨胶条安放于板与钢型材之间。7、根据密封胶的使用说明,注胶宽度与注胶深度最佳尺寸比率为2(宽度):1(深度)。8、注密封胶时,用胶纸保护胶缝两侧的材料,使之不受污染。9、板安装完毕,在易受污染部位用胶纸贴盖或用塑料薄膜覆盖保护,易被划碰的部位,应设安全护栏保护。10、清洁中所使用的清洁剂应对板、胶及钢型材等材料无任何腐蚀作用。四、安全生产及文明施工的措施安全及文明施工是关系到全体施工人员生命的大事,也是直接影响到一个企业和工程成败的关键,它和质量有着同样重要地位,必须引起高度重度。安全施工和文明施工二者互为补充,密不可分。安全施工是文明施工的前提,文明施工是安全施工的保证。因此,我司在落实具体措施的时候,把二者放在同一高度,统筹考虑。1、安全管理:(1)建立从公司、分公司到施工项目文明施工、安全生产管理领导小组,建立安全管理保证体系。项目部设专职安全员一名;班组设兼职安全员。(2)建立安全生产责任制,职责明确。并做到用镜框装上,挂在办公室醒目的地方。公司与项目、项目与班组有职责明确的安全生产协议,并责任到人。(3)施工项目部制订安全教育制度。做到对所有新工人进行三级教育,教育时间不少于50小时,教育率达100%。考试合格后上岗。变换工种做到变换工种教育,经考试合格后上岗。(4)对各工种、各部们进行详细的安全技术交底,交底有记录,被交底人签字.(5)对所有特殊工种做到持证上岗,持证率100%。(6)施工项目部制订安全检查制度。对现场进行安全检查,施工项目部每时每周一次,分公司月检查一次,公司每季进行一次大检查。同时针对施工的不同部位、不同气候、节前、节后进行不定期、季节性和专项的安全检查。对检查中存在的问题做到定人、定时间、定措施整改,并按规定时间复查,同时做好记录。(7)班组建立班组安装活动制度,并有书面记录。班组每日进行安全检查,工种交接进行交接安全检查。班组在使用工具时要对工具进行安全检查,发现隐患及时消除。(8)施工项目部制订“施工现场安全管理制度”、“施工现场安全奖罚制度”、“安全纪律”。遵守安全生产“六大纪律、十不准”对违章者按规定进行严肃处理。(9)力争该项目在中不发生大小伤亡事故。若意外发生,做到及时向有关部门报告,并保护现场,抢救伤者,做好记录。并按事故“四不放过”的原则进行严肃处理。(10)施工现场设安全标志10套。围墙用大字书写安全标语。随着施工层的提高,每隔一层挂一幅大字安全标语,以增加安全生产、文明施工气氛。现场设置一图九牌。根据公司企业标准的要求增设职业道德守则牌公司质量方针目标牌。(11)施工项目部建立安全生产会议制度。基础上部每半月召开一次安全生产会议,全体职工全部参加,并做好会议记录。在会议中学习有关安全生产法规和要求、有关规章制度及各工种操作规程,使大家真正认识安全生产的重要性和搞好安全生产的必要性。2、外脚手架(1)采用落地式外脚手架,材料采用外径φ48*3.5mm钢管搭设。外脚手架搭拆有经审批的专项方案。作业人员持证上岗,验收合格后使用。(2)根据建筑物高度按规范要求外架顶部比建筑物高1.3米搭设外脚手架。严禁钢、竹混搭。严把材料质量关。(3)外脚手架立杆基础应夯实,根据现场平面尺寸,先放线。立杆间距:横向1.2米,纵向1.5米。用两只轧头锚固,钢管连接用符合要求的轧头,外架距墙0.2米。水平每隔4.5米设刚性拉结点,接结点上、下错位。脚手板用1米×1.5米,从第二步起层层铺设。外架从第二步起用标准型密目网四周全封闭围护,搭接长度大于0.4米,用二只轧头锚固,角度45°-60°,上下连续、通顺.外架顶部四角设避雷装置.底部设置良好的接地装置,接地电阻不大于4欧姆。(4)对外架总的搭设要求是横平竖直,连接牢固,底脚着实,层拖拉,设施齐全牢固,不变形,不摇晃.架体垂直偏差不大于H/200。且不大于10厘米,承载不超过270kg/m2。在外架转角处适当位置搭设“之”字形斜道,坡度不大于1/3,并设防滑条,间距30厘米,供专业人员上下用。5、严格按施工方案施工。对原材料进行严格的质量检查,特别是紧固件。所有与结构连接的预埋件,做到埋设牢固、位置正确。施工中要随时检查紧固件是否缺少和破损。严禁在施工过程中随意拆除紧固件。严格控制施工堆积层次和单位面积堆积荷载。在检查中发现失稳和松动现场要立即进行加固。3、“三宝四口”防护(1)入施工现场必须戴好安全帽,扣好帽扣,每人1顶,安全帽按工种分颜色戴好,办工室备用安全帽15项。(2)以上高处作业必须系好安全带,现场备安全带4副。(3)根据高处作业“四口”临边防护的要求,对“四边”临边的不同情况采用上中下三道防护杆。防护栏杆高度上道离地1.2米,中间道离地0.7米,下道离地0.3米,并竖向加扎脚手板.对预留洞口采用严密的封盖措施.对通道口采取搭设防护棚,棚宽大于通道口,防护棚高度3米以上,正面与两侧折边向上棚上翻1米。4、施工用电(1)根据建设部临时用电的规范要求做到有施工用电专项方案,经审批后实施。现场设三相五线制,采用电缆线,线径根据用电量的大小经专门设计计算。并根据用电做到分路架设。做到一机一闸保护和三级配电、三级保护。配电箱全部采用安全型电箱。电箱线下进下出,做到有保护套管。总配电箱、分配电箱、开关箱的动作电流符合规范要求。动力与照明线路分设。将三相五线的保护零线贯通到每个机械设备。(2)照明用二相电缆线,用绝缘子固定,电线过墙用保护套管,线径根据用电量计算而定。室内照明用日光灯,现场照明用碘钨灯。严禁使用金属碘钨灯支架。电箱熔断采用与施工用电负荷相匹配熔断丝,严禁使用铜丝。施工现场所有配电箱装配符合要求的漏电保护器。做到动力和照明线路分设。施工楼层做到层层设置分配电箱。(3)配电系统按总配电(一级)→分配电(二级)→开关箱(三级或末级)设置,并实行两级漏电保护。末级箱按一机一闸一漏一箱的要求设置,闸具、熔断器参数与设备容具相匹配,开关箱的触电保护器规格与施工机具配套,一般机具先用≤30mA的触电动作电流,插入振动器或平板振动器、潜水泵、水磨石机及各种手持式电动机具等运用电流≤15mA的触电动作电流,额定漏电动作时间小于0.1S。箱内装设电源隔离开关。(4)配电箱做好防漏措施,门锁齐全,箱体喷涂相关标志,各级箱体进行统一编号,箱内线路按用途进行标记,箱内张贴电气线路图和检查维修记录表。(5)配电箱引入、引出箱体采用套管,进出电线确保整齐并从箱体底部进入,杜绝使用绝缘差、老化和破皮的电线。(6)做好钢管脚手架、龙门架、塔吊等的防雷接地及设备的接零保护,并做好接地电阻值测试。(7)手持照明灯具、潮湿场所以及金属容器内的照明,均采用36V安全电压,照明灯具的金属外壳做好接零保护,照明专用回路设漏电保护。(8)室外灯具距地面不少于3m,室内灯具不少于2.4m。5、施工机具现场有机械设备保养、维修制度。配备专职机械管理人员。所有机械设备做到三级配电三级保护,一机一闸一保护。主要设备由专人操作,作业人员持证上岗。设备做到由机械管理员统一管理,发现毛病及时维修。对机械设备做到勤保养。做到清洁、干净,机械状况良好,防护设施齐全。气焊瓶管理,做到分开存放,作业时气瓶与乙炔发生器相距5米以上,离焊点10米以上,持证上岗。6、安全施工措施(1)一般规定eq\o\ac(○,1)公司在施工现场设安全员,负责落实有关安全生产的规章制度,做好现场施工人员安全施工宣传教育,使全体施工人员真正认识安全的重要性,进入施工现场必须遵守《建筑安装工人技术规程》,自觉遵守各项安全规定和安全规章制度。eq\o\ac(○,2)特殊工程(电工、焊工)要有市级以上审批专业证书。现场电线按规定架设,绝缘橡皮线穿过道路要加套管,以免压裂触电。eq\o\ac(○,3)充分发挥“三件宝”的作用,进场前,必须穿、戴好安全帽、安全带,正确使用个人劳动保护用品。时刻检查,注意下层的物品,凡2m以上的悬空、高处作业无安全设施的必须系好安全带,扣好保险钩,确保人员的安全,在没有扶手和简易的扶手的楼梯和前台上通过时,应先试其牢固程度,靠近墙的一侧通过,2人以上共同操作前协调一致,互相配合,高空作业严禁抛材料和工具等物件。安装用吊船应按规定搭设。eq\o\ac(○,4)施工安装时,不得违章操作,遇有特殊情况,经请求有关部门领导同意后,方可施工。材料的堆放、吊运必须服从业主及土建单位的统一指挥;未经有关人员批准不得任意拆出安全设施和安全装置。eq\o\ac(○,5)施工人员均需进行身体检查,检查合格后才能参加作业。工作严禁喝酒和打闹。在使用工具前,检查其安全性能是否完好,不具备完好标准的工具严禁使用。eq\o\ac(○,6)设立工地专职安全员,专职负责安全问题,发现问题即时解决,并及时汇报。现场施工时,应严格遵守国家有关防火条例。eq\o\ac(○,7)各种电动机械设备必须有漏电保护装置和可靠安全接地方能开动使用;收工时要切断电源,并检查施工现场,清除隐患。eq\o\ac(○,8)不准穿拖鞋、高跟鞋、赤脚或赤膊进入施工现场;不准穿硬底鞋进行登高作业。(2)雨季、和台风季节的施工安全措施施工前碰上雷、雨季,必须做好预防措施,保证工程质量和安全:eq\o\ac(○,1)预先听天气预报提前做好防雨准备;eq\o\ac(○,2)大雨、暴雨不得进行室外作业;eq\o\ac(○,3)小雨天,为保证打胶质量,不得进行打胶施工,其它安装工作经同意后在确保安全的情况下才可以进行。eq\o\ac(○,4)台风天气时安排停工或者采取规定安全施工加固措施。eq\o\ac(○,5)应做好成品、半成品的保护工作。。(3)防火安全措施要求施工单位建立以项目经理为代表的消防防火领导小组,实行消防责任制,落实专人负责日常防火检查、防火督查等工作,组织人员进行消防知识培训等。认真贯彻执行“预防为主、消防结合”的工作方针。本着自防自救的原则,实行严格、科学管理。eq\o\ac(○,1)严格执行国家规定的建筑施工防火规范,贯彻预防为主原则,在施工现场及宿舍配备灭火器;eq\o\ac(○,2)不准在施工现场明火燃烧杂物和废纸;eq\o\ac(○,3)不准在宿舍、仓库、办公室内使用电饭煲、电水壶、电炉、电热杯,现场饮用水由公司提供;eq\o\ac(○,4)施工现场和办公室禁止吸烟,在宿舍内严禁在床上吸烟,吸烟者应备烟缸,烟头必须丢进烟缸;eq\o\ac(○,5)
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
评论
0/150
提交评论