版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
工程施工组织设计编制:项目经理:审核:二0一二年八月目录一、编制原则及根据··················································41、编制根据·························································42、编制原则·························································43、编制目·························································5二、工程概述························································61、工程概况·························································52、地形地貌特性·····················································63、地基土层构造特性·················································64、工程特点·······················································65、总体布置·························································6三、开工前准备······················································8四、主工作坑施工及顶管准备··········································81、顶进主工作坑施工·················································82、工作坑后背砼墙··················································103、减小阻力办法····················································104、钢筋混凝土接口··················································105、顶管工作井设备安装··············································11五、顶进作业·······················································12六、重要施工机械进场筹划···········································13七、工期及劳动力投入筹划···········································14八、质量保证体系及质量保证办法·····································15(一)质量目的·····················································16(二)质量保证体系·················································16(三)质量保证控制要点·············································17九、施工机械设备维修办法···········································18十、安全生产办法···················································18十一、文明施工办法·················································19十二、雨季施工办法·················································20十三、施工组织机构·················································201、施工组织·······················································202、项目经理部重要人员职责·········································21一、编制原则及根据1、编制根据1.1施工图。1.2地质勘测资料。1.3国家现行施工技术规范、验收原则及质量、安全技术规程等:《建筑桩基技术规范》JGJ94-94《建筑基坑支护技术规范》JGJ120-99《建筑抗震设计规范》GB050011-《建筑构造荷载规范》GB50009-《地下工程防水技术规范》GB50108-《市政排水管道工程质量检查评估原则》CJJ3-90《建筑施工安全检查原则》JGJ59-991.4通过阅读图纸及现场勘查所得到工地自然条件、地区资源条件资料。1.5我单位综合施工能力及近年来参加类似工程经验。1.6劳动力、材料、机具设备消耗定额。1.7我公司人员、机械设备配备以及经济技术实力状况。2、编制原则2.1以设计图为主导,通过合理选取,制定施工组织方案、技术工艺办法等切实可行。施工工艺与设计规定相符,并达到完备、先进、可行。2.2采用先进工法施工。施工工序进度安排、作业循环设计等尽量达到安全、优质、高效。提高施工机械化限度,减少施工成本,提高劳动生产率,减轻劳动强度,统筹安排、均衡生产。2.3组织专业队伍进场,装备足够机械设备进行专业化施工,施工设备、人员及技术配备尽量合理,并留有一定贮存量,保证在规定工期内完毕施工任务并力求提前。2.4遵守施工规范和操作规程及国家关于质量、安全生产规程,严格执行业主和监理工程师指令,保证工程质量与施工安全。2.5开源节流,精打细算,贯彻就地取材原则,尽量运用本地资源,充分运用已有设施,尽量减少暂时工程,减少工程成本,提高经济效益。2.6遵守环保法并切实按关于规定和规定来组织实行。2.7严格按ISO9001:国际质量认证体系和项目法施工规定进行施工管理和质量控制,建立健全质量保证体系,强化施工安全技术组织办法,使各项工作落到实处,为本工程施工顺利、高效进行创造良好条件。3、编制目3.1本着对工程质量负责原则,优质、迅速、高效、低耗地顺利建成所有施工任务;3.2本着忠实于业主、服务于业主地精神,在施工过程中全面履行施工承包合同,兑现予以业主全面承诺;3.3为我公司工程管理、控制部门提供施工资料,使本项目生产、管理状况与公司关于部门保持密切联系,完全按照ISO9001质量认证模式运作,使工程现场施工生产始终处在受控状态;3.4为施工现场提供切实可行施工技术方案以及质量、安全、环保施工技术办法。二、工程概述1、工程概况2、地形地貌特性3、地基土层构造特性甲方提供勘探资料,施工穿越管道宜在粘土层中均有分布。4、工程特点4.1施工工期短,施工质量规定高。5、总体布置5.1施工指引原则⑴施工方案选取及设备选型以满足施工安全、质量、进度、文明施工为前提。⑵施工场地应尽量运用空地施工。⑶尽量避免或减少对道路交通影响,保证工作坑周边土层稳定、施工过程安全及后来运营工作安全。⑷在施工中必要认真执行“四个及时”,即及时支护、及时检测、及时反馈、及时修改。⑸严格控制洞身超欠挖,这是保证施工质量、控制工程成本核心,也是顶管掘进施工重点。5.2施工办法及施工顺序⑴工作坑工作坑采用人工挖孔桩砖护壁支护构造,分级开挖、坑壁采用砖砌墙进行支护,本次顶管穿越施工共设1个顶进工作坑。顶管工作坑开挖深度依照排水管道管底深度计算。⑵洞内掘进采用全断面开挖法施工,开挖时采用人工挖掘。⑶洞内出土采用无轨运送,洞内人工装土,小斗车运出洞外,再用提高架吊出工作坑外。⑷施工顺序施工准备施工准备工作坑开挖支护设备安装调试安装砼管控制测量挖土掘进通风运土垂直运送弃土顶进纠偏加顶铁停顶推程5.3施工难点和对策在整个施工过程中,测量控向是本工程技术要点和难点,本工程通过在顶管前端和最后端管内顶部标注顶进中心轴线标尺,并用经纬仪来测量每一节砼管左右偏差,认真做好顶进测量记录,作为下一节砼管顶进时纠偏根据。本项目贯彻后,公司筹划由顶管专业队负责该工程施工,迅速展开下列各项施工准备工作:成立专门测量小组及时测量、观测工具头等结合各项反馈数据,及时进行分析、指引施工,及时采用有效办法防止各种不利因素对工程影响,以保证施工办法科学可靠及全过程施工安全;依照现场资料,及时调节工具管操作状态,保证施工顺利进行;针对地下障碍物状况,采用办法提前制定解决预案。5.4总体工期安排由于本工程施工工期较紧和工程量较大特点,采用全线开工,流水作业施工办法,在规定工期内完毕合同内所有工作量。三、开工前准备1、进行施工测量和现场放线工作。
2、拟定管线范畴内及施工需用场地内所有障碍物,如管线、电线杆、树木及附近房屋等精确位置。3、按施工平面布置图修建暂时设施,安装暂时水、电线路,并试水、试电。
4、进行顶管所用设备加工制作。
5、依照顶进长度,准备好各类管线和所需辅助物(固定架等)。
6、顶管所用管材订货,施工机械设备工具检修完好准备进场。对施工人员进行技术交底。对工程质量目的及安全进行认真教诲。8、电源:需总容量为30KVA,搭设暂时设施及施工所需准备工作(含防雨棚1座)。四、主工作坑施工及顶管准备1、主付工作坑施工1.1依照顶管位置,为保证主付工作坑绝对安全,拟采用人工挖孔桩方式支护主付工作坑,即边人工挖土边砌筑24CM简力墙形成圆拱型砌体支护土体。该工艺施工场地规定低,施工难度较小,简力墙形成圆拱型砌体强度大,抗渗能力高。工艺也较为成熟,在我公司各种深基坑施工作业中起到核心作用。主工作坑共有4个,尺寸分别为:第一段φ=4.5m、深4.8m;第二段φ=3.0m、深3.8m;第三段第四段共用一种主工作坑φ=3.0m、深3.81.2、工作坑内排水系统1.2.1坑内降水井:在工作坑内渗水量大一角开挖Ø300×500降水井(兼作积水井),降水井内安装一台2.2kw扬程20m以上潜水泵抽水,降水井用盖板封口,只有在维修水泵时候才可以打开。1.2.2坑底盲沟排水系统:工作坑开挖到设计标高时,坑底挖成偏锅底状向降水井坡水,其上填筑20cm厚碎石,碎石含泥量不大于3%,碎石顶面铺平后再铺设隔离带(油毛毡三层或防水塑料布二层)防止地下水上升,制止浇筑底板素砼垫层水泥浆流进碎石层中堵塞盲沟通道,在隔离层上浇C25素砼垫层3盲沟排水系统长处是地下水和洞内渗水从盲沟排到降水井,然后从降水井集中排出坑外,地下水不会倒渗出来,工作坑内能始终保持干燥。1.2.3在工作坑井口周边砌筑240×200挡水墙,防止雨水倒灌进工作坑内,并在工作坑上方搭盖防雨棚,防止雨水进入工作坑。1.2.4工作坑平面布置图2、工作坑后背砼墙:为使顶管反力均匀传递到后背墙及土体,保证顶进顺利无误,后靠背压力均匀,必要严格按设计施工,钢筋摆放位置严格精确,受力面必要表面平整垂直并与顶管中线垂直,与简力墙接触面用油毡隔离以利拔桩,砼后背墙必要达到100%强度方可使用。后背砼墙规格为:3米×2米×0.6米,内置φ后背墙承载力计算最大顶力:P=66t后背抵抗力:N=[σ0]×S=15.3t/m2×6m2=91.8其中:[σ0]——该土层地基承载力特性值:150KPaS——后背墙承载力面积,3m×2m稳定系数:KJ=N/P=1.4,达到规范规定最小稳定系数。3、减小阻力办法:在顶进施工时采用触变泥浆施工技术减小阻力和填充缝隙,边顶进边通过注浆孔注入触变泥浆,同步在水泥套管外涂黄油或机油等方式润滑减阻。4、钢筋混凝土管接口采用钢外套环连接。管节接口重要由宽600毫米、厚6毫米外套环(钢套环)橡胶止水带和软土衬垫构成。钢套环在加工处至现场运送吊装过程中不能变形,接口不损坏,以保证管节在对接过程中,橡胶带不移位、不翻转,保证管节密封性。同步,钢环套在进场前还必要做好防腐解决。橡胶止水带应保持清洁、无油污,并存储在阴暗处,防止老化。施工中,将橡胶止水带用强力胶水粘贴于混凝土管口凹槽处,并粘贴牢固,在管节对接前涂无腐蚀性润滑油以减少摩阻,防止止水带翻转、移位和断裂。软木衬垫采用多层胶合板(厚度1cm左右),将其夹于先后管节钢套环间,以均匀管节间互相作用力,减少接口损坏。管道顶通后,管道须作内接口解决,将管节间胶合板凿至同样深度(深度2~3cm即可),并用沥青弹性嵌缝膏或水泥砂浆抹平。5、顶管工作井内设备安装
5.1导轨安装。严格控制导轨中心位置和高程,保证顶入管节中心及高程能符合设计规定。
5.1.1由于工作井底板浇注了30cm砼,地基稳定,导轨直接放置在工作井底板上。
5.1.2严格控制导轨顶面高程,其纵坡与管道纵坡一致。
5.1.3导轨采用浇注砼予以固定,导轨长度采用2~3m,间距设立为60cm。
5.1.45.2下管、顶进、出土和挖土设备:
采用电动卷扬机下管,用千斤顶、高压油泵作为顶进设备,用斗车、垂直牵引卷扬机作为出土设备,用空气压缩机带风镐机作为挖土设备。
5.3照明设备:井内使用电压不不不大于12V低压照明。
5.4通风设备:人工挖土前和挖土过程中,采用轴流鼓风机通过通风管进行送风。五、顶进作业①顶力计算依照经验公式:P=K粘(22D1-10)L=1.2*(22*1.2-10)*33=649KN=66t式中:K粘-系数,粘土类取值范畴1.0-1.3,取1.2;。D1-管道外径(M):1.2L-管道计算顶进长度(M):33依照计算最大顶力66t。选用100t液压千斤顶1台,高压油泵(32Mpa)1台。100t千斤顶在工作坑内沿顶管中心线布置。②顶进施工程序:(在所有顶管设备安放好,复侧无误后)吊车将第一节d1000管安放工作坑导向轨上,管前端安装钢刃角。人工掏土作业300mm→启动高压油泵,千斤顶工作→管道顶入土内300mm停止顶进,进行人工掏土作业,到管前端钢刃角边止→启动高压油泵再顶进300mm→人工再掏土,以上操作重复进行,最后达到所有顶完。③顶进掏土及运送:禁止超挖,人工掏土必要先上部后下部,挖土坡度不得不不大于60°。以防止塌方事故。掏土深度每次为300mm。制作专用运土斗车,每道管二台交替使用。斗车行进由卷扬机拉动。斗车装土运到工作坑内后由吊车吊到自然地面,装载机车清运到设定存土场地。④顶进质量测控:在顶管前端及最后端管内顶部标注顶进中心轴线标尺,用经纬仪测每顶一镐左右偏差变化认真作顶进测量记录;供下一镐顶进时需纠偏调节根据。先后高程测量;在每顶完一镐后,对前端进行水平测量可发现“扎头”或“昂首”问题,认真作记录,提供下一镐顶进时纠正根据。⑤顶进方向高程偏差调节:顶进方向如发生左右偏差时,采用调节管前端二侧掏土吃力状况进行纠偏,并用管前端纠偏千斤顶予以调节。在顶进中浮现“扎头”可超挖下部土,上部不挖形成力矩差达到逐渐纠正;如土质松软上述办法不明显,可先在前端超挖并将管底土挖出少量还填碎石并加垫方木以加强底部土质强度,从而纠正扎头问题。如浮现“昂首”应一方面检查管前端底下与否有硬物,如有应及早排除。如无硬物则依治理“扎头”办法采用调节掏土吃力办法调节。⑥出土洞内挖出土方采用运土小车人工运出洞外,用提高架吊到工作坑外堆放到弃土场。卷扬机提高能力验算:P=V·r=0.162×1.9=0.31t<1tP—每斗车出土重量,t;V—出土斗车容积,m3;r—土方松密度,t/m3;经计算卷扬机提高能力足够。六、重要施工机械进场筹划序号机械(具)名称型号数量序号机械(具)名称型号数量1高压油泵32mpa18机动翻斗车22汽车吊车16t19汽车13打桩机QY16010潜水泵QW-3014搅拌机111污水泵80QG25千斤顶100t112装载机16电焊机30KVA113乙块切割机17触变泥浆注浆设备114空压机风镐设备2七、工期及劳动力投入筹划工种总工期天3691215壮工机修工起重工电焊工砼工机械操作工测量员材料员汽车司机51111111114111111111411111111141111111114010011111共做好充分准备工作充分理解施工现场道路交通、立交桥施工等状况,积极和关于部门及业主联系,预先办好各种施工手续,力求早日开工。对必须工程材料、成品及半成品早日定货并检查合格,保证及时供货,杜绝停工待料现象。对各种机械和设备经常保养,保证进场施工后发挥最大工效。对设计或监理工程师交付各类中心控制桩、座标、水准点按实际需要做好攀线桩,并重复检查至对的为止。对在工程中所必须混凝土及砂浆配合比,应予先做好实验,待开工后即可申报监理工程师批准使用。2.安排足够劳动力投入施工,并还应保证突击施工人员抽调。3.精心施工,严格检查,杜绝返工,使工程顺利进行。4.做到工毕场清,减少最后清理时间。5.各类内外业资料与工程基本同步,不准弄虚作假,不准发生资料后补现象。6.合理安排机械设备和劳动力,发挥最大施工工效。7.对各种机械设备做到勤保养、勤修理,防止在使用过程中发生损坏,影响工程顺利开展。8.在施工例会上,应将本周所完毕工作量和下周施工安排上报监理工程师,并使之满意。八、质量保证体系及质量保证办法(一)质量目的:严格管理、争创优良工程。(二)质量保证体系:对于此项工程,公司质量管理部负责对工程全过程质量控制,项目经理部现场管理是核心。因而,选取懂工艺、懂技术又有实际施工经验人员担当质量员。质量管理部、施工管理部人员配合项目经理、质量员要对各施工工序上操作人员经常进行教诲,认真负责,按照规定做好本职工作,保证工程质量。如果发现质量隐患,咱们以质量体系为主体,发挥其作用,把质量隐患消灭在萌芽状态,详细做法是:质量员把现场发现质量隐患汇总上来,分析后拿出详细解决办法,尽快指引施工队伍进行改进,改进后报告给质量管理部、施工管理部及项目经理参加,质量管理部对质量隐患做出整治意见并做好纠正及防止跟踪记录。通过这样可达到现场质量监督分工明确,并且达到层层把关作用。此外,质量管理部、施工管理部也可对施工过程中发现质量隐患直接提出整治意见,项目经理部应及时纠正,质量管理部做好有关记录。(三)质量保证控制要点:1、完善质检制度,严把质检关在施工过程中实行三级检查和交接班质量签证制度。由各班组质量员对上一班工程质量进行逐渐验收,合乎规定后,签字接受。2、二个不同工种之间交接亦需要各工种质量员进行检查。各工种质量员需对本工种每道工序检查签证,并上报项目经理,经复验合格后,报监理工程师检查。公司质量主管部门对工程质量进行不定期抽查,并实现质量奖罚制度。3、为了防止此路段顶管施工完毕后,地下水渗入对管道导致侵蚀,采用宽600毫米、厚6毫米钢套环对所有管接头进行密封保护。4、切实做好施工交底工作整个工程施工过程,每个工序施工办法、规定和注意事项,都使每个职工心中有数,并积极动员和发挥全体职工经验,定期召开小组会互相交流,对施工过程中操作办法,就关于质量、安全、工程进度等方面提出合理建议。开展劳动竞赛活动,比质量、比技术、比文明施工、比安全,并由公司实现奖励。5、认真做好测试工作原材料测试成果必要符合设计规定。对钢材、管材、水泥、砂石等材料进行必要测试。凡尺寸不符、质量不符、型号不符及测试成果不合格者,禁止进场和使用。在测试工作中发现问题应及时追究因素,进行改进,不能让不合格材料用于工程建设。6、各类专职人员持证上岗各类专职及特殊工种人员必要持证上岗,并进行技术教诲和专业知识再教诲,使职工从实践中提高业务水平,为在施工中保证安全、保证质量、保证工程进度作出贡献。质量体系网络图本步工序本步工序质量员监理下步工序 报 验返否认工可否认可(四)产品标记阐明:对进场原材料在库房内存储采用卡片、标签标记,在露天存储采用(挂)立牌标记。品名规格材质生产厂家出厂日期到货日期检查成果实验成果暂时水准点、桩点均用红色铅油表达。(3)工序、部位工程在施工过程中用《工序质量评估表》进行标记。九、施工机械设备维修办法施工机械在开工前由项目经理部机管员、维修人员与操作人员共同对机械进行全面检查,如发既有故障隐患尽快维修,施工过程中做好每日收工后对机械进行检查维护。十、安全生产办法1、人员必备劳保防护设施齐全,进入施工现场必要戴安全帽,穿工作服,各种岗位配备相应安全设施。进入洞内作业,必要要有专用对讲机和洞外保持通讯联系。工作坑上挂报警铃铛。每班下井作业前,必要用“四合一”气体检测仪对管道内可燃气体CO、H2S及O2进行检测,检测成果符合规范规定才干下井施工。2、作业坑边设防护栏杆,栏杆高度为:下0.5-0.6米,上1-1.2米。护栏用φ60钢管制作,总长度约60米。工作井井口挂安全防护网,防止坑顶落石伤人。工作坑井口用槽钢做横梁,上满铺木板,只留出渣口和吊管口,出渣口和吊管口设明显标志,不用时所有封闭。3、洞内通风洞内都是人
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 二零二四年度智能语音助手研发合同
- 《小学英语教学设计》课件全套 陈冬花 第1-10章 小学英语教学设计概述-小学英语课堂管理
- 二零二四年度城市照明设计安装合同3篇
- 二零二四年度房地产项目工程设计合同5篇
- 二零二四年度设备采购合同标的设备技术规格要求4篇
- 2024年度货物供应合同with标的:00万件商品3篇
- 大于胎龄儿的临床护理
- 2024年防静电超净技术产品项目资金需求报告代可行性研究报告
- 二零二四年度金融科技产品研发与许可合同2篇
- 2024年度洛阳租房合同模板2篇
- 适用于2024年《语言学概论》课程的教案创新策略
- 中小学学校国家智慧教育云平台应用项目实施方案
- 2024-2030年中国干细胞医疗行业趋势分析及投资战略研究报告
- 湖北省武汉市六校联考2024-2025学年高二上学期11月期中英语试题(含答案含听力原文无音频)
- 2024版2024年【教案+】初中美术《铅笔淡彩》
- 网络安全管理操作手册
- 人教版小学数学六年级上册《扇形的认识》课件
- 通信工程施工方案
- 2024版《糖尿病健康宣教》课件
- 2024年湖南省永州市宁远县自来水公司招聘26人历年高频难、易错点500题模拟试题附带答案详解
- 部编人教版2022-2023学年度第一学期四年级道德与法治上册期末测试卷及答案
评论
0/150
提交评论