白庙大桥架桥机拆除方案_第1页
白庙大桥架桥机拆除方案_第2页
白庙大桥架桥机拆除方案_第3页
白庙大桥架桥机拆除方案_第4页
白庙大桥架桥机拆除方案_第5页
已阅读5页,还剩3页未读 继续免费阅读

下载本文档

版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领

文档简介

1、四、架桥机拆除施工 Dismantle of Beam Setter五、HES管理措施 HES Management Measures六、环境保护措施 Environment Protection Measure七、拆除工作安全技术保证措施 Safety Measure5、梁场施工现场、周边环境、设备资源情况;5. Construction site, surrounding environment and equipment allocation. 6、起重设备安装工程施工验收规范、建筑机械使用安全技术规程。6. Construction Acceptance Code of Lifting

2、 Equipment Installation; Technical Regulation of Safe Utilization of Constructional Machinery 3、白庙大桥架桥机现已完成主臂的拼装,但由于整体拼装完成后不能满足CDB对机械设备的验收要求,要求对已经架设的架桥机全部拆除,并清运出场。4、已拼装的架桥机由贝雷梁片拼装而成,总长约36米,高为3米,宽为3.2米。Assembled beam setter is consisting of multiple pieces of bailey beam. It is approximately 36m in t

3、otal, 3m high and 3.2m wide. 1、白庙大桥架桥机拆除时间计划在:2011年10月6日2011年10月15日,总计工期15天,全部拆除后统一清运出场。Dismantle time of Baimiao beam setter is planned from 6st Oct 2011 to 15th Oct 2011, namely 15 days in total. All components will be removed from site after such beam setter is fully dismantled. 2、在拆除施工作业前一天准备好所需

4、的钢丝绳、卸扣、安全带、扳手等工具,并逐一检查是否合格,如有任何问题应立即更换方能使用。Tools such as steel sling, shackle, body harness, spanner and etc shall be prepared and inspected one day prior to dismantling. In case of any problems, tool will be replaced immediately. 3、人员准备 Manpower Allocation 四、架桥机拆除施工 Beam Setter Dismantle 3、 对所有工人进

5、行安全培训,作业前必须进行安全技术交底,做好JSA分析,并确保让每个作业人员都了解可能发生的风险以及风险应对措施。Conduct safety orientation of training to all workers and safety elaboration and JSA shall be conducted prior to work in order to make every person comprehending possible risk and its mitigation measure. 4高处作业应有合格的梯子提供人员安全上下,拆除忱木、轨道时下方严禁立人。Qua

6、lified ladder should be prepared for workers at height to go up and down safely. When workers are working on demolishing the tracks and timber on top of the beams, no one is allowed to stand in such area under beams. 5、需要在贝雷梁上设置生命线,因为工人要到高空作业拆除天车轨道等工作。Set up life-line on bailey beams for workers who

7、 are going to dismantle crown block track at height. 6、在拆除连接螺栓和卡扣时应先保证吊车就位并已经提住贝雷梁以免发生侧翻造成事故。In consideration that the sequence of the demolishment, the slings should be fixed firmly and the cranes should be positioned properly and also be functioning to hold the beams before removing the connecting

8、 bolts and shackles in order to avoid the bailey beams tip over. 7、前支腿拆除时具有一定危险性,应有专人进行技术指导并专人监护下进行,安全带始终确保100%挂钩并提供合理的挂点。Since it is more dangerous to remove the front legs of the beam setter, the dismantling work shall be conducted under technical guidance and supervision and monitor of specific p

9、ersonnel. The hardness must be 100% tied off all the time and tying point shall be reasonable. 8、材料外运车辆必须经验收合格后进入,严禁超载、超高,材料捆绑时严禁有人站立在材料上进行捆绑工作。 Transporter for transferring dismantled material shall be inspected prior to mobilization. Overload and over-stack is prohibited. No one is allowed to stan

10、d rigged material to conduct any rigging work. 作业人员应正确的使用安全带,确保安全生产,高空作业时,必须拴好安全带。起重吊装指挥信号应由专门人员指挥,且应明确、准确、哨音应响亮。Lifting shall be under signal of specific personnel and whistle signal shall be clear, accurate and loud. 5、严禁超负荷起吊,作业中防吊车倾覆,危险点应设专人监护。Overloaded lifting is prohibited. To prevent tip-over of crane, some danger spots shall be monitored by specific person. 6、所有拆除操作人员须配齐证件

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论