1、目 录一、编制说明················································
2、83;·2二、编制依据···············································
3、183;··2三、工程概况··············································&
4、#183;···2四、地面性能特点············································
5、3;·2五、测量及准备工作············································3六、施工环境要求·
6、83;············································3七、施工机械及人员配备···
7、83;····································3八、使用材料说明············
8、··································4九、施工工序···············
9、;···································4十、施工步骤·············
10、3;····································5十一、各项数据测试············
11、································6十二、施工过程控制················
12、183;···························7十三、地面养护与维护····················
13、83;·····················7十四、常见问题及解决方案··························
14、183;···········8一、编制说明:本工程环氧漆耐磨地面面积较大,施工要求较高,特编制此方案用以指导现场施工。二、编制依据:1、XXXXXXXXX建筑施工图2、甲方出具的地下车库室内装修做法表3、国家、行业现行的施工及验收规范、标准:地坪涂装材料GBT223742008环氧树脂地面涂层材料JCT 1015-2006环氧树脂自流平地面工程技术规范GBT 50589-2010建筑地面工程施工及验收规范GB502092002工程测量规范GB5002693建筑工程施工质量验收统一标准
15、GB503002001建筑施工安全检查标准(JGJ59-99)施工现场临时用电安全技术规范(JGJ46-2005)建设工程施工现场供用电安全规范(GB50194-93)4、我公司有关类似工程的施工经验总结5、业主与施工总包方签订的施工合同三、工程概况:1、本工程地面全部在地下区域内,相当于绝对标高70.30m,车库建筑面积为14259平方米。2、根据业主的要求本工程环氧漆耐磨地面为1mm厚防滑型,颜色为灰色。3、环氧耐磨地面施工范围为地下车库139轴轴段,除去XX楼地下室和XX楼地下室,以及换热站和变配电室等设备间。四、环氧漆耐磨地面的性能特点快干、止滑、耐磨、耐压、防尘、防水、防潮、防腐、耐
16、腐、无缝、易清洁、止滑抵抗力大。五、施工测量及准备工作1、标高的测量与控制根据附近建筑物,业主提供的原始水准点,将室内地坪标高的+0、500m线标高测设到每个混凝土柱子上,作为各基层的控制标高,做地坪时在两个柱子间拉线,用以控制环氧地坪上口的高度。2、地坪施工人员,材料,设备必须到达施工现场,并按分仓面积计算材料用量,预先堆放好材料。六、施工环境要求:、施工现场采用封闭施工,不允许其他工种交叉施工。可能施工周期比较长,为了不影响整个建设工期,采用分区域封闭施工。、地坪的平整度;表面含水率应小于8%,避免今后地坪起泡;、施工时场内温度宜在1030,空气湿度在80以内,在低温条件时,宜采用加热保温
17、措施,但不能直接用明火或蒸气加热。、断绝施工现场的所有不明原因的水源。保证施工现场24小时供电和照明。七、施工机械及人员配备1、地坪涂料工具和设备配置表序号名 称数 量用 途1干式地坪打磨机2混凝土地坪打磨处理2物料搅拌机2双组分环氧材料的搅拌3羊毛滚筒30面层材料的滚涂4手提式打磨机12批刮层修整打磨处理5批刮刀40批刮层批刮施工6电缆配电箱2设备工具接电2、地坪漆施工队伍人员配置表人员安排人数说明项目经理1总体安排及管理质量管理员1各工序质量监督管理搬运和搅拌2环氧材料的现场搅拌和运输批刮和滚涂42个班组4安全员1安全文明生产现场电工1设备及电路检修八、使用材料说明产品名称:环氧树脂地坪涂
18、料底涂材料:主成份:环氧树脂配 比:主剂:固化剂=1.0:1.0中涂材料:主成份:环氧树脂 配 比:主剂:固化剂=1.0:1.0硬骨材料:主成份:石英粉、石英砂 配 比:依使用情况与中涂材料配合比例面涂材料:主成份:环氧树脂 配 比:主剂:固化剂=2.0:1.0九、施工工序1、混凝土基层面:平整度2mm/2M,强度20MPa,清扫、吸尘、表面应平整、干燥、无杂质、油污、松散物,含水率不高于8%。2、环氧底漆:双组份混合环氧树脂底漆涂布于基底上,组合好的底漆材料须在1小时内使用完毕,可用滚涂或刮片均匀滚涂施工至少一遍封闭底漆,厚度在0.1mm。使它渗透至混凝土内部,可坚固基底并防止使用过程中环氧
19、地坪与混凝土出现层间分离。3、环氧中涂砂浆层:在环氧树脂耐磨漆中,按比例加入高度石英砂粉搅拌均匀至无结团存在,调成较稀即可批刮地面二遍,填平砂眼,厚底0.3mm。组合好的中涂材料须在1小时内使用完。石英砂用量随着道数的增加而逐渐减少,或者选用细号砂。加大找平层和耐磨度,使地面更加平整和耐磨。4、环氧中涂腻子层:先按照比例配制材料,然后加入环氧树脂腻子粉搅拌均匀,然后按比例加入固化剂,调成较稀的腻子,即可满刮地面二遍,厚底0.4mm。组合好的中涂材料须在1小时内使用完。固化后,打磨平,清除表面浮尘,目的使其平整。增加表面的附着力和平整度以及耐冲击性。5、环氧防滑层面涂:依照正确的比例将色剂及固化
20、剂混合充分搅拌均匀,使用滚筒或刮板将材料均匀涂布面层二遍,厚度在0.2mm,混合材料需在30分钟内施工完毕,滚涂面层时使其表面平整无色差。压花型:用环氧树脂及固化剂按比例混合好,再加入一定量的粉搅匀。一人用带“”形齿的泥刀铺开物料,然后另一人用压花滚筒在地坪上来回滚动,即可。6、环氧面层收光:根据地坪的硬化情况,利用收光作业。地坪收光完毕,进行薄膜养护或进行专业清洁打蜡,可使地面防尘防水、耐磨耐腐蚀、易清洁。具有明显装饰和保护效果。十、施工步骤图例环氧砂浆止滑地坪涂装图示:-环氧面涂层-环氧腻子层-环氧中涂砂浆层-环氧底涂层-基层处理(研磨及吸尘)底层环氧面涂 环氧底涂层环氧面层 环氧腻子层
21、环氧砂浆层十一、施工环境的各项数据测试地下车库环氧耐磨地坪技术指标项目指标表干时间(h)4实干时间(h)24硬度(擦伤)2H耐磨性(750g/500r)/g0.029耐水性 (168h)无变化耐油性 (120汽油,168h)无变化耐碱性(10% NaOH,48h)无变化耐酸性(10% H2SO4,48h)无变化抗伸度Mpa7抗弯强度7.0抗压强度Na粘接强度/MpaNa柔韧性 (mm)通过耐冲击性(1kg/cm)1级耐污性(%)按K29-4387标准11防滑性(干湿摩擦系数)按K29-5673标准0.75 产品及涂层技术指标:容器中状态涂-杯粘度,s不挥发物含量 干燥时间(h)附着力,级硬度耐
22、冲击性Kg.cm表干实干甲透明微黄乙彩色 甲:1030乙:100442420.6550耐变曲性mm耐磨性,g750g/500转失重耐热性150耐水性耐盐水3%耐H2SO410%耐10%NaOH耐汽油120#耐润滑油1mm通过<0.022h无变化H无变化48h无变化55天无变化55天无变化55天无变化55天无变化55天无变化以上数据为厂家提供的产品质量监督检验站检测结果,全项符合标准。十二、施工过程控制:1、严格执行施工计划、进度、工法、用量等方案;2、有专人负责配料,确保配料的准确性;3、两种材料混合后严格执行搅拌时间;4、在大面积施工前对材料用量和施工人员的手法进行统一调试;先做小样,
23、确认效果符合质量要求后再大面积施工,避免因环境条件变化产生质量问题而造成的较大损失。5、每道工序施工完毕,由技术工程师负责检测是否达到技术要求,以决定是否可以进行下一道工序的施工以及进行下一道工序施工的时间;6、对分区分段施工的接茬位置,严格控制平整度;做好工程施工完毕后的现场清理清洁、封闭、维护、交接工作。十三、环氧树脂涂料地面保养与维护为能保持地面良好的质量状态,在施工结束后进行如下保养及维护:1、当地坪涂料施工完毕后,48小时内人员不得进入,七天后方可重压;2、养护期间,不能有水或各类溶液浸入,并须加强通风设备及防火措施;3、地坪使用时,不准穿有铁钉和沙粒的皮鞋在上面行走;4、一切工作器
24、具都须有固定专用车架安放,严禁带有锐角的金属零件等物件碰撞地面,造成地面涂料损坏;5、有重物撞击或锐利物刮擦的区域须安置橡胶板等保护,搬运车要用橡胶轮胎;安装设备等重大物件须用起重机械时,在接触地面的支撑点应有厚橡皮等软件材料垫妥铺满使用区域,严禁用铁管等金属在地面上接拖设备;6、进行电焊等高温作业时,在电焊火花飞溅到的地方应用耐火材料辅垫好,以防烧坏涂料;7、地坪溅溢有酸、碱、盐及油污时,应立即用水清洗,并擦试干净。8、一旦地坪有损坏,及时使用涂料修补,以免油污通过损坏处渗透到水泥里,造成大面积涂料脱落;9、日常清扫用柔软扫帚或抹布清洁;10、大面积清洗地面时,不能用强化学溶剂(二甲苯、香蕉水等),一般使用中性洗涤剂、肥皂液、清水等,用清洗机
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。