1、CONTENT 目录1. 目的&范围 PURPOSE & SCOPE2. 编制依据 REFERENCE3. 施工准备 PREPARATION CONSTRUCTION4. 施工方法 CONSTRUCTION METHOD5. 人力及设备动员 MANPOWER & EQUIPMENT5.1人力计划表 MANPOWER SCHEDULE5.2工具计划表 TOOL SCHEDULE6. 质量控制 QUALITY CONTROL PLAN7. 健康、安全、保安与环境 HSSE8.附件:作业危险性分析 ATTACHED: JOB HAZARDOUS ANALYSIS目的&范围 Purpose & Sco
2、pe 本施工方案的目的用以阐释BP珠海二期PTA项目仪表控制室内盘柜基础及盘柜的安装,依靠本方案的技术要求来规范现场安装工人有序的进行现场施工工作。This method statement procedure defines the activities of installation instrument cabinet support and cabinet in the I/O room of BP ZhUHAI NO.2 PTA project, depend on technical requirements in this procedure instruct erector t
3、o properly construction in site.编制依据 References 施工管理HSE规范 Construction Management System of Safety, Health, Security and Environment Protection; 现场管理HSE规范 Field Management Procedure for Safety, Health, Security and Environment Protection;GB5003-2002 工业自动化仪表工程施工及验收规范。 Code for construction and accept
4、ance of industrial automation instrument installation (GB5003-2002)GBJ131-90 自动化仪表安装工程质量检定评定标准。 Criteria for evaluation for quality of automation instrument installation engineering(GBJ0131-90)仪表安装“价格清单”分项说明 Description of Price List Items for Instruments Installation 6092.0000.KP.1500仪表安装专用技术规格书 Sp
5、ecial Technical Specification for Instruments Installation 6092.0000.MS.1500业主提供的技术文件及现场施工图Technical documents and construction drawings supplied by main contractor.施工准备 Preparation construction 组织工程施工人员进行图纸会审,熟悉图纸和相关技术资料,对图纸和资料 有疑问的地方,必须在开工前,提前请业主设计代表予以澄清,对修改更正部分 在图纸上给予标注以避免现场错误施工。Construction staf
6、f shall be organized together to be acquainted with the drawings and relevant technical documents. If something is doubted, it must be clarified by the site Engineer before the work starts. All revised drawings should be marked to avoid complication in site installation.根据施工现场实际情况,做好施工中的用电准备。Electri
7、cal power for construction shall be provided properly in accordance with the split areas at site.根据其他专业施工情况合理安排本专业的人员、机具、材料的进现场时间及施工计划时间表。Manpower, equipments 、materials and time schedule shall be reasonably arranged to enter into site with reference to the other works.为避免材料损坏及丢失,所供材料应正确存放保管在仓库里,按照制
8、造厂的产品质量相关数据,制定材料及机械设备的维护、保养计划;并且应始终做好文明施工。Materials supplied should be kept properly in warehouse to avoid damage or loss, make and implement protection and maintenance plan of Materials 、machinery and equipment and back-feed quality information of products; Good housekeeping in the area should be d
9、one always.Construction method施工方法Cabinet support installation盘底座安装盘底座的制作材料应与图纸上一致。The material of cabinet support should be in accordance with drawing.盘底座的制作尺寸应该与图纸设计尺寸相符,其直线度允许偏差为1mm/m,当型钢底座长度大于5m时,全长允许偏差为5mm。The size of cabinet support should be in accordance with drawing demand. The linear allow
10、ance deviation is 1mm/m. When the length of support is more than 5m, the allowance deviation are 5mm.盘底座应在地面施工完成前,安装找正。Before ground construction completed, the cabinet support must be installed and aligned.盘底座的安装位置和平面位置,应与设计文件一致。The position of cabinet support installation should be in accordance w
11、ith design document.盘底座安装时,上表面应保持水平,其水平度允许偏差为1mm/m,当型钢底座长度大于5m时,全长允许偏差5mm. When installation, the surface of cabinet should keep level. The level allowance deviation is 1mm/m. If the length of support is more than 5m, the allowance deviation are 5mm.盘柜安装Cabinet installation仪表盘在搬运和安装过程中,应防止变形和油漆损坏。Du
12、ring transportation and installation, the cabinets must be avoided to distortion and painting damaged.仪表盘的安装位置应与设计图纸一致。The position of cabinets installation should be in accordance with design drawing.仪表盘之间及仪表盘与底座之间应用镀锌螺栓连接牢固。Cabinets or panel and support should be connected firmly by galvanized bol
13、t .单独的仪表盘安装,应符合下列规定: Separate cabinet installation must meet the following regulations:固定牢固 Fixed firmly垂直度允许偏差为1.5mm/m The vertical allowance deviation is 1.5mm/m水平度允许偏差为1mm/m The level allowance deviation is 1mm/m成排的仪表盘的安装,应符合4的规定外,还应符合下列规定:Group cabinets installation must meet 4 and following reg
14、ulations:同一系列规格相邻两盘的顶部高度允许偏差为2mm The top height which the same type of adjacent cabinet, the allowance deviation is 2mm当同一系列规格盘的连接处超过两处时,顶部高度允许偏差为5mm When connect point between the same type cabinet more than 2 locations, the top height allowance deviation is 5mm.相邻两盘接缝处正面的平面度允许偏差为1mm From the front
15、 face of the adjacent panels seaming, the allowance flatness error is 1mm.当仪表盘间的连接超过5处时,正面的平面度允许偏差为5mm When connect point between panels are more than 5 locations, the allowance flatness error are 5mm from front face.相邻两盘的接缝间隙,不大于2mm The gap between adjacent panels seaming no more than 2mm.接地 Ground
16、ing接地母排的材质及制作尺寸应与设计文件一致。The material and size of grounding bar should be in accordance with design document.接地母排应用绝缘支架固定在墙壁上。Use insulation support fixed the grounding bar to the wall.接地线的材质和颜色应与设计文件一致。The material and color of grounding conductor should be in accordance with design document.仪表盘内各回路
17、的各类接地,应分别由各自的接地支线引至主接地线上,由主接地线接到接地母排。Due to all kinds of grounding conductor inside panel, from respective branch grounding connected to main grounding. Then from the main grounding connected to grounding bar.接地支线与主接地线的连接应采取压接。主接地线与接地母排的连接采用镀锌螺栓紧固。.Branch grounding and main grounding should be compr
18、essor connected. main grounding should be connected to grounding bar and fixed firmly by bolts.各接地线、接地母排之间在非连接处应彼此绝缘。 All kinds of grounding conductor and grounding bar should be insulated in the non-connect location.Manpower and Equipment mobilization 人力及设备动员5.1 Manpower schedule 人力计划表No.序号FORCES人员
19、200712341E/I Superintended电仪主管11112Inst. Engineer仪表工程师22223Inspector检查员11114HSE安全员11115Foreman班长11116Instrument仪表工22227Rigger起重工11118Welder焊工11119Common普工510141410Other其它33335.2 Tools schedule设备工具计划表序号No.Description 名称Remarks备注1Weld machine电焊机/2Cutter 切割机 /3compressor clamper压接钳/4Electric hammer冲击钻
20、/5Hand electric drill手电钻 /6Electric bench drill台钻/7Trailer拖板车15t8Crane吊车30t9Level bar水准仪/质量控制 Quality Control材料要提供产品说明书,材料经抽样检测合格后方可投入施工。Materials shall be furnished with product certificates. Re-test of material samples shall be passed before construction. 施工过程须严格按照图纸、澄清文件及现行的施工规范与标准进行。The drawings
21、, clarifications, modern standard and construction specifications shall be complied with stringently. 建立并健全完整的质量责任管理体系,提高全体管理人员和工人的质量意识。Quality Management System and Management Responsibility System shall be established and improved, and increasing quality consciousness of staff management and worke
22、rs. 为消除质量通病,应及时向质量经理汇报质量信息。Quality information shall be feed back to quality manager in time so as to uproot the potential incidents. 调试设备在投入使用前,须将其检测报告及检验申请送至CFCS监理及 IPMT主管处以供检查。Testing equipments shall be sent application for inspection with checking reports to IPMT and CFCS supervisor before construction. 健康、安全、保安与环境 HSSE正确配戴个人防护品 安全帽:安全眼睛、手套、安全鞋、安全帽、安全带等Wear correct PPE: safety glasses, gloves, safety shoes, safety helmet, harness etc. No smoking
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 二零二五年度购车环保补贴申请合同3篇
- 二零二五版电子商务支付平台跨境支付合规审查合同3篇
- 二零二五年货车驾驶员驾驶技能考核及评价合同3篇
- 二零二五版房产抵押合同变更及合同履行监督协议6篇
- 二零二五版酒店物业管理安保保洁服务全面承包合同3篇
- 二零二五版高空作业安全协议书-高空雨棚安全检测与维护合同3篇
- 二零二五年度空压机租赁与能源管理优化合同3篇
- 二零二五版人工智能企业股权整合与行业应用开发合同3篇
- 二零二五年度会议礼品定制及赠送服务合同范本3篇
- 二零二五年度特种防盗门制造与销售承揽合同范本3篇
- 2020小升初复习-小升初英语总复习题型专题训练-完形填空15篇
- 2023年浙江省公务员考试面试真题解析
- GB/T 5796.3-2022梯形螺纹第3部分:基本尺寸
- GB/T 16407-2006声学医用体外压力脉冲碎石机的声场特性和测量
- 简洁蓝色科技商业PPT模板
- 钱素云先进事迹学习心得体会
- 道路客运车辆安全检查表
- 宋晓峰辣目洋子小品《来啦老妹儿》剧本台词手稿
- 附录C(资料性)消防安全评估记录表示例
- 噪音检测记录表
- 推荐系统之协同过滤算法
评论
0/150
提交评论